File #: 25-129    Version: 1 Name: Approve Contract with Southland for City Yard HVAC
Type: Minute Order Status: Consent Agenda
File created: 7/23/2024 In control: City Council Meeting Agenda
On agenda: 9/23/2024 Final action:
Title: CC - CONSENT ITEM: (1) Approval of an Agreement with Southland Industries in the Amount of $1,150,367 for the City Yard HVAC Replacement Project; and (2) Authorization to the City Manager to Approve Amendments to the Agreement in an Amount Not-to-Exceed an Additional $115,037 to Cover Contingency Costs.
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
title
CC - CONSENT ITEM: (1) Approval of an Agreement with Southland Industries in the Amount of $1,150,367 for the City Yard HVAC Replacement Project; and (2) Authorization to the City Manager to Approve Amendments to the Agreement in an Amount Not-to-Exceed an Additional $115,037 to Cover Contingency Costs.

body
Meeting Date: September 23, 2024

Contact Person/Dept.: Gary Wansley/Public Works Maintenance/Operations
Joe Susca/Public Works-Administration

Phone Number: (310) 253-6444
(310) 253-5636

Fiscal Impact: Yes [X] No [ ] General Fund: Yes [X] No [ ]

Attachments: Yes [ ] No [X]

Public Notification: E-Mail: (09/17/2024) Meetings and Agendas - City Council; (09/09/2024) Southland Industries; (09/09/2024) MEP Fusion

Department Approval: Yanni Demitri, Public Works Director/City Engineer (09/03/2024)
_____________________________________________________________________


RECOMMENDATION

Staff recommends the City Council: (1) approve an agreement with Southland Industries in the amount of $1,150,367 for the City Yard Heating, Ventilation and Air Conditioning Replacement Project, CIP No. PF-041 Public Works City Yard HVAC Replacement in combination with PZ-132 Building Repairs; and (2) authorize the City Manager to approve amendments to the agreement in an amount not-to-exceed an additional $115,037 (10%) to cover contingency costs.


BACKGROUND

The City Yard is home to the City's Park Maintenance, Environmental Programs and Operations, and Maintenance and Operations staff. The facility contains many offices and shops and houses equipment, materials, tools and supplies that support the traffic signal, sewer, traffic sign, parking meter, graffiti abatement, pavement painting, facility maintenance, storm drain, park maintenance, streetlight, asphalt and concrete crews.

The useful life of a Heating, Ventilation and Air Conditioning (HVAC) package unit is 15 to 20 years. The City Yard's existing HVAC package units, exhaust fans, ...