Title:
|
(1) Approval of Final Plans and Specifications and (2) Authorization to Publish a Notice Inviting Bids for the Veterans Memorial Building Renovation, P-876.
|
City of Culver City, California
Agenda Item Report
Meeting Date: 09/26/11 Item Number: C-5
CITY COUNCIL AGENDA ITEM: (1) Approval of Final Plans and Specifications and
(2) Authorization to Publish a Notice Inviting Bids for the Veterans Memorial
Building Renovation, P-876
Contact Person/Dept.: Bellur Devaraj/PW Phone Number: (310) 253-5621
Fiscal Impact: Yes [X] No [] General Fund: Yes [X] No []
Public Hearing: [] Action Item: [] Attachments: []
Commission Action Required: Yes [] No [X] Date: _______________
Public Notification: (E-Mail) Agenda and Meetings – City Council (09/21/11)
Department Approval:
Charles D. Herbertson (09/15/11)
City Attorney Approval:
Carol Schwab (by H. Baker) (09/20/11)
Chief Financial Officer Approval:
Jeff Muir (by K. Marsden) (09/20/11)
City Manager Approval:
John M. Nachbar (09/20/11)
RECOMMENDATION:
Staff recommends the City Council (1) approve the final plans and specifications and
(2) authorize the publication of a notice inviting bids for the Veterans Memorial
Building (VMB) Renovation Project P-876.
BACKGROUND/DISCUSSION:
Several rooms and restrooms of the VMB are in need of renovation. In January 2011
the City retained DLR Group Architects to work with the Parks, Recreation, and
Community Services Department to establish a scope of renovations within available
budgeted funds.
The architect has established the following scope of renovations for the VMB.
• Complete refurbishment of the women’s and men’s restrooms with new toilet
fixtures, new flooring and ADA accessible toilets. Additionally, there are
substances which need to be abated, which abatement will occur under a
separate contract.
• Approximately 450 auditorium seats in the auditorium lower level will be removed
and replaced by new seats with new aisle carpeting.
• Painting of the auditorium walls and ceiling tiles.
• Replacement of the accordion door adjacent to the service counter.
City of Culver City, California
Agenda Item Report
• Several cosmetic improvements such as painting for the Iksan Room, Uruapan
Room, Yangi Room, Kaizuka Room and classrooms A, B, C and D
The plans and specifications are currently under review by the Building Safety
Division. The project will be advertised after receiving the building permit. City
Council approval for advertising the project is now requested to expedite the bidding
process in order to meet the construction scheduling constraints to start construction
in January 2012 and to complete construction by the end of March 2012.
FISCAL ANALYSIS:
Proposed Project Budget
Funding Source Amount
P-876 Park Facilities (Account No: 41900876) $30,000
P-876 Capital Improvements (Account No: 42000876) $186,000
P-93650 Redevelopment Agency (Account No:
48693650)
$185,000
Total $401,000
Estimated Project Expenses
VMB renovations $385,000
Construction Inspection Services $ 10,000
10% Project Contingency $38,000
Total Estimated Project Expenses $433,000
The current estimated project costs are higher than budgeted funds. The project will
be bid with several alternate bid items that can be awarded or deleted from the final
contract scope to bring the project costs to within budget. After bid opening, staff will
make a recommendation to the City Council for the scope of contract award.
MOTIONS:
1. Approve the final plans and specifications for the Veterans Memorial Building
Renovations Project, P-876; and,
2. Authorize publication of a notice inviting bids for construction of the Veterans
Memorial Building Renovation Project, P-876