Title:
|
(1) Acceptance of Work Performed by Carvajal Trucking & Tractor, Inc., (2) Authorization to File the Notice of Completion, and (3) Authorization to Release the Retention Payment after the Expiration of the 35-day Lien Period, for the 2012/2013 CDBG Sidewalk Replacement Project, PZ963, CDBG No. 601474-12.
|
City of Culver City, California
Agenda Item Report
Meeting Date: 07/22/13 Item Number: C-2
CITY COUNCIL AGENDA ITEM: (1) Acceptance of Work Performed by Carvajal
Trucking & Tractor, Inc., (2) Authorization to File the Notice of Completion, and (3)
Authorization to Release the Retention Payment after the Expiration of the 35-day
Lien Period, for the 2012/2013 CDBG Sidewalk Replacement Project, PZ963, CDBG
No. 601474-12.
Contact Person/Dept.: Christopher
Evans/PW
Phone Number: (310) 253-5621
Fiscal Impact: Yes [] No [X] General Fund: Yes [] No []
Public Hearing: [] Action Item: [] Attachments: []
Commission Action Required: Yes [] No [] Date: _______________
Public Notification: (E-Mail) Agenda and Meetings – City Council (07/16/13); (Telephone)
Carvajal Trucking & Tractor, Inc. (07/16/13).
Department Approval:
Charles D. Herbertson (07/10/13)
City Attorney Approval:
Carol Schwab (by H. Baker) (07/15/13)
Chief Financial Officer Approval:
Jeff Muir (by M. Noller) (07/16/13)
City Manager Approval:
John M. Nachbar (07/16/13)
RECOMMENDATION:
Staff recommends the City Council:
1. Accept the work performed by Carvajal Trucking & Tractor, Inc. (CT&T) for the
2012 CDBG Sidewalk Replacement Project, PZ963, CDBG No. 601474-12
(Sidewalk Replacement Project); and
2. Authorize filing a Notice of Completion; and
3. Authorize the release of the retention funds in the amount of $2,877.65 after the
expiration of the 35-day lien period.
BACKGROUND/DISCUSSION:
On February 11, 2013, the City Council awarded a construction contract to CT&T to
construct the 2012/2013 CDBG Sidewalk Replacement Project. The Sidewalk
Replacement Project consisted of removing damaged sidewalk sections on
Sherbourne Drive, McManus Avenue, and within Syd Kronenthal Park and
constructing new sidewalk sections.
Change Orders
The Sidewalk Replacement Project incurred one (1) change order in the amount of
nineteen hundred and seventy-seven dollars and fifty cents ($1,977.50) due to an City of Culver City, California
Agenda Item Report
additional sidewalk removal. Also there was a $600.00 credit due to one tree being
removed by the City instead of the Contractor.
FISCAL IMPACT:
Project Budget
CDBG Funds (42880000.730100.PZ963) $ 30,844.00
Gas Tax Funds (41880000.730100.PZ963) $ 780.00
Available Funds $ 31,624.00
Final Project Expenses
Original Construction Contract $ 27,499.00
Actual Construction Cost $ 28,876.50
Subtotal $ 28,876.50
Total Estimated Project Expenses $ 28,876.50
The unspent funds will remain in CDBG Program, PZ-963, for projects in future fiscal
years.
MOTIONS:
That the City Council:
1. Accept the work performed by Carvajal Trucking & Tractor, Inc. for the 2012
CDBG Sidewalk Replacement Project, PZ963, CDBG No. 601474-12; and,
2. Authorize the Public Works Director/City Engineer to execute the Notice of
Completion and submit it to the Los Angeles County Recorder’s Office; and,
3. Authorize the City Manager to release $2,877.65 in retention to Carvajal
Trucking & Tractor, Inc. after the expiration of the 35-day lien period.