Legislation Details

File #: HIST-4645    Version: 1 Subject:
Type: Historical Status: Action Item
In control: City Council Meeting Agenda
On agenda: 3/26/2007 Final action: 3/26/2007
Title: 1) Informational Report on Status of Discussions with 4-Con Engineering, Inc. and California Landscape and Design, dba California SkateParks, Regarding the Cost for Construction of the Skateboard Park Project P-830; and 2) Authorize Staff to Submit an Application for Proposition 40 Roberti-Z-Berg Harris Block Grant Funds in the Amount of $107,980 for the Culver City Skateboard Park Project (P-830).
Attachments: 1. 1) Informational Report on Status of Discussions w - A-1__07-03-26_PW-Eng_Skateboard Park Award Contract - FINAL.doc, 2. 1) Informational Report on Status of Discussions w - A-1__Skateboard Park.pdf
City of Culver City, California City Council Agenda Item Report A1-1 RECOMMENDATION: Staff recommends the City Council: 1. Receive an informational report on the status of discussions with 4-Con Engineering, Inc. and California Landscape and Design, dba California SkateParks, regarding the cost for construction of the Skateboard Park Project P-830. 2. Authorize staff to submit an application for Proposition 40 Roberti-Z-Berg Harris Block Grant Funds in the amount of $107,908 for the Culver City Skateboard Park Project (P-830). BACKGROUND: On March 12, 2007, the City Council approved a motion to reject all bids for the construction of the Skateboard Park Project, P-830 (the “Project”) and authorized staff to negotiate with the two bidders on the Project for a lower price per City Charter Section 2007. The March 12, 2007, City Council agenda report is included as Attachment 1. DISCUSSION: Negotiations immediately proceeded with 4-Con Engineering, Inc. and California Skateparks and the following revised cost proposals were received: Meeting Date: 03/26/07 Item Number: A-1 AGENDA ITEM: 1) Informational Report on Status of Discussions with 4-Con Engineering, Inc. and California Landscape and Design, dba California SkateParks, Regarding the Cost for Construction of the Skateboard Park Project P-830; and 2) Authorize Staff to Submit an Application for Proposition 40 Roberti- Z-Berg Harris Block Grant Funds in the Amount of $107,980 for the Culver City Skateboard Park Project (P-830). Contact Persons/Dept.: Mate Gaspar/PW and William LaPointe/PR&CS Phone Number: (310) 253-5602 and (310) 253-6682 respectively Fiscal Impact: Yes [] No [X] General Fund: Yes [] No [] Public Hearing: [ ] Action Item: [X] Attachments: [X] Public Notification: Master Notification List (03/22/07); Parks and Recreation Commission (03/22/07), California Landscape and Design dba California SkateParks, 4- Con Engineering, Inc., and Skateboard Park stakeholders by e-mail on 3/22/07. Department Approval: Charles D. Herbertson 3/22/07 City Attorney Approval: Carol Schwab (by H. Iker) (03/22/07) City Controller Approval: Marlee Chang (by M. Cole) (03/22/07) City Manager Approval: Jerry B. Fulwood (03/22/07) City of Culver City, California City Council Agenda Item Report A1-2 CONTRACTOR NEGOTIATED CONSTRUCTION COST (Initial Bid Amount) Difference (Bid v. Negotiation) California SkateParks $539,655 ($643,342.00) $(103,687) 4-Con Engineering, Inc. $549,775 ($598,133.00) $(48,358) California SkateParks: Staff reviewed California Skatepark’s proposal, which is based on a value engineering analysis of the project design and recommends several changes to the skatepark that will have minor impact on the overall skatepark design. California Skatepark is recommending that the center planter be reduced in size and the Skatepark be constructed 2 feet to the north (towards Jefferson Boulevard). As a result, a retaining wall at the back of the skatepark will not be required and fewer trees will have to be removed. In addition, the electrical conduit installation will be deleted from the project except in the portion that will be located under new concrete sidewalk along the Jefferson Boulevard frontage. Finally, they are proposing to relocate the entrance to the Skatepark and construct a concrete pad for future bleachers. They have also reduced the unit cost prices for various items. 