eComments During Meetings: When available, click here to submit eComments during a live meeting | Attendees must register here to attend all virtual meetings.

File #: 18-0188    Version: 1 Name:
Type: Minute Order Status: Consent Agenda
File created: 8/21/2017 In control: City Council Meeting Agenda
On agenda: 9/11/2017 Final action:
Title: CC - (1) Acceptance of Work Performed by Elecnor Belco Electric, Inc.; (2) Authorization to File a Notice of Completion; and (3) Authorization to Release the Retention Funds upon Expiration of the 35-Day Lien Period for the Construction of the Traffic Signal Left Turn Phasing and Upgrade Project, PS-003 Federal Aid Project No. HSIPL 5240(032)
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

title

CC - (1) Acceptance of Work Performed by Elecnor Belco Electric, Inc.; (2) Authorization to File a Notice of Completion; and (3) Authorization to Release the Retention Funds upon Expiration of the 35-Day Lien Period for the Construction of the Traffic Signal Left Turn Phasing and Upgrade Project, PS-003 Federal Aid Project No. HSIPL 5240(032)

 

body

Meeting Date:  September 11, 2017

 

Contact Person/Dept: Hong Wang, PW/ Engineering                     

 

Phone Number:  310.253.5604

 

Fiscal Impact:  Yes []    No []                                                                General Fund:  Yes [x]     No []

 

Public Hearing:  []          Action Item:                     []          Attachments: []   

 

Commission Action Required:     Yes []     No [x]    Date:

 

Public Notification:   (E-Mail) Meetings and Agendas - City Council (09/07/17);

 

Department Approval:  Charles D. Herbertson - Public Works Director/City Engineer (08/31/17)

_____________________________________________________________________

 

 

RECOMMENDATION

 

Staff recommends the City Council (1) accept the work performed by Elecnor Belco Electric, Inc.; (2) authorize filing a Notice of Completion; and authorize the release of the retention funds in the amount of $51,783.73 after the expiration of the 35-day lien period, for the construction of the Traffic Signal Left Turn Phasing and Upgrade Project, PS-003 Federal Aid Project No. HSIPL 5240(032).

 

 

BACKGROUND/DISCUSSION

 

In July 2013, the Public Works Department/Engineering Division submitted a competitive grant application for the Federal Highway Safety Improvement Program (HSIP) for Cycle 6. The purpose of the HSIP grant is to improve the safety of pedestrians and all roadway users.  The City was awarded a grant in the amount of $944,889 to improve safety at seven intersections by installing left-turn arrows.  The seven intersections are:

 

1. Centinela Ave./Washington Bl. (NB/SB)

2. Centinela Ave./Washington Pl. (NB/SB);

3. Duquesne Ave./Jefferson Bl. (SB);

4. Jefferson Bl./Jordan Way-Summertime Ln. (SB)

5. Jefferson Bl./Machado Rd. (EB/WB);

6. Sepulveda Bl./Washington Bl. (NB/WB);

7. Sepulveda Bl/Washington Pl. (SB/EB)

 

On May 9, 2016, the City Council awarded a construction contract to Elecnor Belco Electric, Inc. in the amount of $1,000,080 and approved $100,000 (10%) in change order authority to the Public Works Director/City Engineer.

 

Two change orders were issued and approved during the project due to unforeseen field conditions.  Several existing conduits were discovered damaged and were replaced.  The total amount of the change orders was $34,442.89 (3.4% of total construction contract).

 

The project also included the reconstruction of failed portions of Duquesne Avenue and new slurry seal from Lucerne Avenue to Jefferson Boulevard.

 

Elecnot Belco Electric, Inc., substantially completed the project in April 2017 and the final punch list was completed to the satisfaction of staff in late August 2017.

 

Construction management was performed by staff and inspection services were provided by the Nickerson Company in the amount of $67,200 under the existing City Council pre-approved on-call general civil engineering list.

 

 

FISCAL ANALYSIS

 

Project Expenditures:                                                          Amount

Construction Amount                                                                $1,000,080.00

Change Order #1                                                                                    $     11,145.61

Change Order #2                                                                                     $     23,297.28

Material Testing                                                                                     $       2,000.00

Inspection                                                                                                          $     67,200.00

Total Project Expenses                                                                $1,103,722.89

 

Available Funding                                                                                                          Amount 

PS-003 Fund 420  General Funds                                          104,978

PS-003 Fund 423  Federal HSIP Grant                                          944,889

PZ-863 Fund 418 (Residential Street

Paving Program)                                                                                                          100,000

Total budget                                                                                                          $      1,149,867

 

 

ATTACHMENTS

 

None

 

 

MOTION

 

That the City Council:

 

1.                     Accept the Work Performed by Elecnor Belco Electric, Inc. for the Construction of Traffic Signal Left Turn Phasing and Upgrade Project, PS-003 Federal Aid Project No. HSIPL 5240(032).; and,

 

2. Authorize the Public Works Director/City Engineer to execute the Notice of Completion and Submit it to the Los Angeles County Recorder’s office for recordation; and,

 

3. Authorize the release of Retention Funds in the amount of $51,785.73 to Elecnor Belco Electric, Inc., after the expiration of the 35-day lien period.