File #: 19-695    Version: 1 Name: GPU Consultant Teams Interviews
Type: Presentation Status: Action Item
File created: 12/14/2018 In control: City Council Meeting Agenda
On agenda: 1/24/2019 Final action:
Title: CC - Interviews with the Raimi + Associates and Interface Studio Teams for General Plan Update (GPU) Services in Response to Request for Proposals (RFP) #1802.
Attachments: 1. Att 1, Interview questions, 2. Att 2, Practical exercise prompt, 3. Att 3, Team summaries, 4. Att 4, Raimi + Associates team proposal, 5. Att 5, Raimi + Associates team Arts and Cultural Planning preliminary scope and subconsultant qualifications, 6. Att 6, Raimi + Associates team added GHG Inventory scope, 7. Att 7, Raimi + Associates team budget, 8. Att 8, Raimi + Associates team revised schedule, 9. Att 9, Interface Studio team proposal, 10. Att 10, Interface Studio team GHG Inventory scope, 11. Att 11, Interface Studio team budget, 12. Att 12, Interface Studio team schedule, 13. Att 13, RFP 1802
Related files: 20-199
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

title

CC - Interviews with the Raimi + Associates and Interface Studio Teams for General Plan Update (GPU) Services in Response to Request for Proposals (RFP) #1802.

 

 

body

Meeting Date: January 24, 2019

 

Contact Person/Dept: Ashley Hefner/CDD

 

Phone Number: (310) 253-5744

 

Fiscal Impact: No                                           General Fund: Yes

 

Public Hearing: No                      Action Item: No                                          Attachments: Yes

 

Commission Action Required: No

 

Public notification: (E-Mail) Meetings and Agendas - City Council (01/17/2019); Notify Me - Culver City News and Events, General Plan Update, and Public Notifications (01/17/2019); and City’s Social Media Accounts (various dates).

 

Department Approval: Sol Blumenfeld, Community Development Director (12/24/18)

 

 

 

RECOMMENDATION

 

Staff recommends the City Council interview the Raimi + Associates and Interface Studio teams for General Plan Update (GPU) services in response to Request for Proposals (RFP) #1802.

 

 

BACKGROUND

 

                     August 20, 2017: City Council approved issuance of GPU Request for Qualifications (RFQ) #1819

                     September 6, 2017: RFQ was issued

                     September 29, 2017: 36 submittals received in response to RFQ

                     November 16, 2017: City Council approved qualified consultants list based on submittals to RFQ

                     April 23, 2018: City Council approved issuance of GPU Request for Proposals (RFP) #1802

                     April 26, 2018: RFP was issued

                     June 21, 2018: Nine proposals received in response to RFP

                     September 6, 2018: City Council GPU Subcommittee decided to interview the four top scoring teams, based on proposal scores

                     October 18, 2018: Four top scoring teams were interviewed

                     November 6, 2018: City Council GPU Subcommittee recommended the City Council interview the two top teams, based on proposal and interview scores

 

 

DISCUSSION

 

Proposal Evaluation

The City Council GPU Subcommittee and Advance Planning staff reviewed, evaluated and scored the proposals. Cultural Affairs; Current Planning; Economic Development; Finance; Housing; Parks, Recreation and Community Services; Police; Public Works; and Transportation staff reviewed proposal excerpts relevant to their programs. Advance Planning staff reviewed the comments, which were minimal and did not change scoring.

 

The teams’ proposals were scored using this criteria:

                     Project understanding                                                                                    25 pts

                     Scope of work                                                                                                         25 pts

                     Lead firm qualifications and experience                                          15 pts

                     Project team qualifications and experience                     15 pts

                     Implementation schedule                                                                                    10 pts

                     Total                                                                                                                                                   90 pts

 

These teams’ proposals scored highest out of a possible 90 points1:

                     Raimi + Associates                                                                                                          89 pts

                     Interface Studio                                                                                                          80 pts

                     AECOM                                                                                                                               79 pts

                     PlaceWorks                                                                                                                               78 pts

 

The five other proposals scored less than 70 points including: Dialog, Team Ivy, SOM, Torti Gallas + Partners, and Arup. These teams did not move on to the interview phase.

 

City Council GPU Subcommittee/Staff Interviews

The four top scoring teams were interviewed by the following panelists2:

                     Thomas Small, Mayor and GPU Subcommittee member

                     John Nachbar, City Manager

                     Sol Blumenfeld, Director, Community Development

                     Charles Herbertson, Director, Public Works

                     Ashley Hefner, Advance Planning Manager, Community Development

                     Diana Chang, Planning Manager, Transportation

                     Brent Oltz, Advance Planning Associate, Community Development

 

Interviews were two hours long and consisted of: 10-minute presentation by consultants; 45-minute question and answer period (Attachment 1 includes questions), and an hour long practical exercise. For the exercise, a prompt distributed beforehand (Attachment 2) asked teams to facilitate an engagement activity to show how they would work through a policy response to a difficult housing or mobility challenge with the public and City representatives (role played by panelists).