4-Con Engineering, Inc.: Staff also reviewed 4-Con Engineering’s proposal, which indicates that they cannot start the project until August 2007. They have also given another lower total cost to their proposal in the amount of $538,142 if the all-risk insurance and performance and payment bonds are eliminated (which option staff would not recommend). Their new proposal requires that (1) the City provide roll-off bins and dispose of the removed material at no cost to the contractor; (2) the City relocate the irrigation system at no cost to the contractor; and (3) the wrought iron fence be replaced with black vinyl chain link fence. Comparing the two proposals based on the aforementioned facts, staff will be recommending that the City Council award a construction contract to California SkateParks. During the negotiations, staff felt that California SkateParks provided the best options to reduce the project cost. California SkatePark can begin the work after the execution of the contract. The expected construction start date is expected in May 2007 and the four months’ construction schedule is slated to be completed by August 2007. 4-Con stated they cannot begin work until August 2007 which will result in the work being completed in approximately December 2007. The construction of the project will be managed by Site Design, the design consultant for this project, as per the approved agreement. The City Council expressed concerns that Site Design may not have fulfilled their contract obligations due to the bids received that were higher than the engineer’s estimate and the City of Culver City, California City Council Agenda Item Report A1-3 delays in completing the plans and specifications for the project. In the spirit of cooperation, Site Design has agreed to provide, at no additional cost to the City, revised construction plans based on California Skatepark’s proposed value engineered layout of the Skatepark. Staff is in support of this arrangement and also believes it is in the City’s best interest that Site Design continue to be under contract to manage the construction of the project, respond to any request for information, and approve shop drawings. The grading, concrete, and steel inspection will be conducted by one of the geotechnical engineering firms currently on contract with the City. The budget set aside for geotechnical inspection is $20,000. Award of the Contract: The City’s Charter provisions regarding public works contracts|1010| give the Council the authority, by a four-fifths vote, to award a contract without complying with the bidding procedures, provided a public hearing is held on the award of the contract after notice has been given. Such notice must be published at least twice, the first of which must be at least 10 days prior to the hearing. In order to comply with the provisions of the Charter, the award of the contract with California SkateParks must be brought back to Council for consideration at its April 9, 2007 meeting. FISCAL ANALYSIS: This informational report does not create a fiscal impact. However, staff provides the following information for Council’s reference: Current Available Project Budget Funding Source Amount Land and Water Conservation Grant $204,000 Proposition 40 Per Capita Grant $170,000 Proposition 12 Grant $26,934 City General Funds $3,796 Total = $404,730 Estimated Project Expenses Construction contract $539,655 Construction Management $18,180 Construction inspection for grading, concrete, and steel $10,000 Contingency (5%), if necessary $27,000 Total Estimated Project Cost $594,835 |1010| Charter Section 2007 provides that the procedures for awarding public works contracts as set forth in the “old” Charter will remain in effect until such time as the City Council establishes, by ordinance, different procedures. Therefore, the current procedures are set forth in “old” Charter Section 1304. City of Culver City, California City Council Agenda Item Report A1-4 Total Budget Amendment Required $190,105 Proposed Budget Amendment Funding Source Amount Last Available Prop 12 Per Capita Funds $289 Proposition 40 RZH