Legislation Details

File #: HIST-16640    Version: 1 Subject:
Type: Historical Status: Consent Agenda
In control: City Council Meeting Agenda
On agenda: 5/2/2011 Final action: 5/2/2011
Title: Award of a Contract to All American Asphalt, as the Lowest Responsive and Responsible Bidder, for the Construction of the 2011 Pavement Overlay Project, P-863, P-903.
Attachments: 1. Award of a Contract to All American Asphalt, as th - C-3__11-05-02__PW-Eng__CITY COUNCIL__2011 Pavement Overlay Project Contract Award-FINAL.doc, 2. Award of a Contract to All American Asphalt, as th - 11-05-02__PW-Eng__CITY COUNCIL__2011 Pavement Overlay Project Contract Award__Attachment with cover.pdf
City of Culver City, California Agenda Item Report Meeting Date: 05/02/11 Item Number: C-3 CITY COUNCIL AGENDA ITEM: Award of a Contract to All American Asphalt, as the Lowest Responsive and Responsible Bidder, for the Construction of the 2011 Pavement Overlay Project, P-863, P-903. Contact Person/Dept.: Sammy Romo/PW Phone Number: 310-253-5619 Fiscal Impact: Yes [X] No [] General Fund: Yes [X] No [] Public Hearing: [] Action Item: [] Attachments: [X] Commission Action Required: Yes [] No [X] Date: _______________ Public Notification: (E-Mail) Meetings and Agendas – City Council (04/27/11); (E-Mail) - All American Asphalt, Hardy and Harper, Inc., Sequel Contractors, Sully-Miller Contracting Co., Excel Paving, Silvia Construction, Inc., (04/28/11) Department Approval: Charles D. Herbertson (04/20/11) City Attorney Approval: Carol Schwab (by H. Baker) (04/27/11) Chief Financial Officer Approval: Jeff Muir (by K. Marsden) (04/27/11) City Manager Approval: John M. Nachbar (04/27/11) RECOMMENDATION: Staff recommends the City Council: 1) Award a contract with All American Asphalt as the lowest responsive and responsible bidder for the construction of the 2011 Pavement Overlay Project, P-863, P-903; and, 2) Authorize the Public Works Director/City Engineer to increase the construction contract with All American Asphalt in an amount not to exceed $236,750 (25% of base bid) for additional street resurfacing work. BACKGROUND: The scope of work consists of removing and replacing two to three inches of deteriorated asphalt concrete with new rubberized asphalt concrete. All streets will be re-striped to current conditions, except for Bentley Avenue, which will be re- striped to include a bike lane in each direction. Additionally, curb and gutter will be replaced where necessary. The following is a list of streets to be resurfaced: 1. Jasmine Avenue: Culver Boulevard to Farragut Drive 2. Vinton Avenue: Braddock Drive to Farragut Drive 3. Farragut Drive: Jasmine Avenue to 100 feet west of Motor Avenue 4. Bentley Avenue: Venice Boulevard to Washington Place 5. Pigott Drive: Sepulveda Boulevard to Bentley Avenue 6. Matteson Avenue: Alley west of Bentley Ave. to alley east of Bentley Ave. City of Culver City, California Agenda Item Report 7. Ocean Drive: Cota Street to Studio Drive 8. Rhoda Way: Cota Street to Studio Drive 9. Kinston Avenue: Rhoda Way to Jefferson Boulevard 10. Cota Street: Rhoda Way to Jefferson Boulevard 11. Stevens Circle 12. Dobson Way: Stevens Circle to Jefferson Boulevard 13. Hayter Avenue: Sawtelle Boulevard to Port Road 14. Segrell Way: Sawtelle Boulevard to Slauson Avenue 15. Coombs Avenue: Barman Avenue to Farragut Drive 16. Walgrove Avenue: Zanja Street to Washington Boulevard DISCUSSION: On April 7, 2011, the City Clerk’s Office staff publicly opened the bids. Six contractors responded with the following bid amounts: CONTRACTOR BID AMOUNTS 1 All American Asphalt $947,000 2 Hardy and Harper $1,011,000 3 Sequel Contractors $1,025,650 4 Sully-Miller Contracting Company $1,034,000 5 Excel Paving $1,054,410 6 Silvia Construction $1,184,475 Staff reviewed the six sets of contractor bid documents and determined