 

The teams’ interviews were scored using this scale:

1.                     Did not meet expectations

2.                     Partially met expectations

3.                     Met or exceeded expectations

4.                     Outstanding achievement or ability

 

The teams’ interviews were scored using this criteria:

                     Experience

                     Project understanding and approach

                     Scope of work

                     Project management

                     Communication and engagement

                     Practical exercise

 

These teams’ interviews scored highest out of a possible 144 points:

                     Raimi + Associates                                                                                                          143.5 pts

                     Interface Studio                                                                                                          131 pts

 

The PlaceWorks and AECOM teams scored notably lower, which led to the GPU Subcommittee decision to move the Raimi + Associates and Interface Studio teams only to the City Council interview phase.

 

Added Services Requested after Interviews

 

A Greenhouse Gas (GHG) Emission Inventory is required to inform the climate adaptation and resiliency element in the GPU. The GPU RFP didn't request an inventory scope because the Public Works Department is preparing one on a separate track (funded by Southern California Edison (SCE)). After issuing the GPU RFP, Advance Planning staff realized that due to SCE funding constraints, that inventory will address energy emissions only; i.e., not land use, buildings, transportation, and industry.

 

As such, staff requested a scope and budget from the top two teams to prepare a comprehensive inventory addressing all relevant emissions. The existing environmental planning subconsultants on both teams can provide this service. The energy section of the comprehensive inventory will rely on the ‘SCE energy-only inventory’ and update as needed. Both teams’ schedules and budgets have been updated to include a GHG Inventory.

                     

During GPU Subcommittee/Staff Interviews, a recommendation from some panelists was to strengthen the Raimi team’s expertise on arts and cultural planning. The Cultural Planning Group has been added to the team and a final scope and budget3 will be presented at the interview. Attachment 5 includes a preliminary scope and subconsultant qualifications.

 

City Council Interviews

Each interview will be one hour with a half hour presentation and a half hour for questions and answers. City Council Members will hold its deliberations of the proposals until the January 28, 2019 regular meeting. Below is a snap shot of team schedules, budgets, and subconsultants. Attachment 3 includes a more detailed summary.

                                          

The Raimi + Associates team’s scope of work requires about three years to complete at a cost of $1,829,8353 and subconsultants are listed below. Attachments 4 to 8 include the proposal, information for added services discussed above, budget, and schedule.

                     ESA

                     HR&A

                     Perkins + Will

                     Nelson/Nygaard

                     Rally

                     Sherwood Design Engineers

                     The Cultural Planning Group

                     Urban Systems

                     Veronica Tam + Associates

 

The Interface Studio team’s scope of work requires about three years to complete at a cost of $1,998,241 and subconsultants are listed below. Attachments 9 to 12 include the proposal, information for added services discussed above, budget, and schedule.

                     Barry Miller

                     Circlepoint

                     Estolano Lesar

                     Fehr & Peers

                     Here LA

                     Katz & Associates

                     Ludlow Kingsley

                     Michael Baker

                     Sherwood Design Engineers

                     Stoss

                     Strategic Economics

 

NEXT STEPS

 

On January 28, 2019, City Council will:

 

1.                     Discuss January 24, 2018 GPU Services interviews;

2.                     Select, and approve a professional services agreement with, the team led by Raimi + Associates to perform General Plan Update (GPU) services in response to Request for Proposals (RFP) #1802 in an aggregate amount not to exceed $1,829,835; or

3.                     Select, and approve a professional services agreement with, the team led by Interface Studio to perform General Plan Update (GPU) services in response to Request for Proposals (RFP) #1802 in an aggregate amount not to exceed $1,998,241; and

5.                     Authorize the City Attorney to review/prepare the necessary documents; and,

6.                     Authorize the City Manager to execute such documents on behalf of the City.

 

 

FISCAL ANALYSIS

 

There is no fiscal impact associated with this item.

 

 

ATTACHMENTS

 

1.                     Interview questions

2.                     Practical exercise prompt

3.                     Top two team details

4.                     Raimi + Associates team proposal

5.                     Raimi + Associates team Arts and Cultural Planning preliminary scope and subconsultant qualifications

6.                     Raimi + Associates team GHG Inventory scope

7.                     Raimi + Associates team budget3

8.                     Raimi + Associates team schedule

9.                     Interface Studio team proposal

10.                     Interface Studio team GHG Inventory scope

11.                     Interface Studio team budget

12.                     Interface Studio team schedule

13.                     Request for Proposals #1802

 

 

NOTES

 

1.                     ‘References and satisfaction of previous clients’ is a scoring criteria in the RFP, but was not scored as only two raters actually conducted the checks. They were mostly positive and the results were shared with the GPU Subcommittee for consideration.

2.                     Vice-Mayor and GPU Subcommittee Member, Meghan Sahli-Wells, agreed to be absent from GPU Subcommittee/Staff Interviews due to scheduling conflicts. Staff briefed her afterward.

3.                     The Raimi + Associates budget does not include fees for The Cultural Planning Group, which will be presented at the Council interviews.

 

 

MOTION

 

That the City Council interview the Raimi + Associates and Interface Studio teams for General Plan Update (GPU) Services in response to Request for Proposals (RFP) #1802.