Block Grant $107,908 General Funds Reserve $82,816 Total Estimated Budget Amendment $190,105 On March 7, 2000, Proposition 12, the 2000 Parks bond Act was approved by California voters. The 2000 Parks Bond Act provides $155 million for local park projects to be distributed with the Roberti-Z’Berg-Harris Urban Open Space and Recreation Grant Program. The RZH grants are allocated to cities, counties, and park and recreation districts on a population-based formula. Funds allocated to local agencies will be appropriate primarily for projects that rehabilitate existing facilities at local parks; develop facilities that promote positive alternatives for youth and that promote cooperation between local parks and recreation services providers. On October 13, 2003, the City Council adopted Resolution No. 2003-R084 approving staff’s request to apply for grant funds for the Roberti-Z’Berg-Harris Block Grant Program under the California Clean Water, Clean Air, Safe Neighborhood Parks, and Coastal Protection Act Of 2002. A fully executed contract in the amount of $107,908 was received by the City in March 2004. In order to secure funding for a specific project, a project application must be submitted to the California Department of Parks and Recreation Office of Grants and Local Services. Staff will provide the City Council with a formal recommended budget amendment at the time the City Council considers the formal award of contract (expected on April 9, 2007). ATTACHMENTS: 1. The City Council agenda report dated March 12, 2007, ‘Consideration to Reject All Bids Received for Construction of the Skateboard Park Project, P-830.’ 2. California Skateparks Statement of Qualifications and value engineering cost proposal dated March 20, 2007. 3. 4-Con proposal dated March 22, 2007. City of Culver City, California City Council Agenda Item Report A1-5 MOTIONS: That the City Council: 1. Receive the informational report on the status of discussions with 4-Con Engineering, Inc. and California Landscape and Design, dba California SkateParks, regarding the cost for construction of the Skateboard Park Project P- 830; and 2. Authorize staff to submit an application for Proposition 40 Roberti-Z’Berg-Harris Block Grant Funds in the amount of $107,908. MEETING DATE: March 26, 2007 AGENDA ITEM 1) Informational Report on Status of Discussions with 4-Con Engineering, Inc. and California Landscape and Design, dba California SkateParks, Regarding the Cost for Construction of the Skateboard Park Project P-830; and 2) Authorize Staff to Submit an Application for Proposition 40 Rob-ti-Z-Berg Harris Block Grant Funds in the Amount of $107,980 for the Culver City Skateboard Park Project (P-830). ATTACHMENTS Pages 1. Council Agenda Report from March 12, 2007 1-3 2. California Skateparks Qualifications and Value 4-14 Engineering Cost Proposal dated March 20, 2007 3. 4-Con Proposal dated March 22, 2007 15-16City of Culver City, California City Council Agenda Item Report , ,„ Meeting Date: .1 - . Item' P-M _ ._ .: AGENDA consideration - _,. o Reject All Ids skatelaitord: •:Park Project P483 . . Received iiii -- to id- ., _. . -. pn , c prsions' e Daniel iffek ' Garcia1PV - .-.2 ;ind Bill ,'LP Oilite/PR& lO , p Number: 8. 58.2.-- .2 a nd 253-6682 repectively , ti :— . . iiiffp a — . ,.-Pra , - es: 0 ' , : 'P it : Hearing : MR tn- JX1 , , Attachments: men: 1 : _ ., .: Park East - Public Organizations businesses Notification: Mas1r, : utifioAtiort,List, Skaubbard 'JS4: S ITE n' VOU ,.4- ita7 4 - id- e jiU:w ithin 'a . o.0 Ta .,: Took litot 4044 141 ail ' ril - NO) o farice._an - ,,. :- Amp § Seliii 71-11-afi'Oft Users Park _a -6. :6f - ...oriiiiiiih . ff- . . ic iW • actoci a An ato ow ,1,1, TarYMNOtittiirgit Associa tion, ...L-,. . . 1*:_le-tii4f--- _,:at- ' -7atiftailtCity , --- -,------ -----, - , -,---- ---- ------- - -- Users at Culver City Park (flyer at - - ' lattirii4— Park (flyer : d uring . .:A.4I distribution d istribution pubIisb ed Park -- n On:. _ ,. - ,7 : - - - '"- - -""- -- - . j . Co , owe Display . on . March 01, 2007)'-. ... Skatearks &.4-Con reiiil MiTOICARIZMUti-agarAy ' City Marléè ' - ' ilW141:- 7 6- MMZ I,`''' - - -- ----- : !WO .407-te 4.w.