File #: 18-0621    Version: 1 Name: CC - Approval of Final Plans and Specifications and Authorization to Publish a Notice Inviting Bids for the 2018 Pavement Rehabilitation Project, PS-005
Type: Minute Order Status: Consent Agenda
File created: 12/14/2017 In control: City Council Meeting Agenda
On agenda: 1/8/2018 Final action:
Title: CC - Approval of Final Plans and Specifications and Authorization to Publish a Notice Inviting Bids for the 2018 Pavement Rehabilitation Project, PS-005
Attachments: 1. Location Maps.pdf
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
title
CC - Approval of Final Plans and Specifications and Authorization to Publish a Notice Inviting Bids for the 2018 Pavement Rehabilitation Project, PS-005

body
Meeting Date: January 8, 2018

Contact Person/Dept: Diana Szymanski/Public Works

Phone Number: 310-253-5623

Fiscal Impact: Yes [X] No [] General Fund: Yes [X] No []

Public Hearing: [] Action Item: [] Attachments: [X]

Commission Action Required: Yes [] No [X] Date:

Public Notification: (E-Mail) Meetings and Agendas - City Council (01/03/2018);

Department Approval: Charles D. Herbertson 12/20/2017
_____________________________________________________________________


RECOMMENDATION

Staff recommends the City Council approve the final plans and specification and authorize the publication of a notice inviting bids for the 2018 Pavement Rehabilitation Project, PS-005.


BACKGROUND/DISCUSSION

Per the pavement management system recommendation and visual observation, staff has selected streets to be resurfaced with new asphalt. The scope of work generally consists of replacing two inches of deteriorated asphalt concrete with new rubberized asphalt concrete. In areas of extensive pavement failure, the asphalt section will be removed and replaced with full depth asphalt pavement. Additionally, damaged or tree uplifted curb and gutter will be replaced where necessary. The following arterial and residential streets are scheduled for resurfacing:

1. Sepulveda Bl. between Ballona Creek and Jefferson Bl./Sawtelle Bl.
2. Washington Pl. between Centinela Bl. and Grand View Bl.
3. Centinela Ave. between Washington Bl and Washington Place
4. Harter Ave. between Washington Bl and PCC pavement
5. Westwood Blvd between Ocean Drive and Cota Street
6. Fairbanks Way between Ocean Drive and Dobson Way
7. Pickford Way between Ocean Drive and Studio Drive
8. Pickford Way between Kingston Ave and Dobson Way
9. Glencoe Ave between Zanja St. and Washington ...