title
CC - (1) Approval of an Agreement with ACCO Engineered Systems in an Amount Not-to-Exceed $648,722 to Replace the Heating, Ventilation and Air Conditioning System at the Veterans Memorial Complex; (2) Acceptance of a Five-Year 0% Interest Loan in the Amount of $450,789 from the County of Los Angeles for the Project; and (3) FOUR-FIFTHS VOTE REQUIREMENT: Approve a Budget Amendment to Increase CIP PE-005 Funding from $230,000 to $648,722 in Fiscal Year 2021/22 in Order to Complete the Project in One Phase/Fiscal Year and to Record the Loan Proceeds of $450,789 and SCE Incentive Funds of $16,833.
body
Meeting Date: December 13, 2021
Contact Person/Dept: Joe Susca, Public Works Administration
Phone Number: 310-253-5636
Fiscal Impact: Yes [X] No [] General Fund: Yes [X] No []
Public Hearing: [] Action Item: [] Attachments: []
Commission Action Required: Yes [] No [X] Date:
Public Notification: (E-Mail) Meetings and Agendas - City Council (12/08/2021); ACCO Engineered Systems (11/17/2021); Southern California Regional Energy Network (11/17/2021)
Department Approval: Yanni Demitri Public Works Director/City Engineer (11/29/2021)
_____________________________________________________________________
RECOMMENDATION
Staff recommends the City Council (1) approve an agreement with ACCO Engineered Systems (ACCO) in an amount not-to-exceed $648,722 for the Veterans Memorial Auditorium (Vets) Heating, Ventilation and Air Conditioning (HVAC) system replacement; (2) accept a $450,789 five-year, interest-free loan from the County of Los Angeles to fund a portion of the project's cost; and (3) approve a budget amendment to increase CIP PE-005 funding from $230,000 to $648,722 in Fiscal Year 2021/22, in order to complete the work in one phase/fiscal year and to record the loan proceeds of $450,789 and SCE Incentive Funds of $16,833. (budget amendment requires four-fifths vote).
BACKGROUND
The City has been ...