File #: 25-690    Version: 1 Name: Award Contract to Ayala to Replace Police Station Pump
Type: Minute Order Status: Consent Agenda
File created: 1/14/2025 In control: City Council Meeting Agenda
On agenda: 1/27/2025 Final action:
Title: CC - CONSENT ITEM: Approval of a General Services Agreement with Ayala Sewer Contractors in an Amount Not-to-Exceed $59,750 to Replace a Sewage Pump Located at the Police Station.
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

title

CC - CONSENT ITEM: Approval of a General Services Agreement with Ayala Sewer Contractors in an Amount Not-to-Exceed $59,750 to Replace a Sewage Pump Located at the Police Station.

 

body

Meeting Date:                       January 27, 2024

 

Contact/Dept:                     Gary Wansley, Public Works-Maintenance Operations

 

Phone Number:                       310-253-6444

 

Fiscal Impact:                     Yes [X]     No [  ]                     General Fund:                     Yes [X]     No [  ]

 

Attachments:                      Yes [  ]     No [X]

 

Public Notice:                     E-Mail: GovDelivery Meetings and Agendas - City Council (01/22/2025); Ayala Sewer Contractors (01/14/2025); Pump Man SoCal (01/14/2025); EGL Plumbing, Inc. (01/14/2025)

 

Dept Approval:                     Yanni Demitri, Public Works Director/City Engineer (01/15/2025)

_____________________________________________________________________

 

 

RECOMMENDATION

 

Staff recommends the City Council approve a general services agreement with Ayala Sewer Contractors in an amount not-to-exceed $59,750 to replace a sewage pump located in the basement of the Police Station; CIP Project No. PZ-132 (Building Repairs).

 

 

BACKGROUND/DISCUSSION

 

The basement of the Police Station has a pit containing sewage that is automatically pumped out and into the City’s sewer main.  The pump has failed and cannot be repaired.  As a result, staff is manually removing sewage from the pit each day. 

 

The pump’s replacement falls under the “Exceptions to Bidding Requirements” of Culver City Municipal Code §3.07.055.I which includes “contracts for professional or general services as set for in §3.07.065. §3.07.065 A states the City may award purchase orders and contracts in any amount for professional or general services provided the purchase order or contract shall be based upon competitive quotations. §3.07.065 C.5 states general services shall include repair and maintenance service for equipment, machinery or other City-owned personal property. 

 

Staff obtained the following price quotes from competing firms to replace the failed pump with an enhanced system comprised of a duplex sewage ejector system containing two pumps, cleaning and coating the pit with an epoxy resin, and installation of new valves and float switches, a new steel lid with flanges for easier access, and a new control panel that will share the pumping duty between the two pumps and send alarms to staff if/when the system fails:

 

                     E.G.L. Plumbing Inc.                                          $45,000

                     Ayala Sewer Contractors                                          $59,750

                     Pump Man So Cal                                                               $67,508

 

Although E.G.L. Plumbing proposed the lowest price and is qualified to perform the work, E.G.L. does not carry adequate insurance coverage to meet the City’s requirements. They are unwilling to increase their policy coverage amounts to meet those requirements.  As such, staff recommends hiring Ayala Sewer Contractors as the second lowest price firm. Ayala is qualified to perform the work and if approved, they will replace the failed pump with the enhanced system in three working days. 

 

 

FISCAL ANALYSIS

 

The Adopted Budget for Fiscal Year 2024-2025 includes sufficient funds in CIP Project No. PZ-132 (Building Repairs) to cover the $59,750 expenditure. CIP Project No. PZ-132 can be found in the Capital Improvements section of the budget book under Capital Improvements - Facilities Planning Reserve (Fund 420F) on page 480.

 

 

ATTACHMENTS

 

None.

 

 

MOTIONS

 

That the City Council:

 

1.                     Approve a general services agreement with Ayala Sewer Contractors in an amount not-to-exceed $59,750 to replace the sewage pump at the Police Station; and

 

2.                     Authorize the City Attorney to review/prepare the necessary documents; and

 

3.                     Authorize the City Manager to execute such documents on behalf of the City.