title
CC - Award of a Construction Contract to Premier Developing Services, Inc. as the Lowest Responsive and Responsible Bidder for Construction of the Hayden Tract Spur Parking Lot Project in an Amount Not-To-Exceed $811,926.25.
body
Contact Person/Dept: Glenn Heald/CDD
Todd Tipton/CDD
Phone Number: (310) 253-5752
(310) 253-5783
Fiscal Impact: Yes [X] No [] General Fund: Yes [] No [X]
Public Hearing: [] Action Item: [] Attachments: Yes [] No [X]
Commission Action Required: Yes [] No [X] Date:
Commission Name:
Public Notification: (E-Mail) Meetings and Agendas - City Council (03/10/16)
Department Approval: Sol Blumenfeld, Director of Community Development
(03/09/16)
______________________________________________________________________
RECOMMENDATION
Staff recommends the City Council award a construction contract to Premier Developing Services, Inc. (Premier), as the lowest responsive and responsible bidder for the construction of the Hayden Tract Spur Parking Lot Project (Project) in an amount not-to-exceed $811,926.25 ($667,596.25 Base Contract Amount plus $124,330 in Contingency Authority and up to $20,000 in Utility Connection Costs).
BACKGROUND
On January 31, 2012, the City executed an Owner Participation Agreement (OPA) with the Hayden Tract Owners' Association (Owners) to design and construct an at-grade parking lot on the former Los Angeles County Metropolitan Transportation Authority railway spur in the Hayden Tract (the Project). An amendment to the OPA was executed on May 8, 2015.
The City retained KOA Corporation (KOA) to design the Project and to perform all construction management services. On February 8, 2016, the City Council approved the plans and specifications and authorized the issuance of a Notice Inviting Bids for construction of the Project.
DISCUSSION
The Notice Inviting ...
Click here for full text