Meeting Date: August 8, 2016
Contact Person/Dept: Todd Tipton/CDD
Phone Number: (310) 253-5783
Fiscal Impact: Yes [] No [X] General Fund: Yes [] No [X]
Public Hearing: [] Action Item: [] Attachments: Yes [X] No []
Commission Action Required: Yes [] No [X]
Public Notification: (E-Mail) Meetings and Agendas - City Council (08/02/2016); Chamber of Commerce (08/02/2016).
Department Approval: Sol Blumenfeld (07/29/16)
______________________________________________________________________
RECOMMENDATION:
Staff recommends the City Council (1) discuss a potential amendment to Culver City Municipal Code (CCMC) Section 9.07.035 to allow for the limited expansion of construction hours under certain circumstances, as authorized by permit; and (2) direct the City Manager as deemed appropriate. [Note, this item has been placed on the agenda pursuant to a request from IDS Real Estate Group (Attachment No. 1).]
BACKGROUND:
On July 6, 2016, IDS Real Estate Group (IDS) submitted a request to pour concrete between the hours of 4:00 a.m. and 8:00 a.m. beginning August 1, 2016 and ending on December 16, 2016. IDS is constructing a new approximate 280,000 square foot creative office building and an approximate 990 space parking structure (Project) at 5800 Bristol Parkway (Site). The Project is called C3 and will be constructed primarily of concrete.
Due to the amount of concrete being poured, IDS believes the 4:00 a.m. start time will:
* Allow concrete trucks to arrive on site largely before peak travel periods thus reducing the Project's traffic impacts;
* Reduce the potential of concrete "spoiling" in the ...