File #: 15-383    Version: 2 Subject:
Type: Resolution Status: Consent Agenda
In control: City Council Meeting Agenda
On agenda: 11/9/2015 Final action:
Title: CC - Adoption of a Resolution Approving an Encroachment Agreement with Sunesys for Fiber Optic Telecommunication Cable in the Public Right-of-Way on Jefferson Boulevard near Leahy Street.
Attachments: 1. 15-11-09__PW-ENG_CITY COUNCIL__SUNESYS__Jefferson-Leahy__Encroachment Agreement__Attachment (2).pdf, 2. 15-11-09__PW-ENG_CITY COUNCIL__SUNESYS__Jefferson-Leahy__Encroachment Agreement__Attachment.pdf
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
title
CC - Adoption of a Resolution Approving an Encroachment Agreement with Sunesys for Fiber Optic Telecommunication Cable in the Public Right-of-Way on Jefferson Boulevard near Leahy Street.

body
Contact Person/Dept: Sammy Romo / Public Works
Phone Number: (310) 253-5619

Fiscal Impact: Yes [] No [X] General Fund: Yes [] No [X]

Public Hearing: [] Action Item: [X] Attachments: Yes [X] No []

Commission Action Required: Yes [] No [X] Date:
Commission Name:

Public Notification: (E-Mail) Meetings and Agendas - City Council (11/05/15)

Department Approval: Charles D. Herbertson, Public Works Director/City Engineer (10/30/2015)
______________________________________________________________________

RECOMMENDATION

Staff recommends the City Council adopt a resolution approving an Encroachment Agreement with Sunesys for 94 linear feet of proposed fiber optic telecommunication cable in the public right-of-way on Jefferson Boulevard, approximately 127 feet east of the centerline of Leahy Street.


BACKGROUND / DISCUSSION

Sunesys is proposing to install a new fiber optic pathway in order to complete the connection of their existing fiber optic lines.

The work involves tying into the applicant's existing splice box in the sidewalk adjacent to Jefferson Boulevard, proceeding west for 10 feet, then turning north across Jefferson Boulevard for 79 feet, and then turning east for 5 feet before rising up the existing utility pole. The conduit across Jefferson Boulevard will be placed via directional boring, and the conduit in the sidewalk will be placed by open-cut trenching.

The total distance of the new installation in the public right-of-way is 94 linear feet. There are no new utility poles proposed along the route.



Legal Framework

Sunesys is the holder of a Certificate of Public Convenience and Necessity issued by the Califo...