File #: 16-981    Version: 1 Name: Acceptance of Work Performed by Southwest Pipeline and Trenchless Corp
Type: Minute Order Status: Consent Agenda
File created: 5/2/2017 In control: City Council Meeting Agenda
On agenda: 6/12/2017 Final action:
Title: (1) Acceptance of Work Performed by Southwest Pipeline and Trenchless Corp; (2) Authorization to File a Notice of Completion; and (3) Authorization to Release the Retention Funds upon Expiration of the 35-Day Lien Period, for the Construction of the Sewer Main Lining Rehabilitation Project (Phase 4)
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
title
(1) Acceptance of Work Performed by Southwest Pipeline and Trenchless Corp; (2) Authorization to File a Notice of Completion; and (3) Authorization to Release the Retention Funds upon Expiration of the 35-Day Lien Period, for the Construction of the Sewer Main Lining Rehabilitation Project (Phase 4)

body
Meeting Date: June 12, 2017

Contact Person/Dept: Hong Wang/Public Works

Phone Number: 310.253.5604

Fiscal Impact: Yes [X] No [] General Fund: Yes [] No [X]

Public Hearing: [] Action Item: [] Attachments: []

Commission Action Required: Yes [] No [] Date:

Public Notification: (E-Mail) Meetings and Agendas - City Council (06/07/17);

Department Approval: Charles D. Herbertson, Director of Public Works/City Engineer (06/1/17)
_____________________________________________________________________


RECOMMENDATION

Staff recommends the City Council (1) accept the work performed by Southwest Pipeline and Trenchless Corp; (2) authorize filing a Notice of Completion; and authorize the release of the retention funds in the amount of $206,468.76 after the expiration of the 35-day lien period, for the construction of the Sewer Main Lining Rehabilitation Project (Phases 4), PZ-906.


BACKGROUND/DISCUSSION

On December 8, 2014, the City Council awarded a contract to Southwest Pipeline and Trenchless Corp (Southwest Pipeline) to construct the Sewer Main Lining Rehabilitation Project, PZ-906 (Phase 4) in the amount of $3,141,590.00 and $627,410.35 in change order authority.

On October 22, 2015, the City Council approved Change Order No. 1 in the amount of $833,350 to install additional 460 sewer lateral to mainline connection 'top hat' trenchless lateral sealing and authorized change order contingency of $627,410 ($340,000 for additional 200 top hats and remaining $287,411 for unforeseen conditions).

Southwest Pipeline substantially completed both projects and the change orders in late 2016 and the final punch...