eComments During Meetings: When available, click here to submit eComments during a live meeting | Attendees must register here to attend all virtual meetings.

File #: 25-400    Version: 1 Name: Award of Contract in the Amount of $618,400.56to Houston and Harris PCS Inc., as the Lowest Responsive and Responsible Bidder, for the Citywide Sewer Main CCTV and Condition Assessment (Phase I) Project, PZ-230
Type: Minute Order Status: Consent Agenda
File created: 10/9/2024 In control: City Council Meeting Agenda
On agenda: 11/11/2024 Final action:
Title: CC - CONSENT ITEM: (1) Award of Contract in the Amount of $956,800 to Pipe Tech, Inc., as the Lowest Responsive and Responsible Bidder, for the Citywide Sewer Main CCTV and Condition Assessment (Phase I) Project, PZ-230; and (2) Authorization to the Public Works Director/City Engineer to Approve Change Orders in an Amount Not-to-Exceed $239,200.
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

title

CC - CONSENT ITEM: (1) Award of Contract in the Amount of $956,800 to Pipe Tech, Inc., as the Lowest Responsive and Responsible Bidder, for the Citywide Sewer Main CCTV and Condition Assessment (Phase I) Project, PZ-230; and (2) Authorization to the Public Works Director/City Engineer to Approve Change Orders in an Amount Not-to-Exceed $239,200.

 

body

Meeting Date:                                          November 11, 2024

 

Contact Person/Dept.:                     Hong Wang, Public Works Department/Engineering Division

 

Phone Number:                                          (310) 253-5604

 

Fiscal Impact:                     Yes [X]    No [  ]                     General Fund:                     Yes [  ]     No [X]

 

Attachments:                     Yes [  ]     No [X]

 

Public Notification:                     E-Mail: Meetings and Agendas - City Council (11/07/2024)  

 

Department Approval:                     Yanni Demitri, Public Works Director / City Engineer (10/28/2024)

_____________________________________________________________________

 

 

RECOMMENDATION

 

Staff recommends the City Council (1) award a contract in the amount of $956,800 to Pipe Tech, Inc., as the lowest responsive and responsible bidder, for the Citywide Sewer Main CCTV and Condition Assessment (Phase I) Project, PZ-230; and (2) authorize the Public Works Director/City Engineer to approve change orders in an amount not-to-exceed $239,200.

 

 

BACKGROUND

 

As the City’s sanitary sewer collection system ages, the risk of potential failure increases. Issues of concern include collapse, tree root blockage, overflow, and other potential service interruptions.  Closed circuit television (CCTV) inspection services are used to assess the condition of the sewer pipe systems and to identify and prioritize rehabilitation and maintenance projects.  Sewer system condition assessment by CCTV is required by the City’s Sewer System Maintenance Plan (SSMP).

 

The City maintains 89 miles of sanitary sewers.  Under this proposed work, about 50 miles of City sewer mains and about 1,200 manholes will be inspected and rated on their condition using industry established standards.  The remaining sewer mains will be inspected in the upcoming years.  The specifications for the project have been prepared by the Engineering Division staff.

 

The citywide sewer system was last inspected by video in 2010-2012.  As a result of the inspection efforts, the City rehabilitated approximately 35 miles of sewer mains in subsequent years, especially those located in backyard easements.  This has greatly reduced required maintenance and the occurrence of sewage overflow.

 

On May 28, 2024, the City Council approved the project plans and specifications and authorized staff to publish a Notice Inviting Bids.

 

 

DISCUSSION

 

A Notice Inviting Bids was published on Culver City PlanetBids website on September 19, 2024.  Bid opening date was on October 17, 2024.  Three contractors responded with the following bid amounts:

 

CONTRACTOR                                                                                                BID AMOUNTS

 

1. Pipe Tech, Inc.                                                                                                          $   956,860

2. National Plant Services                                  $2,097,001

3. Pipe and Plant Solutions, Inc.                                                               $3,375,400

 

Staff reviewed the bid documents and determined Pipe Tech, Inc. submitted the lowest responsive total base bid.  The Engineer’s estimate for the project is $750,000.  Staff reviewed the bid proposal from Pipe Tech, Inc. and found the bid documents responsive and complete.  Its bid bond, contractor’s license, and worker’s compensation insurance were reviewed and determined to meet City requirements.  Pipe Tech, Inc. has completed similar projects for the City of Los Angeles and other southern California cities with satisfactory performance.

 

A proposed construction contingency amount of $239,200 (25%) is requested for unforeseen conditions and to allow for additional sewer main inspection as identified by the City. The management of the project will be conducted by the Public Works Department / Engineering Division.

 

 

FISCAL ANALYSIS

 

The Adopted Budget for Fiscal Year 2024-2025 includes funding for the City Sewer Main CCTV and Condition Assessment (Phase I) Project in the amount of $1,196,000 including contingency funds in the amount of $239,200 in CIP Project PZ-230 (Sewer Enterprise Fund - Sewer Local & Emergency Repair), which can be found in the Capital Improvements section of the budget in Fund 204 (Sewer Enterprise Fund) on page 477 of the budget book.

 

Project Budget

PZ-230 (Fund 204)                                                                                                                                                      $1,209,300

 

 

Estimated Project Expenses

Citywide Sewer Main CCTV Phase I, PZ-230                                                                                     $  956,860

Contingency (25%)                                                                                                                                                                        $  239,200

                                                                                                                              Total estimated expense:   $1,196,060

 

 

ATTACHMENTS

 

None

 

 

MOTIONS

 

That the City Council:

 

1)                      Award a contract to Pipe Tech, Inc., as the lowest responsive and responsible bidder, for the Sewer Main CCTV and Condition Assessment (Phase I) Project, PZ-230, in the amount of $956,800;

 

2)                      Authorize the Public Works Director/City Engineer to approve change orders in the amount not-to-exceed $239,200,

 

3)                      Authorize the City Attorney to review/prepare the necessary documents; and,

 

4)                      Authorize the City Manager to execute such documents on behalf of the City.