Title:
|
(1) Acceptance of Work Performed by Republic Intelligent Transportation Services, Inc. (2) Authorization to File a Notice of Completion; and (3) Authorization to Release the Retention Payment after the Expiration of the 35-day Lien Period for the Upgrade of Traffic Signal Preemption Devices at Various Locations, P-882, Federal Aid No. ITS 05–5240 (014).
|
City of Culver City, California
Agenda Item Report
Meeting Date: 07/12/2010 Item Number: C-5
CITY COUNCIL AGENDA ITEM: (1) Acceptance of Work Performed by Republic
Intelligent Transportation Services, Inc. (2) Authorization to File a Notice of
Completion; and (3) Authorization to Release the Retention Payment after the
Expiration of the 35-day Lien Period for the Upgrade of Traffic Signal Preemption
Devices at Various Locations, P-882, Federal Aid No. ITS 05–5240 (014)
Contact Person/Dept.: Hong Wang/PW Phone Number: 310-253-5604
Fiscal Impact: Yes [X] No [] General Fund: Yes [X] No []
Public Hearing: [] Action Item: [] Attachments: []
Commission Action Required: Yes [] No [X] Date: _______________
Public Notification: (E-Mail) Agenda and Meetings – City Council (07/7/2010); (Email)
Republic Intelligent Transportation Services, Inc. (07/6/10)
Department Approval:
Charles D. Herbertson(06/30/10)
City Attorney Approval:
Carol Schwab (by H. Baker) (07/07/10)
Chief Financial Officer Approval:
Jeff Muir (by N. Kimball) (07/07/10)
City Manager Approval:
P. Lamont Ewell (07/08/10)
RECOMMENDATION:
Staff recommends the City Council: (1) accept the work performed by Republic
Intelligent Transportation Services, Inc. (Republic ITS),; (2) authorize filing a Notice
of Completion; and (3) authorize the release of the retention funds in the amount of
$18,286.44 after the expiration of the thirty-five day lien period for the Upgrade of
Traffic Signal Preemption Devices at Various Locations, P-882, Federal Aid No. ITS
05 – 5240 (014).
BACKGROUND:
On January 25, 2010, the City Council awarded a construction contract with
Republic ITS for the upgrade of the City’s fire preemption components at 44 of 100
signalized intersections within the City. Traffic signal preemption devices provide
priority to emergency vehicles to go through signalized intersections in a safe
manner in order to reduce response time.
DISCUSSION:
Republic ITS successfully completed the work in accordance with the contract
specifications. The construction management and inspection were performed by
Public Works Department Staff.
City of Culver City, California
Agenda Item Report
The City Council approved a $3,589 contingency contract amount. A change order
in the amount of $3,239.40 was approved for quantity adjustments and to provide
preemption emitters for the City’s fire trucks.
FISCAL ANALYSIS:
Project Budget
Funding Source Amount
Intelligent Transportation System federal
funds (42300882)
$78,228
SAFETEA-LU federal funds (42300882)
$23,037
Playa Vista Mitigation Funds (42000882) $82,172
Capital Improvement and Acquisition Fund
(42000882)
$25,000
Total $208,437
Final Project Expenses
Original Construction Contract Amount
$179,625.00
Change Order $3,239.40
Final Construction Contract Amount $182,864.40
As part of the original project budget, $25,000 was appropriated from the General
Fund to supplement grant and developer mitigation funding. Since the project was
completed under budget projections, the General Fund appropriation will not be
expended and will return to the fund balance.
MOTIONS:
That the City Council:
1. Accept the work performed by Republic ITS for the Upgrade of Traffic Signal
Preemption Devices at Various Locations, P-882, Federal Aid No. ITS 05–
5240 (014); and,
2. Authorize the Public Works Director/City Engineer to execute the Notice of
Completion and submit it to the Los Angeles County Recorder’s Office for
recordation; and,
3. Authorize the release of $18,286.44 in retention to Republic ITS after the
expiration of the 35-day lien period.