eComments During Meetings: When available, click here to submit eComments during a live meeting | Attendees must register here to attend all virtual meetings.

File #: 24-808    Version: 1 Name: Main St Change Orders
Type: Minute Order Status: Consent Agenda
File created: 3/1/2024 In control: City Council Meeting Agenda
On agenda: 3/18/2024 Final action:
Title: CC - CONSENT ITEM: (1) Approval of an Amendment to the Existing Construction Contract with Concept Consultant Inc. for the Main Street Bollards Project, CIP No. PS-023 for a Total Contract Amount Not-to-Exceed $426,898; and (2) FOUR-FIFTHS VOTE REQUIREMENT: Approval of a Proposed Budget Amendment Appropriating an Additional $83,673 from General Fund Unassigned Fund Balance to Cover the Additional Project Costs.
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
title
CC - CONSENT ITEM: (1) Approval of an Amendment to the Existing Construction Contract with Concept Consultant Inc. for the Main Street Bollards Project, CIP No. PS-023 for a Total Contract Amount Not-to-Exceed $426,898; and (2) FOUR-FIFTHS VOTE REQUIREMENT: Approval of a Proposed Budget Amendment Appropriating an Additional $83,673 from General Fund Unassigned Fund Balance to Cover the Additional Project Costs.

body
Meeting Date: March 18, 2024

Contact Person/Dept.: Andrew Maximous/Public Works

Phone Number: (310) 253-5628

Fiscal Impact: Yes [X] No [ ] General Fund: Yes [X] No [ ]

Attachments: Yes [ ] No [X]

Public Notification: (E-Mail) Meetings and Agendas - City Council (03/13/2024)

Department Approval: Yanni Demitri, Public Works Director/City Engineer (03/07/2024)
______________________________________________________________________


RECOMMENDATION

Staff recommends the City Council (1) approve an amendment to the existing construction contract with Concept Consultant Inc. for the Main Street Bollards Project, CIP No. PS-023 for a total contract amount not-to-exceed $426,898; (2) approve a proposed budget amendment appropriating an additional $83,673 from General Fund Unassigned Fund Balance to cover the additional project costs.


BACKGROUND/DISCUSSION

On May 22, 2023, the City Council authorized a construction contract with Concept Consultant Inc. for the Main Street Bollards Project. Construction of the project began in August 2023.

During construction, the contractor encountered several unforeseen conditions that were not a part of the contractor's original bid. These conditions include a thicker roadway pavement section, drainage, conduits and wiring, additional striping, and constructing a temporary ADA ramp. The contractor submitted five (5) change orders totaling $115,953 and a credit of $1,080. The original contract amount was $312,025 plus a contingency amount of $31,200 for a total contract amount...

Click here for full text