title
CC - (1) Award of Construction Contract to Metro Builders & Engineers Group, Ltd., as the Lowest Responsive and Responsible Bidder, in the Amount of $1,094,312, for the Construction of the Transfer Station Stormwater Diversion Project, PZ-948; and (2) Authorization for the Public Works Director/City Engineer to Approve Change Orders, in an Amount Not-to-Exceed $110,000.
body
Meeting Date: May 30, 2017
Contact Person/Dept: Lee Torres/PW Dept.
Phone Number: (310)253-6457
Fiscal Impact: Yes [X] No [] General Fund: Yes [X] No []
Public Hearing: [] Action Item: [X] Attachments: []
Commission Action Required: Yes [] No [X] Date:
Public Notification: (E-Mail) Meetings and Agendas - City Council (05/24/17);
Department Approval: Charles D. Herbertson (05/16/17)
_____________________________________________________________________
RECOMMENDATION
Staff recommends the City Council (1) approve the award of a construction contract to Metro Builders & Engineers Group, Ltd., as the lowest responsive and responsible bidder, in the amount of $1,094,312, for the construction of the Transfer Station Stormwater Diversion Project, PZ-948; and (2) authorize the Public Works Director/City Engineer to approve Change Orders, for an amount not-to-exceed $110,000, if necessary, for construction.
BACKGROUND
On January 23, 2017, City Council approved the final plans and specifications and authorized publication of a notice of inviting bids for the Transfer Station Stormwater Diversion Project, PZ948.
Public Works Environmental Programs & Operations Transfer Station Facility (Facility) functions as a transfer facility for recyclables, municipal solid waste, and organics waste collected locally from residential, commercial, and industrial properties within Culver City. The refuse and recyclables are transported from the Facility to landfills and recycling facilities and the organic material is sent to a composting f...