Title: PUBLIC HEARING - FOUR AFFIRMATIVE VOTES REQUIRED – (1) Award of Various Contracts for the Completion of the Construction of Fire Station No. 3 Project, P-857; and (2) Approval of an Amendment to the Existing Professional Services Agreement with RTI Consulting, Inc. for Construction Management Services for the Fire Station No. Project, P-857.
Attachments: 1. PUBLIC HEARING - FOUR AFFIRMATIVE VOTES REQUIRED – - PH-2__10-05-10__PW-ENG__CITY COUNCIL__Award FS #3 Contracts & RTI Agreement - FINAL.doc, 2. PUBLIC HEARING - FOUR AFFIRMATIVE VOTES REQUIRED – - 10-05-10_Public_Hearing_FireStationNo3.pdf
City of Culver City, California Agenda Item Report Meeting Date: 05/10/2010 Item Number: PH-2 CITY COUNCIL AGENDA ITEM: PUBLIC HEARING - FOUR AFFIRMATIVE VOTES REQUIRED – (1) Award of Various Contracts for the Completion of the Construction of Fire Station No. 3 Project, P-857; and (2) Approval of an Amendment to the Existing Professional Services Agreement with RTI Consulting, Inc. for Construction Management Services for the Fire Station No. Project, P-857. Contact Person/Dept.: Andy O’Connell/PW Phone Number: (310) 253-5606 Fiscal Impact: Yes [X] No [] General Fund: Yes [X] No [] Public Hearing: [X] Action Item: [] Attachments: [X] Commission Action Required: Yes [] No [X] Date: _______________ Public Notification: Published in the Culver City News (04/29/10 and 05/06/10(E-Mail) Agenda and Meetings – City Council (05/06/2010) Department Approval: Charles D. Herbertson (04/29/10) City Attorney Approval: Carol Schwab (by H. Baker) (04/29/10) Chief Financial Officer Approval: Jeff Muir (by N. Kimball) (05/05/10) City Manager Approval: P. Lamont Ewell (05/06/10) RECOMMENDATION Staff recommends the City Council: 1. Award various contracts as set forth in this report for the completion of the construction of Fire Station No. 3 Project, P-857 (the “Project”) in a total amount not-to-exceed $111,000 (requires four affirmative votes). 2. Approve an amendment to the existing Professional Services Agreement with RTI Consulting, Inc. for construction management services for the Fire Station No. Project, P-857. BACKGROUND On March 1, 2010, the City Council and Redevelopment Agency terminated, for convenience, the contract with FEI. The staff report and minutes excerpts related to that action is attached for the City Council and Agency Board’s information. DISCUSSION Attachment 1 identifies a list of the scope of work needed to complete construction and the recommended contractors and their estimated bids. This work includes all City of Culver City, California Agenda Item Report items needed to complete construction of the Project. Along with the work not performed by FEI, there are other items that are being requested by the Fire Department. As set forth in the attachment, there are thirteen different contractors needed to complete all of the necessary work for an estimated total construction cost not-to-exceed $111,000.00. Other charges that have not been included are the costs for the final interior and exterior cleaning and the cost to move equipment and furniture from the existing Fire Station No. 3. Since a general contractor will not be utilized, each of the individual contractors will be considered as a “prime contractor.” Fifteen percent of the total construction cost that is normally charged by a general contractor for overhead and profit will be saved by hiring individual contractors. However, the City’s construction manager will then need to assume some of the duties that would normally be associated with a general contractor, such as coordinating and supervising the work. The proposal from RTI Consulting, Inc. to complete the Project as construction manager is provided as Attachment 2. Staff is recommending that the City utilize those subcontractors who have performed satisfactorily on various aspects of the Project and hire additional subcontractors where necessary to complete work that was not completed by the former prime contractor, FEI. By using the original subcontractors when possible, the warranty on their original work will be kept intact. For these reasons, as well as the need to get the new Fire Station No. 3 open and operating after the substantial delay caused by the former prime contractor FEI, staff is recommending this expedited process. The City Charter provisions regarding public works contracts|1010| give the City Council the authority, with four affirmative votes, to award a contract without complying with the bidding procedures, provided a public hearing is held on the award of the contracts and after public notice has been