-4- -- ---e- - -:'•.r,,- . 7.----: :_ L, -- L-- T w ...: : 0/06: .:: - - 1 r- ,w-1 ,1-- - ---- 07'---- ---" _ iMit ityManagerA N.,,,,,, - W.Fulwobd (03107/07) „ ,Lng 10Affh . ,, , RECOMMENDATION: all bids received for the construction of City Park, 9910 Jefferson Boulevard bidder 4-Con Engineering, Inc the final plans and specifications the construction of the Skateboard Park due to a reorganization that occurred in delays to the final completion of plans the project was advertised for construction opened by the City Clerk, yielding the and at the Staff recommends the City Council reject Culver City Skateboard Park located at Culver and authorize staff to negotiate with the lowest BACKGROUND/DISCUSSION: the following On August 8, 2006, the City Council approved authorized staff to advertise for bids for Project (P-830). The project was delayed design consultant's office that resulted and specifications. On January 11, 2007 bids. On February 15, 2007, the bids were publicly bids: CONTRACTOR BID AMOUNT 4-Con Engineering, Inc. $ 598,133.00 CA Landscape & Design dba CA Skateparks $ 643,342.00City of Culver City, California City Council Agenda Item Report 4 Con Engineering, Inc. was found to be the lowest responsive and responsible bidder for the project with a proposed price for the project not to exceed $598,133.00. Staff contacted the contractor's references and determined the contractor performed satisfactory work for other agencies and has successfully completed other skateboard parks. Also the bonding and insurance policies were reviewed and found to meet City requirements. City staff and its consultant, Site Design Group, Inc., believe that through negotiations with the lowest bidder, an affordable cost can be achieved for the City. Staff believes these negotiations would be in the best interests of the City and recommends that the City enter into negotiations with 4 Con Engineering. In order for these negotiations to proceed, all bids received on February 15, 2007 must first be rejected. The City's Charter provisions regarding public works contracts 1 give the Council the authority to reject any and all bids presented. In addition, the Council, by a four- fifths vote, may award a contract without complying with the bidding procedures, provided a public hearing is held on the award of the contract. As such, it would be legally permissible for the City to negotiate with the lowest bidder, once all prior bids are rejected. Staff anticipates reaching agreement with 4 Con Engineering, Inc. for construction of the skateboard park; however, if no agreement is achieved, staff will make further recommendations to the City Council regarding re-bidding the project. Should the negotiations be successful, the proposed agreement would be presented to the City Council for consideration and potential award. If awarded, construction of the project would be managed by Site Design, under their previously approved agreement. FISCAL ANALYSIS: The item presented to the City Council this evening does not create a fiscal impact. However, if the negotiations are successful, the City Council would be asked to allocate funding for any proposed contract at the time of the Council's consideration of the award of contract. ATTACHMENTS: 1 Charter Section 2007 provides that the procedures for awarding public works contracts as set forth in the "old" Chartei will remain in effect until such time as the City Council establishes, by ordinance, different procedures. Therefore, the current procedures are set forth in "old" Charter Section 1304.City of Culver City, California City Council Agenda Item Report None. MOTIONS: That the Council: 1. Reject all bids for a construction contract for the construction of the Skateboard Park Project (P-830); and 2. Authorize staff to negotiate with the lowest bidder on behalf of the City:.I r:4 .0 .0 5- • 0 0 z r,|109| r, .0 4- 76'ecitogu . , > . pc• • — • cll. >a CD 00 < (D|1010|2(GfA) CALIFORNIA iskateparks THE LEADER IN SPECIALTY SKATEPARK CONSTRUCTION March 20, 2007 Mr. Charles Herbertson Public Works Director/City Engineer City of Culver City 9770 Culver