City of Culver City, California
City Council Agenda Item Report
RECOMMENDATION:
Staff recommends the City Council award a contract to ICE Engineering, Inc., as
the lowest responsive and responsible bidder, for the Pedestrian Islands
Modification Project, P-915 (CDBG #601085-08).
BACKGROUND:
The adopted 2008-09 Capital Improvement Budget includes the Pedestrian
Islands Modification Project, P-915 (CDBG #601085-08) located at the
intersection of Overland Avenue and Jefferson Boulevard to enhance the path of
travel for sight-impaired pedestrians through the existing raised channelized
islands. This project has been endorsed by the Disability Advisory Committee.
The project will reconstruct a portion of the raised islands with a new concrete
passageway to provide improved channelized/directional cues for sight-impaired
pedestrians.
This is a Community Development Block Grant project which was approved by
the City Council in January 2008 per the recommendation of the Community
Development Block Grant Advisory Committee.
DISCUSSION:
The Project was advertised for construction bids and on March 12, 2009, the
Deputy City Clerk publicly opened bids. Five (5) contractors responded with the
following bid amounts:
Meeting Date: 4/13/09 Item Number: C-6
AGENDA ITEM: Award of a Contract to ICE Engineering Inc., for the Pedestrian
Islands Modification Project, P-915 (CDBG #601085-08)
Contact Person/Dept.: Lee Torres/Public
Works Department
Phone Number: 310.253.5623
Fiscal Impact: Yes [X] No [] General Fund: Yes [x] No []
Public Hearing: [ ] Action Item: [] Attachments: [X]
Public Notification: Master E-Mail Notification List (04/08/09); Tom Crabson, CDBG Labor
Compliance Officer, ICE Engineering Inc., Excel Paving Company, DG Yeager
Construction Co., Shawnan, and VAP Construction Inc. via fax April 2
nd
.
Department Approval:
Charles D. Herbertson (04/02/09)
City Attorney Approval:
Carol Schwab (by H. Baker) (04/07/09)
Chief Financial Officer Approval:
Jeff Muir (by N. Kimball) (04/08/09)
City Manager Approval:
Jerry B. Fulwood (04/08/09) City of Culver City, California
City Council Agenda Item Report
Contractor Bid Amounts
1. ICE Engineering Inc., of Rowland Heights, CA $ 27,550.00
2. Excel Paving Company, of Long Beach, CA $ 40,990.00
3. DG Yeager Const. Co., of San Clemente, CA $ 41,682.60
4. Shawnan, of Downey, CA $ 60,200.00
5. VAP Construction Inc., of La Mirada, CA “No Written Bid Amount”
Staff reviewed the apparent lowest bid proposal (ICE Engineering Inc.) and found
the bid documents responsive and complete. The bonding information,
contractor eligibility, and Workmen’s Compensation Insurance were reviewed
and determined to meet City requirements.
ICE Engineering, Inc. has completed several similar projects for other municipal
agencies in the local region. Representatives from the cities of San Dimas and
Stanton indicated that ICE Engineering, Inc. performed in a professional manner
and recommended them for future projects.
The construction management and construction inspection will be performed by
the Public Works Department/Engineering Division.
The project is tentatively scheduled for construction in May and to be completed
by the end of June.
FISCAL ANALYSIS:
This project is partially funded with $10,000 from CDBG funds. The additional
$20,500 required to complete the project will need to be transferred from another
project.
The table below details current project budget:
Current Project Budget
Pedestrian Islands Modification Project, P-915 (CDBG #601085-08)
Funding Source Amount
CDBG (42800915) $ 10,000.00
Total = $ 10,000.00
Estimated Project Expenses
Pedestrian Islands Modification Project, $ 27,550.00 City of Culver City, California
City Council Agenda Item Report
P-915 (CDBG #601085-08)
Total Estimated Project Cost $ 27,550.00
Contingency (10 %), if necessary $ 2,755.00
Total $ 30,305.00
The project was approved for partial funding with $10,000 from CDBG funds with
an understanding that at the time of approval additional funding from other
sources would be required.
Based on the bid amount, an additional $20,305 is required to sufficiently fund
the construction of the project including a 10% construction contingency. Staff
proposes to transfer $20,500 from the Minor Pavement and Concrete
Improvement Program, P-554 (42000554) to this project to adequately fund the
construction of the Pedestrian Islands Modification Project, P-915 (CDBG
#601085-08). There are sufficient funds remaining in P-554 to provide the
remaining required funds for the project.
ATTACHMENTS:
1. Location Map
MOTIONS:
That the City Council:
1) Award a contract to ICE Engineering, Inc., as the lowest responsive and
responsible bidder, for the Pedestrian Islands Modification Project, P-915
(CDBG #601085-08), based on its bid amount of
$27,550;
2) Authorize the Public Works Director/City Engineer to approve change orders,
if necessary, in an amount not-to-exceed $2,755; and
3) Authorize the City Attorney to review/prepare the necessary documents; and,
4) Authorize the City Manager to execute such documents on behalf of the City.
MEETING DATE: 04/13/09
AGENDA ITEM: Approve Contract with ICE Engineering Inc., for the
Pedestrian Islands Modification Project, P-915 (CDBG
#601085-08)
ATTACHMENT
Page|109| Location Map 1-3/
CONSTRUCT NEW PASSAGEWAYS AT THE NE & SW
CORNER OF JEFFERSON BOULEVARD AND
OVERLAND AVENUE PER CALTRANS STANDARD PLAN A88B
AND CITY REQUIREMENTS
N>|1010|ORMIT.C2
PEDESTRIAN ISLAND MODIFICATION PROJECT, P- 915
(OVERLAND AVENUE AND JEFFERSON BOULEVARD)I. Remove portion of raised island and construct new 3 Y2" thick
concrete passageway per Caltrans Standard Plans A88B and
City Requirements.
1. Construct new 6" concrete curbs per Ca grans Standard Plans
A88B and City Requirements.
3. Install pedestrian push button post per Ca'trans Standard
Plans ES-7A.
tioD141cP1-5 C.) z---1 PROJECT, P-915
(CDBG # 601085-08)
SW CORNER OF JEFFERSON BLVD.
AND
OVERLAND AVE.
I. Install new traffic signal pull box to and adjust to grade per
SS PVVC 460-1.
i. Reconstruct concrete raised island to match existing.
Reconstruct roadway pavement per City Requirements.
7. I lErh ws _saw°
onstruction NotesConstruction Notes
1. Remove portion of raised island and construct new 3 Y2" thick
concrete passageway per Ca!trans Standard Plans A88B and
City Requirements.
21°' PAR''.,•.^,2 2, Construct new 6" concrete curbs per Caltrans Standard Plans
A88I3 and City Requirements,
3. Install pedestrian push button post per Caltrans Standard
Plans ES-7A,
4. Install new traffic signal pull box to and adjust to grade per
SSPWC 460-1.
5. Reconstruct concrete raised island to match existing.
6. Reconstruct roadway pavement per City Requirements.