City of Culver City, California
City Council Agenda Item Report
RECOMMENDATION:
Staff recommends the City Council approve an agreement with SanCon
Engineering, Inc. (SanCon) to rehabilitate sewer manholes throughout the City.
BACKGROUND:
A sewer manhole is a maintenance access point from the surface of the ground to
the sewer main. Sewer manholes are primarily constructed of brick and mortar and
have a steel ladder. Bricks are inert and do not deteriorate. However, the hydrogen
sulfide gases generated by the sewage flow will cause the mortar to disintegrate
between the bricks. Without the bonding of the mortar to the bricks, structural failure
of the manhole could result causing bricks to fall into the sewer main leading to
blockage of sewage flow and, in the worst case scenario, collapse of the street
above the manhole.
DISCUSSION:
Public Works Staff identified 27 sewer manholes in need of rehabilitation. The work
will include the rehabilitation of existing concrete and brick sanitary sewer manholes
to rebuild strength and eliminate possible infiltration, exfiltration, root intrusion, and
future deterioration of the concrete due to the sewer environment.
Maintenance and repair work is not subject to formal bidding requirements per the
City’s Charter. On December 9, 2008, a Request for Proposal (RFP) was released
Meeting Date: February 9, 2009 Item Number: C-4
AGENDA ITEM: Approval of an Agreement with SanCon Engineering Inc. to
Rehabilitate Sewer Manholes Throughout Culver City.
Contact Person/Dept.:
Eric Mirzaian
Public Works-Maintenance Operations
Phone Number:
(310) 253-6410
Fiscal Impact: Yes [x] No [] General Fund: Yes [] No [x]
Public Hearing: [] Action Item: [] Attachments: [X]
Public Notification:
Master E-Mail Notification List (02/04/09); SanCon Engineering, Inc.; Zebron
Contracting, Inc. (via letter on February 2, 2009)
Department Approval:
Charles D. Herbertson (01/29/09)
City Attorney Approval:
Carol Schwab (by H. Baker) (02/03/09)
Chief Financial Officer Approval:
Jeff Muir (by M. Noller) (02/04/09)
City Manager Approval:
Jerry B. Fulwood (020/04/09) City of Culver City, California
City Council Agenda Item Report
to qualified contractors and was advertised on the City’s website. On January 13,
2009, the following proposals were received:
SanCon Engineering, Inc.…………$158,100.00
Zebron Contracting, Inc……………$212,301.00
SanCon’s proposal was based on the following per vertical foot pricing:
Rehabilitation of manholes 4’ or less in diameter...……….$525 per vertical foot
Rehabilitation of manholes 5’ or greater in diameter…… $575 per vertical foot
Replacement of manhole frame and cover (9 locations)….$1,000 each location
Based on the dimensions of the sewer manholes that will be rehabilitated and the
replacement of 9 frames and covers, the total cost will be $158,100.
SanCon’s proposal of $158,100 also includes traffic control, field measurements,
surface preparation, removal and elimination of deteriorating existing steps, mortar
repair and chemical grout injection to prevent infiltration.
Staff is requesting authorization to enter into an agreement with SanCon at a not-to-
exceed cost of $158,100 plus a 15% contingency.
FISCAL ANALYSIS:
Sufficient funding has been allocated in the Fiscal 2008-09 Sewer Capital
Improvement Fund Project Account 20400230 (Sewer Localized and Emergency
Repairs).
ATTACHMENTS:
1. Proposal submitted by SanCon Engineering Inc.
2. Map of project locations
MOTION:
That the City Council:
1. Approve an agreement with SanCon Engineering, Inc. to rehabilitate 27 sewer
manholes at a cost not to exceed $158,100; and,
2. Authorize the Public Works Director/City Engineer to negotiate change orders, if
necessary, not to exceed $23,715 (15% contingency); and City of Culver City, California
City Council Agenda Item Report
3. Authorize the City Attorney to review/prepare the necessary documents; and,
4. Authorize the City Manager to execute such documents on behalf of the City.
MEETING DATE: 2/9/09
AGENDA ITEM:
Authorization to Enter Into an Agreement with San Con
Engineering Inc. to Rehabilitate Sewer Manholes
Throughout Culver City
ATTACHMENTS
Pages|109| Proposal submitted by SanCon Engineering, Inc. 1|109| Map of project locations 2SANCON ENGINEERING, INC.
GENERAL ENGINEERING CONTRACTOR
Tel: (714) 891-2323
STATE CONTRACTORS LICENSE #731797
Fax: (714) 891-2524
SANCON PROPOSAL SCOPE
This bid includes the following:
• Confined Space Entry Procedures and Equipment
• Prevailing wage / Certified Payroll
• Traffic Control including plans and permits as required
• Field Measurement
• Surface preparation
• Removal of Existing Steps
• Bench Rehabilitation
• Mortar Repair
• Chemical Grout Injection to stop infiltration
• Installation of Polytriplex CIPP Epoxy Fiberglass Manhole Rehabilitation System
• 10 Year Warranty on Materials and workmanship
Bid: 9138
Assumptions:
• Water for our work will be available from the nearest City hydrant (with City provided water meter)
• Work hours on non-major roadways 8AM to 5 PM
• Manhole depths are measured from F&C to bottom of invert
This bid excludes the following:
• Night Work
• Survey to locate manholes or Access arrangements & Permission to access work areas
• SWPCP plans or BMP's
Pricing Structure:
• Manhole Rehabilitation 3 & 4' Dia:
$ 525.00/ VF
• Manhole Rehabilitation 5' Dia:
$ 575.00/ VF
• Replacement of manhole F&C in concrete:
$ 1,000.00/ EA
We appreciate the opportunity to provide you this proposal and would be glad to answer any questions
you might have regarding Sancon Engineering or the Polytriplex product.
Respectfully Submitted,
Chuck Parsons
Sancon Engineering, Inc
9138 5841 Engineer Drive
Huntington Beach, CA 92649CULVER CITY
MANHOLE REHABILITATION
PROJECT
Syd Kroenthal Park
(5)
Culver Center
(4)
.„
„
4343 Duquesne Ave.
(2)
10915 Washington Blvd.
(1)
4315 Jackson
(2)
4460 Sepulveda Blvd.
(1)
4520 Sepulveda Blvd.
(1)
Cota & Rhoda
(6)
Mesmer Pump Station
(4) _