CC - Approval of Professional Services Agreements with (1) McCain Inc. for the Adaptive Traffic Control System (ATCS) Project, PL-005 in an Amount Not-to-Exceed $2,016,885 ($1,831,885 Base Cost with a 10% Contingency of $185,000); and 2) Advantec Consulting Engineers for System Manager and Construction Management and Inspection Services in an Amount Not-to-Exceed $160,420.
body
Meeting Date: 09/12/2016
Contact Person/Dept: Hong Wang, Public Works/Engineering
Phone Number: 310.253.5604
Fiscal Impact: Yes [X] No [] General Fund: Yes [x] No []
Public Hearing: [] Action Item: [] Attachments: []
Commission Action Required: Yes [] No [X] Date:
Public Notification: (E-Mail) Meetings and Agendas - City Council (09/07/2016); McCain Inc., Rhythm Engineering (09/07/2016);
Department Approval: Charles D. Herbertson (08/29/16)
______________________________________________________________________
RECOMMENDATION
Staff recommends the City Council approve professional services agreements with (1) McCain Inc. for the Adaptive Traffic Control System (ATCS) Project, PL-005 in an amount not-to-exceed $2,016,885 ($1,831,885 base cost with a 10% contingency of $185,000); and (2) Advantec Consulting Engineers for system manager and construction management and inspection services for PL-005 in an amount not-to-exceed $160,420.
BACKGROUND
Culver City is one of the main transportation hubs in the region with major arterial streets such as Washington Boulevard, Culver Boulevard, Sepulveda Boulevard, Jefferson Boulevard, and Slauson Avenue. It is also in close proximity to major freeways, I-10 to the north and I-405 to the west. Currently, the City is experiencing traffic congestion due to increased regional and local traffic. Regional traffic originates from vehicles using local arterial streets to access surrounding areas as well as to bypass the congested freeway network. Local arterials are among the busiest in th...