given. Notice of this public hearing was published in the Culver City News on April 29 and May 6, 2010. It should be noted that the original contract with FEI was issued by both the City and the Redevelopment Agency. That contract provided that the Agency would fund up to $3,000,000 of the construction costs, with the remainder funded by the City. The work completed under the FEI contract exceeded the $3,000,000 funded by the Agency. Therefore, these contracts to complete the work are proposed to be awarded by the City Council and funded solely by the City through the General Fund appropriation made by the City Council at the time the original contact was awarded in 2007. Staff is also recommending extending the contract with RTI Consulting, Inc. to prepare the necessary scope of work, manage the construction, and coordinate the close-out documentation and final payment processes in order to fully bring closure |1010| Charter Section 2007 provides that the procedures for awarding public works contracts as set forth in the “old” Charter will remain in effect until such time as the City Council establishes, by ordinance, different procedures. Therefore, the current procedures are set forth in the “old” Charter Section 1304. City of Culver City, California Agenda Item Report to this Project. The aggregate contract amounts for the remaining work will not exceed the amount of funds remaining in the Project account. FISCAL ANALYSIS In addition to the original retention amount of $499,788.04, which is currently held in an escrow account, there is approximately $370,000 remaining in the Fire Station No. 3 project budget (42000857). The City may authorize a release in the amount of $427,483.63 for retention payments, after all legal obligations have been met by FEI, including the clearance of all stop notices. This will leave a total remaining budget of approximately $440,000 which will be used to complete any remaining work and other contractual obligations. ATTACHMENTS 1. Staff report and Minute Excerpt from the March 1, 2010 City Council/Redevelopment Agency Meeting 2. List of recommended contractors and estimated bid amounts for all work needed to complete construction of the Project. 3. RTI Consulting, Inc. Proposal dated April 20, 2010. MOTIONS That the City Council: 1. Award the various contracts as set forth in Attachment 1 in a total amount not to exceed $111,000.00 (requires four affirmative votes); and, 2. Approve an amendment to the existing professional services agreement with RTI Consulting, Inc. for Construction Management Services for the Fire Station No.3 Project for an additional not-to-exceed amount of $25,335.00; and, 3. Authorize the Public Works Director/City Engineer to increase the RTI Consulting Inc. agreement by an amount not to exceed $5,000.00, if necessary; and, 4. Authorize the City Attorney to review/prepare the necessary documents; and 5. Authorize the City Manager to execute such documents on behalf of the City. 5/10/10 JOINT CITY COUNCIL/REDEVELOPMENT AGENCY BOARD AGENDA ITEM: (1) PUBLIC HEARING (FOUR AFFIRMATIVE VOTES REQUIRED) — Award of Various Contracts for the Completion of the Construction of Fire Station No, 3 Project, P- 857; (2) Approval of an Amendment to the Existing Professional Services Agreement with RTI Consulting, Inc. for Construction Management Services for the Fire Station No. 3 Project, P-857; and (3) Redevelopment Agency Board Authorization to Reimburse the City for Fifty Percent of the Total Cost of the Remaining Work. MEETING DATE: AGENDA ITEM: ATTACHMENTS|109| List of recommended contractors and estimated bid amounts for all work needed to complete construction of the Project|109| RTI Consulting, Inc. Proposal dated April 20, 2010 3 March 1, 2010 City Council/Redevelopment Agency Joint Agenda Item: (1) Termination of the Contract with FEI Enterprises, Inc., for the construction of Fire Station No. 3, Project P-857, (2) Authorization to File a Notice of Cessation, and (3) Authorization to Release a Portion of the Project Retention Funds. (without attachments) and Minutes Pages 1-2 3-4 5-8CULVER CITY FIRE STATION NO. 3 List of Recommended Contractors and Estimated Bid Amounts for All Work Needed to Complete Construction of the Project ITEM NUMBER Item 1 DESCRIPTION OF ITEM Miscellaneous electrical rework; install IWO single door map cases; replace sheet metal downspouts with cast iron piping; install ceiling fans; provide stucco wood framing repair to parapet wall at top landing of exterior stairway; and instail new BBQ RECOMMENDED CON1RACTOR / versictok Precision One ESTIMATED BID - AMOUNT $ 10,000 Item 2 