File #: 15-130    Version: 1 Name: All American Ashpalt - Acceptance of Work
Type: Minute Order Status: Consent Agenda
File created: 7/27/2015 In control: City Council Meeting Agenda
On agenda: 7/27/2015 Final action:
Title: (1) Acceptance of Work Performed by All American Asphalt; (2) Authorization to File a Notice of Completion; and (3) Authorization to Release the Retention Payment of $37,822.20 after Expiration of the 35-Day Lien Period for the Washington Place and Sawtelle Boulevard Resurfacing Project, PZ-942, Federal Aid No. STPL 5240 (031).
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

title

(1) Acceptance of Work Performed by All American Asphalt; (2) Authorization to File a Notice of Completion; and (3) Authorization to Release the Retention Payment of $37,822.20 after Expiration of the 35-Day Lien Period for the Washington Place and Sawtelle Boulevard Resurfacing Project, PZ-942, Federal Aid No. STPL 5240 (031).

 

body

Contact Person/Dept: Hong Wang/PW

Phone Number:  310-253-5604

 

Fiscal Impact:  Yes [X]    No []                                                                             General Fund:  Yes X]     No []

 

Public Hearing:  []                               Action Item:                     []                         Attachments:   Yes []     No []   

 

Commission Action Required:     Yes []     No [X]         

 

Public Notification:  (E-Mail) Agenda and Meetings - City Council (07/22/15); (E-Mail) All American Asphalt bidders (07/22/15)

 

Department Approval:  Charles D. Herbertson (07/16/15)

______________________________________________________________________

 

 

RECOMMENDATION

 

Staff recommends the City Council:  (1) accept the work performed by All American Asphalt; (2) authorize the filing a Notice of Completion; and (3) authorize release of the retention payment of $37,822.20 after expiration of the 35-day lien period for the Washington Place and Sawtelle Boulevard Resurfacing Project, PZ-942, Federal Aid No. STPL 5240 (031).

 

BACKGROUND/DISCUSSION:

On October 13, 2014 the City Council awarded the construction contract to All American Asphalt for the Washington Place and Sawtelle Boulevard, PZ-942, Federal Aid No. STPL 5240 (031).  The project included the resurfacing of Washington Place between Zanja Street and Rosabell Street, Sawtelle Boulevard between Braddock Drive and Culver Boulevard and between Washington Boulevard and Washington Place. In addition, Washington Place from Grand View Boulevard and Rosabell Street was restriped to include bike lanes.

All American Asphalt successfully completed the project. Two change orders were issued in the total amount of $23,459.53 for additional survey of existing street flow line grades on Sawtelle Boulevard and traffic striping modifications on a portion of Washington Place and dedicated bike lanes along Sawtelle Boulevard between Culver Boulevard and Braddock Drive.

Construction management and inspection was provided by Interwest Consulting, Inc., and material testing services were provided by Geo-Environmental Inc., both selected through the list of on-call consultant firms pre-approved by the City Council.  

 

FISCAL ANALYSIS:

Project Budget

Federal Highway STPL Funds (42380000.730100.PZ942)

$672,000

PZ-965 (Fund 418) Washington Place Re-Striping Project

$54,000

PZ-684 (Fund 418) Streetlight Improvement

$16,000

PZ-428 (Fund 418) Curb, Gutter, and Sidewalk Reconstruction

$49,000

PZ-942 (Fund 417) Sawtelle Boulevard Resurfacing

$30,000

PZ-554 (Fund 420) Minor Pavement and Concrete Improvement

$10,000

Available Funds

$831,000

Final Project Expenses

Construction Contract (Base Bid + Additive Bid)

$732,984.46

Change Order

$ 23,459.53

Subtotal

$ 756,443.99

Construction Management and Inspection Services (Estimated)

 $47,000.00

Material Testing Services

$21,500

Total Final Project Expenses

 $824,943.99

ATTACHMENT:

None

 

MOTIONS:

That the City Council:

1)                     Accept the work performed by All American Asphalt for the Washington Place and Sawtelle Boulevard Resurfacing Project, PZ-942, Federal Aid No. STPL 5240 (031); and,

 

2)                     Authorize the Public Works Director/City Engineer to execute the Notice of Completion and submit it to the Los Angeles County Recorder’s office for recordation; and,

 

3)                     Authorize the release of $37,822.20 in retention funds to All American Asphalt following the expiration of the 35-day lien period.