All American Asphalt submitted the lowest total base bid. Staff reviewed the bid proposal from All American Asphalt and found the bid documents responsive and complete. Its bid bond, contractor’s license, and worker’s compensation insurance were reviewed and determined to meet City requirements. All American Asphalt has completed several similar projects for the City of Culver City recently such as the 2007 Residential Overlay Project, the 2009 Residential Overlay Project, and the 2010 Pavement Overlay Project with satisfactory performance. Staff recommends awarding the construction contract to All American Asphalt, as the lowest responsive and responsible bidder, for the construction of the 2011 Pavement Overlay Project, P- 863, P-903. Due to the favorable low unit prices in All American Asphalt’s bid and a sufficient available budget, it is recommended that the following street segments be added to the scope of work: • Rhoda Way: Studio Drive to Ocean Drive • Barman Avenue: Coombs Avenue to Elenda Street • Sentney Avenue: Washington Boulevard to southerly cul-de-sac City of Culver City, California Agenda Item Report • Fay Avenue: Washington Boulevard to northerly city limit • Revere Place: Farragut Drive to southern cul-de-sac The construction management of the project will be conducted by Engineering Division staff. Both construction inspection services and material testing services will be procured through a competitive Request for Proposal (RFP) process, to be selected from a list of firms pre-approved by the City Council. After the RFP’s are received, staff will review and select the consultant. The costs for these services are expected to be approximately $30,000 and $10,000, respectively. The proposed construction project will begin in July 2011 and is expected to be substantially completed by September 2011. Public Notification Approximately two weeks prior to construction activity, the adjacent businesses and residences will be provided with written information on the project schedule and contact information for questions and/or concerns regarding the project. FISCAL ANALYSIS: Proposed Project Budget Funding Source Amount P-863 Proposition 42 (43000863) $65,103 P-863 General Funds (42000863) $700,530 P-863 Measure R (43100863) $599,000 P-903 Proposition 1B (42900903) $180,342 Total = $1,544,975 Estimated Project Expenses 2010 Pavement Overlay Project, P- 863, P-903, Construction Contract $947,000 Increase Contract Amount by 25% $236,750 Construction Inspection Services $30,000 Geotechnical Construction Services (Observation & Testing) $10,000 Subtotal $1,223,750 10% project contingency $122,375 Total Estimated Project Expenses $1,346,125 City of Culver City, California Agenda Item Report ATTACHMENTS: 1. Location Map MOTIONS: That the City Council: 1) Award a contract to All American Asphalt, as the lowest responsive and responsible bidder, for the 2011 Pavement Overlay Project, P-863, P-903, in the amount of $947,000, based on its base bid; 2) Authorize an increase of the construction contract with All American Asphalt in an amount not to exceed $236,750 (25% of base bid) for additional street resurfacing; 3) Authorize the Public Works Director/City Engineer to approve change orders in the amount not-to-exceed $122,375, if necessary; and, 4) Authorize the City Attorney to review/prepare the necessary documents; and, 5) Authorize the City Manager to execute such documents on behalf of the City. MEETING DATE: 05/02/11 AGENDA ITEM: Award of a Contract to All American Asphalt, as the Lowest Responsive and Responsible Bidder, for the Construction of the 2011 Pavement Overlay Project, P-863, P-903 ATTACHMENTS Pages 1 Location Maps 1-6 JASMINE AVE FROM FAIR-RAGUT DR TO CULVER BL VINTON AVE FROM FARRAGUT DR TO BRADDOCK DR • ... :: : . RAGUT DR E : . .. ''''' ' : Fk()11/1 100' WEST OF MO R A E • .1- 1" ::: : ' :: ::::: ::: : ::... ::::::::::: ........ '...0 i • ' :: ••• - • • . . • • • . :: 10 JASMINE AVE.::::. : ::. • ,en • . . . . " REVERE PL Public Works Department Engineering Dis4sion Location Map 1 2011 Residential Overlay Project Legend Resurfacing • Culver City Boundary ..." 125 250 500 Feet THE CITY OF CULVER CITY 1NFORMATGErq TECHNOLOGY DEPARTMENT GEOGRAPHIC INFOIRMATION SY.STEPAS ,.. MARCH 29 2011 BENTLEY AVE [ FROM MATTESON AVE TOHVENIqE:B.1... I: BENTLEY AVE - FROM WASHINGTON PL TO MATTES:ON AVE MATTESON AVE • 1 FROM BENTLEY AVE TO EAST END PIGOTTDR FROM SEPLILVEDA BLVD TO BENTLEYAVE Public Works Department Engineering Division Location Map 2 2011 Residential Overlay Project Legend Resurfacing • Culver City Boundary 125 250 500 =611n 11 Feet '''' '' ,%%Z YZa:k7' 117:,;4 n 77:7,1727,2,:aVr4",,,P A : =0,=. 1mr. 11. r nmin evr.aromfar ell, THE CITY OF CULVER -CITY NFORMATION TECHNOLOGY DEPARTMENT GEOGRAFHiC !NFCRMATI ON 2737E109 1:, JAN12.7,1, 2011 --•----- . WAY . • . 1; DR KI•101A • • : ••• ROM C.0 TA 37. TO: 5.1 -1 ...1 b • • • Public Works Deparinient Engineering Division Location Map 3 2011 Residential Overlay Project . : . . CF • .•. • • ••• FROM CO,E. ST1•0178a.e0.K; • 19 . 4.f - --- • •<>"• "q6s. • "••• . I dr,'IAV.t. • . rkdivf10:FERseirq BLTC IS-I0OA WAY Legend Resurfacing • Culver City Boundary COTAS DOBSON • • • : 7T.40171.bth, eL • • • 1-AYT5R AV:F: " FROM SA TSL0 AVE TO PORT RIDi '• & HERITAGE Pl. MACHA:60 : . . rs3-' . • • : KEL:MQ ST KALEIN 04) logo Ric,Li. 0"°' ..9 \ . BLANCO VVY 0 . Li- co AVVTLLE•BL 6c I ,0 e - ! u & ' • z 0 1 • * ,.*.' 0 • C3 . . . P . .;q". ... LLI : < Oe/ 0 .>r' I . -,t -! 0 o_ __I • .6 :It, X 0 2 El ?)- ' 2 • P. 4, ,:5 ;_= ,-., -L. 0 4+ . -c• --: . "I' a' .4 1 • . • • :(4, • ,N. .. ,s0 • , -• : :: t . . Z. • •••••Z • ti• • . . : . : .• • •:.:p• :, • > • . • • . :.-< 0 0 ... . • . . •.• ousH.:‘iQY - ..:--..:. • , ... 20........•••• •:. . ... -:.....::.•• - . . . . ••. . . ... ..... • •• • . . . . . :•••• • • ::•. . : • • •••:0: • • : . : • ...::::::.... .............. 250 500 1,000 Feet THE CITY OF CULVER CITY INFORMATION TECHNOL OGY DEPARTMENT GEOGRAPPdc INFORMATION SYSTEMS m muena APSILY. 2011 ' • '' : Public Works Department Engineering Divislon Location Map 4 2011 Residential Overlay Project • FROM .QPQM13-$:•AVE•70ELNDA• ::$17 : 1:•• ti /6 kfr 4Z- ‹) 49 Y . LY/ r- 4 b00,2 - Legend Resurfacing • Culver City Boundary 125 250 500 Feet ::•:60QMOS AVE .." ::FRQM . F.ARRO:UrpR.T.Q:$ARmAN .i.Ay.E: nry r...r maNel reprt4e.fienzrven...,,,,mm, rer,ed the ww-s, Pq ITO I-ns 1.1.1mh. M a eempla.,riele.6.7.nr re' [m.o. cbb1.1.1-: yak. Neumel 7,- Ma rIllohyrd er0, 12 bn•Iner 1044;177g1T/11ra FtrF1,7;r c' 4,77:g.11 1=4" 41.1.= THE CITY OF CULVER CITY INFORMATION TECHNOLOGY ITEPARTMENT WOGRAPHCIWORMATICN SYSTEMS 977D MI, E0 BLVD APP,125, 2011 WALGROVE AVE:. . • FROM ZANJASTTO WASHINGTON . .14:,. • Public Works Department Engineering Division Location Map 5 2011 Residential Overlay Project Legend Resurfacing ,,, • Culver City Boundary 130 260 520 6•11111=11111n 1. Feet 144.1 .11=" THE CITY OF CULVER CITY INFORMATFON TRCHNOLC*Y MPARTMENT cEocRAPHEC INF•IRMATION SYSTEMS swo .10.14 12,77 'e .At 77. I' l:93,5171- KARRFI p. 2 011 Public Works Department Engineering Division Location Map 6 2011 Residential Overlay Project i.SA - 1 0 6 ,,,,/ (/iN • r". 'it, • 1 - FAY AVE l- 0 . FROM WASHINGTON E TO CITY LIMIT! N...1* /.." "qt; _ > .,„ a er • ....0* 8 1..\6\ z w ç4. CIl f '-(f) • '0 .-- .‘V- - ,tr 4 u) 0,00 m" 10 V.- (9 • lq/14S BL . i) — .i. --: • ' ' ...-/ ,4 .,. 1., i , in rlw i ..... woo Legend MI Resurfacing Culver City Boundary 4IM • SENTNEYAV 'FROM ...WASHINGTON - BLTO: CU:LDESAC' ....... ::..:...... 0 120 240 480 1n 1=61111n 1 Feet THE CM' OF CULVER CITY I5FORMA1 ON TECHNOLOGY DEPARTMENT GEOGP.SPI-C:7NFMMAI1C -N SYSTEMS APRIL 25, 2011