CITY 'CQUNC11,_ 'AGENDA ITEM: Award of 0 ::COnatrUCtiOn .Contract .tO::FreeWay:,
. Electric, as the Lowest Responsive and :Responsiblei Bidder, for the Construction
: of the Buckingham Parkway and Sumner Way Pedestrian Signal Crosswalk :Project,
P--.80L
ContadtPetson/DePt.: Elaine Jeng/RA/, Phone :Number: 310-253-5621/310-253-
Mate QaaparipW 5.6
Fiscal Impact: p .s] No ,I1 i i l
General Fund: Yes []
: ::NO [c]:
Public Hearing: I]: : :Action : Item: []::
Attachments: II:
Commission Action Required: Yet : No [X] Pate:
Public Notification: (EA/lail) Agenda and Meetings 7 city Council (04/28/10);: (EA/laillii
. Freeway Electric (04/26/10); (USPS) Fox Hills Neighborhood Homeowner's Association
: (04/26/10)
Department Approval:
' Charles D. ::HerbertsOn (Q4/22/10):
City Attorney Approval:
: Carol Schwab : (by H. Bakot.) (04/27/10)
Chief Financial Officer Approval:
Jeff Muir (by N. Kimball) (04/20/10)
: City Manager Approval:
P. LaMonti:EWell (04128/10)
RECOMMENDATION:
a construction contract to Freeway
bidder, for the construction of the
Pedestrian Signal Crosswalk Project, P-
(FHNA) requested that the City
neighborhood as part of the Neighborhood
compliance with this City Council adopted
on all the streets in the Fox Hills
on existing traffic at the time, the NTMP
not recommend any traffic calming
that future pedestrian and vehicular
in the vicinity, including Symantec,
Pointe, would likely exceed the minimum
calming improvements: 1) a 3-way STOP
and Sumner Way; and 2) a pedestrian-
intersection of Buckingham Parkway and
Canterbury Drive and Sumner Way was
Staff recommends the City Council award
Electric, as the lowest responsive and responsible
Buckingham Parkway and Sumner Way
885.
BACKGROUND:
In 2005, the Fox Hills Neighborhood Association
assess the traffic impacts in the Fox Hills
Traffic Management Program (NTMP). In
program, traffic count data was collected
neighborhood. It was concluded that, based
thresholds were not met, and staff could
measures. Nevertheless, staff determined
traffic, due to the then-planned developments
Westfield Culver City, and 700 Corporate
threshold for allowing the following traffic
at the intersection of Canterbury Drive
activated traffic signal crosswalk at the
Sumner Way. The 3-way STOP on
installed in 2006.City of Culver City, California
Agenda Item Report
KOA Corporation completed the design and preparation of the plans and
specifications for the pedestrian traffic signal. Final plans and specifications were
approved by the City Council for advertisement for construction bids in late 2008.
The advertising for construction bids was delayed to allow staff to complete time
sensitive grant funded projects in 2009.
DISCUSSION:
On February 23, 2010, the project was advertised for construction bids. The bid
opening occurred on March 11, 2010. A total of seven (7) bids were received
ranging between $60,599 and $80,763. The following table summarizes the bid
results:
-
Contractor Bid Amounts
Freeway Electric $60,599.00
2 Pro Tech Engineering $64,132.50
3 CT & F $64,651.05
4 Christopher R Morales $64,859.00
5 California Professional Engineering $66,361.00
6 KDC, Inc. $69,728.00
7 Steiny & Company $80,763.00
The apparent lowest responsive and responsible bidder is Freeway Electric. Staff
reviewed Freeway Electric's bid proposal and found the bid documents were
accurate and complete. Freeway Electric's bid bond, contractor's license and
worker's compensation all meet City requirements. Staff reviewed and consulted
with their listed references and found that they performed satisfactorily in other
jurisdictions for similar work.
Public Works Department staff will serve as construction manager and inspector.
Should the City Council award the contract, construction is slated to commence in
June 2010 and expected to be completed by September 2010. Approximately two
weeks prior to commencement of construction activity, the adjacent residents will be
notified and provided with contact information for questions regarding the project.
FISCAL ANALYSIS:
The budget for this project was included in the Capital Improvement Program for FY
2008-2009 in the amount of $60,000 (Howard Hughes Development funds). Out of
the approved project budget, $10,000 was spent for design. To meet the necessary
budget for construction, $20,000 of Howard Hughes Development Funds in P-789,
(Sawtelle/Blanco Pedestrian Traffic Signal Project) will be administrativelyCity of Culver City, California
Agenda Item Report
transferred
determined
and
and
to P-885. The Sawtelle/Blanco Pedestrian Traffic
not to meet the necessary warrants to install a pedestrian
the project will be closed. The following table summarizes
expenditures:
Signal project was
traffic signal
the proposed budget
Budget Amount
Buckingham/Sumner (remaining) P-885 $50,000
Transfer from P-789 $20,000
Total $70,000
Proposed expenditures Amount
Freeway Electric Contract $60,599
Contingency $9,000
Total $69,599
MOTIONS:
That the City Council:
1) Award a construction contract to Freeway Electric, as the lowest responsive and
responsible bidder, in the amount of $60,599 for the Buckingham Parkway
Pedestrian Crossing Installation, P-885; and,
2) Authorize the Director of Public Works/City Engineer to approve change orders
totaling a not-to-exceed amount of $9,000; and,
3) Authorize the City Attorney to review/prepare the necessary documents; and,
4) Authorize the City Manager to execute such documents on behalf of the City.