Title: (1) Acceptance of Work Performed by Peterson-Chase General Engineering Construction, Inc.; (2) Authorization to File a Notice of Completion; and (3) Authorization to Release the Retention Payment in the Amount of $3,618.31 after Expiration of the 35-Day Lien Period, for the Construction of the Duquesne Avenue Bridge Expansion Joint Repair Project, PZ-938.
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

title

(1) Acceptance of Work Performed by Peterson-Chase General Engineering Construction, Inc.; (2) Authorization to File a Notice of Completion; and (3) Authorization to Release the Retention Payment in the Amount of $3,618.31 after Expiration of the 35-Day Lien Period, for the Construction of the Duquesne Avenue Bridge Expansion Joint Repair Project, PZ-938.

 

body

Contact Person/Dept: Hong Wang/PW

Phone Number:  310.253.5604

 

Fiscal Impact:  Yes [x]    No []                                                                             General Fund:  Yes [x]     No []

 

Public Hearing:  []                               Action Item:                     []                        Attachments:   Yes []     No [x]   

 

Commission Action Required:     Yes []     No []    Date:

Commission Name:          

 

Public Notification:   (E-Mail) Meetings and Agendas - City Council (3/25/16)  

 

Department Approval:                     Charles D. Herbertson, P.E. Public Works Director/City Engineer (3/18/16)

______________________________________________________________________

 

RECOMMENDATION

 

Staff recommends the City Council accept the work performed by Peterson-Chase General Engineering Construction, Inc., authorize the filing of a Notice of Completion, and authorize release of the retention payment in the amount of $3,618.31 after expiration of the 35-day lien period for the construction of Duquesne Avenue Bridge Expansion Joint Repair Project, PZ-938.

 

 

BACKGROUND/DISCUSSION

 

On August 24, 2015 the City Council awarded the construction contract to Peterson-Chase General Engineering Construction, Inc. in the amount of $70,440.00 for the construction of Duquesne Avenue Bridge Expansion Joint Repair Project, PZ-938.  The project included the replacement of the deteriorated bridge expansion joint steel plates and pavement transition.

 

The Contractor successfully completed the project in January 2016, within budget and contract time. To minimize the construction impact to traffic, the repair was conducted during several Saturdays and at least one lane was open to traffic during construction. One change order in the amount of $4,866.10 was issued to account for the additional traffic control cost to maintain the street open to traffic during construction.

 

Construction management and general inspection was provided by Public Works Engineering Division staff.  The deputy inspection for steel welding work was provided by RTI Consulting, which was selected through the list of on-call consultant firms pre-approved by the City Council.  

 

 

FISCAL ANALYSIS

 

Project Budget

Citywide Bridge Repairs (PZ-938 Fund #420)                     $79,525.00

Pavement Improvement (PZ-863 Fund #420)                     $  8,000.00

Total Available Funds                                                                                    $87,525.00

 

Final Project Expenses

Final Construction Amount                                                                                    $ 67,500.00

Change Order #1                                                                                                         $   4,866.10

Deputy Inspection for Steel Work                                                               $   3,588.00

Total Final Project Expenses                                                               $ 75,954.10

 

 

ATTACHMENTS

 

None.

 

 

RECOMMENDED MOTION(S)

 

That the City Council:

 

1)                     Accept the work performed by the contractor, Peterson-Chase General Engineering Construction, Inc., for the Construction of the Duquesne Avenue Bridge Expansion Joint Repair Project, PZ-938; and,

 

2)                     Authorize the Public Works Director/City Engineer to execute the Notice of Completion and submit it to the Los Angeles County Recorder’s Office for recordation; and,

 

3)                     Authorize the release of $3,618.31 in retention funds to Peterson-Chase General Engineering Construction, Inc., following the expiration of the 35-day lien period.