File #: 18-037    Version: 2 Name: Sully-Miller Change Order, PS-005
Type: Minute Order Status: Consent Agenda
File created: 7/11/2017 In control: City Council Meeting Agenda
On agenda: 7/24/2017 Final action:
Title: CC - Approval of an Extra Work Change Order, in the Amount of $96,000, to the Existing Contract with Sully-Miller Contracting Company for the Construction of the 2017 Pavement Rehabilitation Project, PS-005
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
title
CC - Approval of an Extra Work Change Order, in the Amount of $96,000, to the Existing Contract with Sully-Miller Contracting Company for the Construction of the 2017 Pavement Rehabilitation Project, PS-005

body
Meeting Date: July 24, 2017

Contact Person/Dept: Hong Wang/Public Works Dept.

Phone Number: 310.253.5604

Fiscal Impact: Yes [X] No [] General Fund: Yes [] No [X]

Public Hearing: [] Action Item: [] Attachments: []

Commission Action Required: Yes [] No [] Date:

Public Notification: (E-Mail) Meetings and Agendas - City Council (7/18/2017);

Department Approval: Charles D. Herbertson (07/13/17)
_____________________________________________________________________


RECOMMENDATION

Staff recommends the City Council approve an extra work change order, in the amount of $96,000, to the existing contract with Sully-Miller Contracting Company for the construction of the 2017 Pavement Rehabilitation Project, PS-005


BACKGROUND/DISCUSSION

As part of the City's current street rehabilitation project, PS-005, Buckingham Parkway from Slauson Avenue to Hannum Avenue/Buckingham Avenue is scheduled to be resurfaced. In addition, a condition of approval for the C3 project located at 5800 Bristol Parkway requires the Developer to resurface Hannum Avenue from Bristol Parkway to Uplander Way. With the City's project and C3 project, this would leave a 700 foot pavement rehabilitation gap on Hannum Ave from Uplander Way to Buckingham Parkway. Staff recommends that the City approve a change order to Sully-Miller's contract to include this segment in the PS-005 contract. The cost estimate to resurface Hannum Avenue from Uplander Way to Buckingham Parkway is approximately $96,000. The actual construction cost will be based on the original contract bid unit price.

After the pavement resurface is completed, a bike lane will be added on Hannum Avenue from Slauson Avenue to Bristol Parkway, wherever feasible.

Th...