eComments During Meetings: When available, click here to submit eComments during a live meeting | Attendees must register here to attend all virtual meetings.

File #: 24-141    Version: 1 Name:
Type: Minute Order Status: Consent Agenda
File created: 7/31/2023 In control: City Council Meeting Agenda
On agenda: 8/14/2023 Final action:
Title: CC- CONSENT ITEM: Approval of an Amendment to the Existing Professional Services Agreement with KOA Corporation, in an Amount Not-to-Exceed $38,112 for Additional Construction Management Services on City Owned Property at 3860 and 3900 Sepulveda Boulevard.
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
title
CC- CONSENT ITEM: Approval of an Amendment to the Existing Professional Services Agreement with KOA Corporation, in an Amount Not-to-Exceed $38,112 for Additional Construction Management Services on City Owned Property at 3860 and 3900 Sepulveda Boulevard.
body
Meeting Date: August 14, 2023
Contact Person/Dept: Elaine Warner / Office of Economic and Cultural Development
Tevis Barnes/ Housing and Human Services Department

Phone Number: (310) 253 - 5777
(310) 253 - 5782

Fiscal Impact: Yes [X] No [] General Fund: Yes [X] No []
Attachments: Yes [] No [X]
Commission Action Required: Yes [] No [X]
Public Notification: (E-Mail) Meetings and Agendas - City Council (08/09/2023)
Department Approval: Jesse Mays, Assistant City Manager (08/08/2023)
______________________________________________________________________


RECOMMENDATION

Staff recommends the City Council approve an amendment to the existing professional services agreement with KOA Corporation in an amount not-to-exceed $38,112 for additional construction management services on City owned property at 3860 and 3900 Sepulveda Boulevard.


BACKGROUND

The City of Culver City acquired the one- and two-story motel structures, one at 3868 Sepulveda Blvd. (Deano's Motel), and an adjoining facility at 3900 Sepulveda Blvd. (Sunburst Spa and Suites), both located in the City of Culver City, for reuse as interim and permanent supportive housing as part of Project Homekey. Construction began in October 2022, and KOA has been actively involved in the construction of the project, supervising and verifying the work of the contractor, sub-contractors, and project schedule. In February 2023, an amendment to the agreement with KOA was approved for extended services until July 2023.


DISCUSSION

The project has encountered delays due to electrical design and equipment relative to the switchgear assembly at both sites. There are a number of smaller "punch list"...