Add railing to parapet wall at top landing of exterior stairway; add bends to stairway hand rails; and install prefabricated ladder for roof access V.I.P. Iron Works, Inc. $ 3,000 Item 3 Purchase two single door map cases Poblocki Sign Company' Item 4 . Remove and replace concrete slabs in many areas due cracking caused by improper joint control; install concrete landing at rear kitchen • door; and install proper curb cut at southerly landscape area adjacent to main driveway li American Qua ty Builders $ 37000 Item 5 PurchaseTurbo STS 4 burner BBQ Barbeques Galore*** Item 6 Remove and replace incorrect roof patches and install new densdeck and tapered insulation at low roof on north side of second floor Westway Construction Inc. ' Item 7 Furnish and install television mounts at various Haas Entertainment nment Item 8 + Provide and install pedestrian gate lock protection and electrical interface with swing gate at north driveway C & H Gates • 1,600 Item 9 Uncover and correct wiring defects along irrigation piping; connect system to Calsense control panel; investigate and correct low pressure flows at north and east side of project; and perform landscape maintenance American Gardens (Estimate) 15,000 Item 10 Install soap dispensers in bathroom areas Stumbaugh' $ 300 Item 11 Install glass doors in day room cabinets Precision One $ 1,500 It 12 em Install proper wiring in rear kitchen door and connect to Hirsch pad system Master Technology Integrators, Inc.*** $ 1 , 200 em It 13 Attic Stock not furnished by FEI. Items to be determined by Maintenance Facilities Staff TBD ' 3 500 , ,•,,, ,.__ 'Original subcontractor to FEI on Fire Station No. 3Item 16 Aili 111111111.111111111 Item 17 Item 18 Item 19 Purchase replacement dedication plaque at entry H. Toji & Company*" Item 20 ' CULVER CITY FIRE STATION NO. 3 List of Recommended Contractors and Estimated Bid Amounts for All Work Needed to Complete Construction of the Project ITEM NUMBER DESCRIPTION OF ITEM RECOMMENDED CONTRACTOR! VENDOR ESTIMATED BID AMOUNT 2,100 Grand Total Trade/Vendor Costs : *" Original Subcontractor to FEI on Fire Station No. 3 111,000Consulting, Inc. April 20, 2010 City of Culver City Public Works Department Engineering Division, 2 nd floor P.O. Box 507 9770 Culver Boulevard Culver City, California 90232-0507 Attu: Andy O'Connell, Senior Civil Engineer RE: Culver City Fire Station NO. 3 New Construction Project Construction Management Services — Work to Complete Scope Dear Andy: At your request MI Consulting Inc_ has prepared a proposal for assisting the City in addressing the work required to be completed at the Culver City Fire Station No. 3 Construction Project in order to allow for the Fire Department to fully occupy the new facility. Based upon the work to complete list prepared by RTI Consulting updated February 2, 2010, our plan is to go out to the responsible trades who performed satisfactorily on various aspects of the fire station project. We would secure their commitment on schedule and cost to complete the items identified in the completion list. Where no trade was utilized in the original construction, our plan is to reach out to specific trades, formalize a proposal for work to be performed directly for the CCPW and then follow the process through completion and acceptance by the CCPW and CCED. Please note that each trade will become "Prime Contractors" and the process of Construction is "CM with Multi-Primes". Once the work has been accepted by the required agencies, we would coordinate the close-out documentation and final payment processes in order to hilly bring closure to this project. We have under separate cover attached the Exhibit "B" for the construction management services to be provided for this project. We are comfortable that once released to proceed we will be able to move the process forward in a consistent and timely manner Sincerely, RTI Consulting Inc. Robert E. Neiwirth Principal Cc: Culver City Fire Station No. 3 8325 McConnell Avenue Westchester, CA 90045 Tel: 310.670.5977 c-Fax: 310.919.3030 www.rti.comConstruction Management Services Based upon 8 week period from Council release to completion Culver City Fire Station No. 3 Work to Complete CM Service Schedule Fee Computation Work to Complete List Prepare Proposal scopes of work and Contract agreements for work to be completed. Attend council meetings as required for approvals. Perform Daily Job walks/Document progress. Prepare weekly project schedules identifying work to be performed and coordination with City departments Coordinate Contractor requirements with City Agencies If Certified Payroll documentation required from trades, provide monitoring and managing paperwork from each trade Review Payment Applications and prepare Recommendations, Review Waivers and Lien releases Coordinate with Testing & Inspection agencies Review and distribute Submittals, RPI"s and Completion lists Close-out documentation & Final Payment processes Totals for CM Services to complete tasks Assumptions: I This Consultant will not provide fulltime staff to this project nor maintain an onsite office. To do so would require a modification to this exhibit. 