title
(1) Acceptance of Work Performed by Peterson-Chase General Engineering Construction, Inc.; (2) Authorization to File a Notice of Completion; and (3) Authorization to Release the Retention Payment in the Amount of $3,618.31 after Expiration of the 35-Day Lien Period, for the Construction of the Duquesne Avenue Bridge Expansion Joint Repair Project, PZ-938.
body
Contact Person/Dept: Hong Wang/PW
Phone Number: 310.253.5604
Fiscal Impact: Yes [x] No [] General Fund: Yes [x] No []
Public Hearing: [] Action Item: [] Attachments: Yes [] No [x]
Commission Action Required: Yes [] No [] Date:
Commission Name:
Public Notification: (E-Mail) Meetings and Agendas - City Council (3/25/16)
Department Approval: Charles D. Herbertson, P.E. Public Works Director/City Engineer (3/18/16)
______________________________________________________________________
RECOMMENDATION
Staff recommends the City Council accept the work performed by Peterson-Chase General Engineering Construction, Inc., authorize the filing of a Notice of Completion, and authorize release of the retention payment in the amount of $3,618.31 after expiration of the 35-day lien period for the construction of Duquesne Avenue Bridge Expansion Joint Repair Project, PZ-938.
BACKGROUND/DISCUSSION
On August 24, 2015 the City Council awarded the construction contract to Peterson-Chase General Engineering Construction, Inc. in the amount of $70,440.00 for the construction of Duquesne Avenue Bridge Expansion Joint Repair Project, PZ-938. The project included the replacement of the deteriorated bridge expansion joint steel plates and pavement transition.
The Contractor successfully completed the project in January 2016, within budget and contract time. To minimize the construction impact to traffic, the repair was conducted during several Saturdays and at least one lane was open to tr...