Blvd., Culver City, CA 90232 Re: Culver City Skatepark California Skateparks thanks you for the opportunity to provide our Statement of Qualifications for your future skate park project. Developing a successful facility requires the services of experienced skatepark designers and builders who are passionate about what they create. California Skateparks consists of a cohesive team of skate park designers, builders, professional skateboarders, landscape architects and construction managers who possess the requisite skills and experience to successfully complete your project on time and within budget. We. are pleased to have received national recognition from municipalities, professional skateboarders, and the media for our attention in accommodating the needs of the community and in the skill of designing and building creative, cost-sensitive state of the art facilities. Our innovative projects, including skate plazas, skate spots, pools and expansive transitional terrain have won world-wide attention for being dynamic, fully functional, landscapes for skateboarding which complement the surrounding environment. California Skateparks is confident that with our team's extensive knowledge in design and construction of facilities for skateboarding, we can provide a state of the art landscape for skateboarding with due care and diligence. Should you have any questions, I can be reached at 909-949-1601 or via e-mail at joe@califomiaskateparks.com Sincerely, Joe Ciaglia President/CEO cc: William L. La Pointe, Director of Parks, Recreation & Community Services Dan Garcia, Senior Civil Engineer May Ng, Project Manager California Skateparks, Inc_ (Gc1 2) 273 N. Benson Ave. Uplang, CA. 91786 Phone: 909.949.1601 • Fax: 909.981.9368 • www.califonfiaskateparks.com0 / / 0 0|10101010109| 0 .1;A7E., (7)|101010|0Culver City Skatepark P-830 Value Engineerin Bid item Description Item No. Estimated Quantity Unit Unit Price Extended Amount|109| Mobilization-Max 5% 1 LS 27000 $ 27,000.00|109| Clear and Grubbing 21800 SF 1 $ 21,800.00|109| Tree Removal 10 EA 1000 $ 10,000.00|109| Earthwork 1 LS 67000 $ 67,0001)0|109| Export Cut omit CV 20|109| Install Signage 1 EA 1000 $ 1,000.00|101010|Floor Drains 6 EA 300 $ 1,800.00 8 , 6" Drain Lines 480 LF 45 $ 21,600.00 9 Drain Line Connection 1 EA 3750 $ 3,750.00 10 Relocate Irrigation 1 LS 4000 $ 4,000.00 11 Top Deck 4" 8400 SF 10 $ 84,000.00 12 Flat Bottom-6" 265 SF 10 $ 2,650.00 13 Contruct Ledge 258 SF 120 $ 30,960.00 14 Construct Stairs 218 SF 50 $ 10,900.00 15 Construct Turndown 58 LF 70 $ 4,060.00 16 Construct Ret. Wall 115 . IF 225 $ 25,875.00 17 Construct Mow Curb omit LF 9 18 Construct 6" Banks 1975 SF 22 $ 43,450.00 19 Construct Transitions 2750 SF 22 $ 60,500.00 20 Construct Bank Wall 1325 SP 27 $ 35,775.00 21 Pool Coping and Tile 175 IF 65 $ 11,375.00 22 2" x 2" Sq. Steel 166 IF 35 $ 5,810.00 23 2-1/2"x 5" Rect. Steel 19 IF 50 $. 950.00 24 3" Round Steel Pipe 17 LF 50 $ 850.00 25 6' Fencing 545 IF 90 $ 49,050.00 26 Gates for Fencing 2 EA 600 $ 1,200.00 27 Electrical 1" Conduits 200 LF 10 $ 2,000.00 28 No.5 Pull Boxes _ omit EA 350 29 Contingency 1 EA 6000 $ 6,000.00 30 Sidewalk at street 700 SF 9 $ 6,300.00 Total Base Bid Amount $ 539,655.00Colby W. Carter Designer/Construction Manager • Over 23 years of skateboarding and industry related experience • Professional skateboarder for 10 years • Planning and Design of over 82 public and 17 private skateparks • Provided construction management/observation for over 43 skateparks Colby possesses the proven qualifications and skills to plan and coordinate the various aspects of developing skateparks facilities. His diverse experience in professional skateboarding, design and construction make him unique as a park planner who can successfully address both the client's as well as the skaters needs. Twenty years of recognized achievements in skateboarding and skatepark design and construction has given Mr. Carter the extensive knowledge and insight necessary to develop terrain for skateboarding. In addition to his skateboarding career, he has designed over a 100 skateparks and provided construction management/observation for 43 of them. Along With featured articles in local, national and international newspapers and magazines regarding skatepark design and construction, professional skaters and industry leaders have endorsed Mr. Carters designs as some of the best facilities to date.