2 Reporting requirements are reduced to specific reports on progress, issues, changes and/or completion., 3 Each Prime Contractor has the responsibility for site safety, has not based their costs on prevailing wage compliance, they have based their costs on quality workmanship. Spreadsheet of CM Services Page 1 of 1|10101010101010|8Agendas Public Notification: (E-Mail) Meetings and . Enterprises, Inc. (02/24/10) Commission Action Required: Yes [] No [X] Department Approval: Charles Herbertson (02/23/10) Chief Financial Officer ApprOS/ 01 Mark Scott (by N Kimball) (02123/10) City Attorney Approval: Carol Schwab (by H. Baker) (02/23/10) Agency General Counsel: Murray Kane (02/24/10) City Manager/Executive Di Approval: (02/24/10) City of Culver City, California Agenda Item Report Meeting Date: 03/0112010 Item Number: J-1 CITY COUNCIL I REDEVELOPMENT AGENCY JOINT AGENDA ITEM- (1) ion to Release a Portion of the Project R'eitnec. otifoo a Notice of Cessation, . n r the n d e s . . and (3) n o. , Project P-857, i Authorization onstruction of Fire Station of the Contract with FEI Enterprises Termination - Author' t- - — , ‘2) Auth - - to File N 3 iza :•••••::.••••••••• •••••••••• ••••• •• ••••, • • • Phone Number: (310) 253-5606 Fiscal Impact: [X] General Fund' [Xi Public Hearing' . Action Item: [Xi ,Mtagnmentspc]:::: RECOMMENDATION: Staff recommends that the City Council 1) terminate the contract with FEI Enterprises, Inc. for the construction of Fire Station No. 3, Project P-857; 2) authorize the filing of a Notice of Cessation; and 3) authorize the release of a portion of the retention after the expiration of the 35-day lien period and the clearance of all stop notices. Staff recommends that the Redevelopment Agency Board terminate the contract with FEI for the construction of Fire Station No. 3, RDA Project (55393700). BACKGROUND: On June 18, 2007, at a joint City Council/Redevelopment Agency meeting, FEI Enterprises, Inc. ("FEI") was awarded a contract for the construction of the new Fire Station No. 3 located at 6030 Bristol Parkway (the "Project"). Work started on the Project on August 7, 2007, with a contract duration of 345 days and formal completion date of July 16, 2008. During the first year of work, the contract duration was formally extended to September 11, 2008 due mostly to rain delays. Between January 9, 2009 and February 18, 2009, after the untimely death of the City's construction manager, work on the Project was suspended. Upon recommencement of the work, FEI provided the City with assurances the Project would be completed by the end May 2009. Despite the fact that this "new"City of Culver City, California Agenda Item Report completion date was eight months after the last approved completion date (September 11, 2008), FEI was unable to complete the Project by the May 2009 deadline and continued providing the City with new completion dates that were never met. Finally, in November 2009, the City informed FEI that the Project must be completed by December 11, 2009, and the cost of all unfinished work would be deducted from their final payment. On December 28, 2009 a formal letter (Attachment 1) was sent to FEI stating the Project was substantially complete on December 11, 2009 and the cost of all corrective work (Attachment 2) would be submitted to FEI as a deductive change order. On February 9, 2010, the deductive change order was mailed to FEI by certified mail and was received by FEI on Thursday February 11, 2009 (Attachments 3 and 4). FEI was instructed to review and sign the deductive change order within five days of its receipt. Liquidated damages of approximately $385,000 ($1,000 per day) for Project delay were also included in the deductive change order as allowed in the contract documents. Staff has calculated an increase in contract time of 61 days which reflects all of the reasonable delays, beyond September 11, 2008, caused by the temporary shutdown, rain, and change order work (Attachment 5). Subtracting the deductive change order amount of $358,860.21 from the remaining FEI contract balance