Title: CC - CONSENT ITEM: Approval of Final Plans and Specifications and Authorization to Publish a Notice Inviting Bids for the Sidewalk, Curb Ramp and Driveway Approach Project, PZ-428.
Attachments: 1. 1.2026-04-27 – ATT PZ428 Specifications.pdf
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

title

CC - CONSENT ITEM: Approval of Final Plans and Specifications and Authorization to Publish a Notice Inviting Bids for the Sidewalk, Curb Ramp and Driveway Approach Project, PZ-428.

 

body

Meeting Date:                      April 27, 2026

 

Contact.:                     David Nauta/Public Works, Engineering

 

Phone Number:                     (310) 253-5606

 

Fiscal Impact:                     Yes [  ]    No [X]                     General Fund:                     Yes [X]    No [ ]

 

Attachments:                     Yes [  ]    No [X]

 

Public Notification:                     E-Mail: Meetings and Agendas - City Council (04/23/2026)

 

Department Approval:                     Yanni Demitri, Public Works Director/City Engineer (04/06/2026)

_____________________________________________________________________

 

 

RECOMMENDATION

 

Staff recommends the City Council approve the final plans and specifications and authorize the publication of a notice inviting bids for the Sidewalk, Curb Ramp and Driveway Approach Project, PZ-428.

 

 

BACKGROUND

 

The City receives maintenance requests from the public for areas such as broken and uplifted concrete sidewalks, curb ramps, driveway approaches and street sections. Public Works Department compiles resident requests and investigates them to assess the damage and potential hazard to pedestrians. In addition to the ongoing repairs completed by Public Works Maintenance and Operations Staff, Engineering Division regularly manages projects that can address many locations at once, prioritizing locations based on severity, budget constraints, and previous maintenance measures. This Project addresses infrastructure repairs citywide at various locations. Since sidewalk uplift at many locations is mainly attributed to parkway tree root intrusion, tree root trimming is also part of the scope, and the City Arborist shall be consulted.

 

The bid documents include both the construction exhibits and specifications that have been prepared by engineering staff.

 

 

 

 

FISCAL ANALYSIS

 

The total estimated project cost is $416,000. The proposed project will be funded with City funds allocated FY 25/26 FY budget for Capital Improvement Projects through General Fund and Gas Tax Fund sources found on pages 591 and 590 of the budget book respectively.

 

Proposed Project Budget Funding Source

 

418.CP.80000.000.000.000.730100.PZ428                                                               $ 444,500.00

420.CP.80000.000.000.000.730100.PZ428                                                               $   78,500.00

 

 

ATTACHMENTS

 

1.                     2026-04-27 - ATT PZ428 Specifications

 

recommended action

MOTIONS

 

That the City Council:

                     

Approve the final plans and specifications and authorize the publication of a notice inviting bids for construction of for the Sidewalk, Curb Ramp, and Driveway Approach Project, PZ-428.