|10101010101010|Company Bias Joseph M. Claglia I President/CEO|109| * Holds contractor licenses in 12 states|109| ? Over 25 years experience in construction and landscaping. • 14+ years experience in project management • 14+ years experience in Corporate Finance • Extensive knowledge in skate park construction • • Expert knowledge of city code requirements state wide • Extensive knowledge in Horticulture 1 Mr. Claglia leads California Skateparks and California Landscape and Design. He is a licensed contractor with over 25 years of construction and landscaping experience. He is a forward-thinking planner and construction manager who is setting high standards for skatepark development His experience and knowledge allows him to thoroughly evaluate each project and focus on solid construction methodology, sound planning and • systematic project costing while addressing each clients needs with due care and diligence. Joe prides himself on quality of work and customer satisfaction. Joe has also been involved in his community by helping to • improve many of the local parks_ Even with his success, he still stays involved in all aspects of his projects and • can be seen in the design studio or finishing shotcrete.|101010101010101010|1 • Colby is 100% dedicated to being an integral part in the evolution of terrain built for skateboarding through the creation of unique and innovative designs and construction methodologies. Because of his experience and involvement with the skate community, Colby is able to facilitate skaters dreams buil an idea to reality. Colbys visionary leadership, hard work and tenacity to overcome obstacles through to completion is a great asset and has helped California Skate parks grow into the most successful skatepark provider in the world.I|10101010101010|Brian Pino Project Manager • Goodyear Community Skapark - Goodyear, Arizona • McDowell Mountain Ranch - Scottsdale, Arizona • Pecos Park - City of Phoenix, Arizona • Anthem Community Park - Anthem, Arizona|109| • BMX Park - Flagstaff, Arizona • Mike Farm Skatepark - Prescott, Arizona • City of Logan Public Concrete Skate Park-Logan city, Utah • Jim Warren Skatepool- Franklin, Tennessee Brian is a professional skatepark craftsman with extensive experience in all disciplines of construction. His knowledge and expertise in industrial framing, commercial concrete, shotcrete placement, finishing, parking structures, and residential framing has helped him become one of the best skatepark builders in the world. Brian has managed the construction of numerous competition/evert and skate park projects. His diverse experience in skate park planning, design and specialized construction, coupled with his 31 year history as an active skateboarder, make him a strong addition to California Skateparks and any skateparlc venture. • Eric Dawkins Project Manager • Veterans Skatepark - Alabaster, Alabama • Selma-Berry Park - Selma, California • Sandstone Ranch - Longmont, Colorado • Ashland, Oregon • Medford, Oregon • Grants Pass, Oregon • Allen Station Skatepark - Allen, Texas|109| • Canadian Skatepark, Texas|1010|• Grants Pass, Oregon • Seattle Center Skatepark -Seattle, Washington Eric Dawkins has been skating since he was seven years old and has over 30 years of skateboarding experience giving him first hand knowledge and understanding of the sport and its evolution. Mr. Dawkins has traveled nearly all 50 states, Canada and Mexico in pursuit of skateboarding terrain taking note of what he filed and what he felt worked for him as a skater. He has worked on dozens on skateparks and developed his construction techniques entirely through experience in the field and has gone on to build some of the greatest facilit ies in the nation. He brings with him a wealth of skills and abilities exclusive to his trade.Mario Rodriguez Project Manager • • Powhattan Skatepark - Arlington, VA • Ayala