of $296,519.77 leaves FEI owing the City $62,340.44. FEI has declined to sign the deductive change order. DISCUSSION: In order to release the undisputed retention funds and move forward with the completion of the final corrective work and complete the Project, staff recommends the City and Agency terminate the contract with FEI for convenience per Section 14.4 of the contract documents (Attachment 6). Subsection 14.4.3 of the contract documents states that the contractor is entitled to reasonable overhead and profit on work not executed. Applying a 15% rate on the estimated cost to complete the unfinished work ($94,250.00), the overhead and profit amount is determined to be $14,137.50. Subtracting that amount from the $62,340.44 that FEI owes the City, leaves a balance due to the City of $48,202.94. The provisions of the contract documents, as well as State Law, allow the City to withhold 150% of the disputed amount from the retention funds, which amounts to $72,304.41. Staff recommends the City Council authorize the release of a portion of the retention (less 150% of the disputed amount) in the amount of $427,483.63 after the expiration of the 35-day lien period and clearance of all stop notices FISCAL ANALYSIS: In addition to the original retention amount of $499,788.04, which is currently held in an escrow account, there is $370,763 remaining in the Fire Station No. 3 project budget (42000857). The City may authorize release of the $427,483.63 retention payment, after all legal obligations have been met by FEI, including the clearance ofCity of Culver City, California Agenda Item Report all stop notices. This will leave a total remaining project budget of approximately $440,000 which will be used to complete any remaining work and other contractual obligations. Staff expects the final Fire Station No. 3 Project to be completed under budget due primarily to the liquidated damages charged against FEI due to Project delays. ATTACHMENTS: 1. Substantial Completion Letter, dated December 28, 2009 2. Estimated Cost to Complete Work 3. Deductive Change Order Letter, dated February 9, 2010 4. Deductive Change Order 5. Liquidated Damages Calculation 6. Section 14.4 of Contract documents MOTION: That the City Council: 1. Terminate the contract with FEI Enterprises, Inc. for the construction of Fire Station No. 3, Project P-857 per Section 14.4 of the contract documents; and, 2. Authorize the City Attorney to review/prepare the necessary documents; and, 3. Authorize the City Manager to execute such documents on behalf of the City; and 4. Authorize the City Manager to execute the Notice of Cessation and submit it to the Los Angeles County Recorder's office; and, 5. Authorize the release of a portion of the retention (less 150% of the disputed amount) in the amount of $427,483.63 following the expiration of the 35-day lien period and the clearance of all stop notices. That the Redevelopment Agency Board: 1. Terminate the contract with FEI Enterprises, Inc. for the construction of Fire Station No. 3, Project P-857 per Section 14.4 of the contract documents. 2. Authorize the Agency General Counsel to review/prepare the necessary documents; and, 3. Authorize the Executive Director to execute such documents on behalf of the City. March 1, 2010 Joint Item Item J-1 (1) Termination of the Contract with FEI Enterprises, Inc. for the Construction of Fire Station No. 3, Project P-857, (2) Authorization to File a Notice of Cessation, and (3) Authorization to Release a Portion of the Project Retention Funds. Discussion ensued between the City Council and staff regarding a suggestion to examine the way contracts are awarded; concern with awarding to the lowest bidder and clarification that the City awards to the lowest responsible bidder; and a suggestion to more clearly define the word responsible in terms of contract evaluation. MOVED BY COUNCILMEMBER MALSIN, SECONDED BY MAYOR WEISSMAN AND UNANIMOUSLY CARRIED, THAT THE CITY COUNCIL: 1.TERMINATE THE CONTRACT WITH FEI ENTERPRISES, INC. FOR THE CONSTRUCTION OF FIRE STATION NO. 3, PROJECT P-857 PER SECTION 14.4 OF THE CONTRACT DOCUMENTS; 2.AUTHORIZE THE CITY ATTORNEY TO REVIEW/PREPARE THE NECESSARY DOCUMENTS; 3.AUTHORIZE THE CITY MANAGER TO EXECUTE SUCH DOCUMENTS ON BEHALF OF THE CITY; 4.AUTHORIZE THE CITY MANAGER TO EXECUTE THE NOTICE OF CESSATION AND SUBMIT IT TO THE LOS ANGELES COUNTY RECORDER'S OFFICE; AND 5.AUTHORIZE THE RELEASE OF A PORTION OF THE RETENTION (LESS 150% OF THE DISPUTED AMOUNT) IN THE AMOUNT OF $427,483.63 FOLLOWING THE EXPIRATION OF THE 35-DAY LIEN PERIOD AND THE CLEARANCE OF ALL STOP NOTICES. o0o|1013|