Skatepark - Chino, CA, • Bell Gardens Skatepark - Bell Gardens, CA • Burbank Skatepark - Burbank, CA • Coronado Skatepark - Coronado, CA • Etnies Skatepark - Lake Forest, CA • Greencastle Skatepark -Greencastle, Indiana • Granite Skatepark - Sacramento CA|109| • Tarizanite Skatepark - Sacramento CA • Poway Skatepark - Poway, CA|1010|• Oxnard Skatepark - Oxnard, CA • The Mat Hoffman Action Sports Park - Oklahoma City, Ok. Mario throughout the years has acquired a wide range of expertise in all trades involved with successful skatepark construction. He oversees each skatepark project personally and attends to all aspects of the|109| construction from demolition to the finished product. Mario is a licensed contractor and has mastered many|109| trades. Mario has the skills to place and finish shotcrete, forming, run equipment of all sizes, and install rebar. • Wayne Reynolds, City Project Manager for the City of Whittier quoted by the Whittier Daily Journal as saying, "this is one of the first contractors I have ever irked with where I did not have to stay on top of the project • constantly." Andrew Olguin Ornamental Specialist • Santa Monica, California (skatepark metals and custom fence) • Costa Mesa, California (skatepark metals and bathroom structure) • Sacramento, California (sle atepark metals and _ pipe structure) • Upland, California (skatepark metal and full pipe false. forms) 20 years of experience in fabrication and installation of ornamental metals, which include but not limited to: design and fabrication of custom iron fences, gate fabrication and installation of metal pipe coping, edging and rails on over 60 slcateparks. Andrews's responsibilities include shop drawings, detailing and quality control. Samann Project Manager • Tewinkle/Volcorn Skate park - Costa Mesa, CA_ • • Ped low Skate Park .- City of Los Angeles, CA|109| Founders Skatepark - City of Ontario, CA • Ontario Metrolink - City of Ontario, CA • Rialto Streetscape City of Ontario, CA|10101010101010|Nikolai has been involved in the public and private sector since 1986. Over the last 20-years, he has specialized in General Engineering and Site Construction. He has bid nearly one billion dollars in a 20 year span in Private/Public bids. He has held positions as Chief Estimator, Director, Divisional Manager, Project Manager, Construc' 'on Manager and Site Superintendent Nikolai is an excellent spec reader and plan studier. He has extensive 'hands on construction knowledge in estimating, project management, field supervision and sales, marketing and estimating. Currently he is working as Divisional Manager of the Skatepark Division of California Landscape and Design, Inc. dba California Skateparks overseeing Business Development, Project Management, Con t; act Negotiations and Estimating. I0 Calg• ornitiaateparks, Inc. 00 1 273 N. BensonAve. Upland, CA_ 91786 Phone: 909.943.1601 • Far 909.981.9368 • -1,nirw.californiaskateparks_comSkate Park Project List Alabama Alabaster Veteran's Skate Park Huntsville Lydia Gold Skate Park Arizona Buckyee Chandler Flagstaff Florence Glendale Goodyear Phoenix Phoenix Prescott Scottsdale Tucson California Blue Horizon Skate Park Espee BMX Park BMX Skate Park Anthem Merrill Ranch Glendale Skate Park Goodyear Community Skate Park Anthem Community Skate Park Phoenix First Divine Church Skate Park Yavapai Skate Park McDowell Mountain Ranch Skate Park Anthem Red Rock Skate Park Bell Flower Bell Gardens Borrego Springs Burbank Chino Chino Hills Citrus Heights Corona Costa Mesa Duarte Lake Forest Fontana Fresno Glendora Jurupa Junipa Jurupa Laverne Ladera Ranch Laguna Niguel La Quinta Long Beach Lompoc Lynwood Mariposa Monrovia Montclair Murrieta Bellflower Skate Park Bell Gardens Skate Park Borrego Springs Skate Park Burbank Skate Park Ayala Skate Park Big League of Dreams Skate Park Rusch Skate Park Santana Regional Skate Park Volcom Skate Park Duarte Skate Park Etnies — Lake Forest Skate Park Fontana Skate Park/Plaza Lions Den Skate Park Glendora Skate Park Harada Skate Park James Huber Skate Park Orchard Skate Park Laverne Skate Park Terramore Skate Park Laguna Niguel Skate Park La Quinta Skate Park Long Beach Skate Park Vandenberg AFB Skate Park Lynwood Skate Park Mariposa Skate Park Monrovia Skate Park Montclair Skate Park Murrieta Skate Park California Skateparks. Inc. (-67 1 273 N. Benson Ave. Uplancl. CA. 91786 "el, ••-• CI n-•California Needles North Fontana Palm Desert Pamona Placerville Porterville Poway Sacramento Sacramento San Diego San Dimas Santa Monica Selma Solvang Upland Westminster Whittier Colorado Needles Skate Park Jesse Turner Heath & Fitness Center Skate Park Palm Desert Skate Park Martin Luther King Skate Park Placerville Skate Park Porterville, California Poway Skate Park Granite Skatepark Tanzanite Mission Valley YMCA Skate Park San Dimas Skate Park Santa Monica Skate Park Berry Park Skate Park Solvang Skate Park Upland Skate Park Westminster Skate Park Whither Skate Park Commerce City Commerce City Skate Park Longmont Sandstone Ranch Community Skate Park Georgia Dekaib County Brook Run Skate Park Gwinett County DeShong Skate Plaza Gwineft County Mt. Teen Park Skate Park Hawaii Honolulu Kapelio Skate Park Honolulu Kamiloiki Skate Park Honolulu Mananna Skate Park Indiana Fort Wayne Lawton Skate Park Greencastle Green Castle Skate Park South Bend South Bend Skate Park Kansas Derby Derby Skate Park Wichita Wichita Skate Park Kentucky Bowling Green Roland Bland Skate Park California Skateparks, Inc. M 273 N Benson Ave. Upland, C.4_ 91786 fr., a, " " •Long branch Maple Shade North Wildwood Sayerville North Carolina Longbranch Skate Park Heart Skate Park Northwildvvomf Skate Park Kennedy Skate Park Grayson Grayson Skate Park Oklahoma Edmond Edmond Skate Park Oklahoma City Riverfront Skate Park Tulsa Tulsa Skate Park Tennessee Franklin Fran?din Skate Park Maryland Charles County La Plata Skate Park Green Belt Green Belt Skate Park Olney Olney Skate Park Michigan Grand Haven Mulligans Hallow Skate Park Minnesota Paris Oxford Hills Skate Park Missouri Hannibal Hannibal Skate Park Kansas City Penn Valley Skate Park O'Fallon St Charles Skate Park Nevada Las Vegas Hollywood Skate Park New Mexico Albuquerque West Side Skate Park New Jersey California Skateparks, Jnc. ('- =] . 273 N. Benson Ave. Upland CA 91786 _Texas Canadian Canadian Skate Park Irving Irving Skate Park The Woodlands Bear Branch Wheel Friendly Park Wisconsin Black River Falls Black River Falls Skate Plaza Wyoming Cheyenne Cheyenne Skate Park California Skateparks, Inc. 273 N. Benson Ave. Upland, CA. 917862751 Avalon Street, Riverside, CA 92509 (951) 222-2241, Gen Fax (951) 222-2248 Estimating Fax (951)222-2285 r-r- Tat 64519, -Con Engineering, Inc. R From: 6IAC;(11 6E7.°1117 Fax: 310 - 7-C" 3 5-46 4 Pr._ 3 w- ic3- _S-C3o Re: S rfr (zr\- Pages: )_ Date: 3p--?-1 7 Xt‘rgent For Review Please Comment [] Please Reply For Your File 7-0 ert. L.," a/2 K1 t-cf-et / f ool n "es"- Aetir 7/?r r,41,i e _ 06,07 rzA p (e.ersr c irr '1 0 Lie ta-S g Gr( CA s.1,4 qFqqc•qP.SUI ' I Al0 ' I gq 21 (WICIF./77-4-171 I RPM TflN4 4-1.4- a s rt. ./v.StAit. L- i• • 4-Con EngineerinCinc: 03/22/2007 858 0702153 CULVER CITY NEG *** Rick Biditera BID TOTALS Description Statue - Rn4 Quantity Units Unit Price Total •Bid|10 10|MOBILIZATION F -New 1.000 LS 39,000.00 39,000.00 20 CLEARING AND GRUBBING F - New 21,800.000 SF 1,10 23,950.00 30|1010|TREE REMOVAL New • - 111(1 C" ! r f's PADE PREPARATION F - New 14,000 1,000 EA LS 800.00 85,000.00 11,200.00 85,000,00|10 10|6,j EXPORT CUT F - New 280.000 CY 26,00 7,000.00 7,0 NI SIG NAGE AT ENTRY MEATAL F - New 1.000 EA 1,200,00 1,200.00 70 CONSTRUCT FLOOR DRAIN 6" ROUND WITH 6" ROUND STAIN F New 6.000 EA 200,00 1,200.00 80 CONSTRUCTS" DRAIN LINE PVC SDR•35 F - New 480.000 LF 40.00 19,200,00 00 CONSTRUCT DRAIN LINE CONNECTION F New 1.000 EA 4,000.00 4,000.00 100 RELOCATE IRRIGATION SYSTEM F - New 1.000 LS 7,000.00 7,000,00 110 CONSTRUCT TOP DECK 4" WFF REINFORCED CONCRETE F - New 9,088.000 SF 10.50 96,529.00 120 CONHSTRCUT FLAT BOTTOM 6" REBAR REINFORCED F New 265.000 SF 12.00 3,180,00 130 CONSTRUCT LEDGE - AVE 1 1-6" HIGH REBAR F -New 258.000 SF 160,00 41,250.00 140 CONSTRUCT STAIRS - REBAR REINFORCED F - New 358.000 SF 22.00 7,876,00 150 CONSTRUCT TURNDOWN WALL- COMPLETE,REBAR F - New 170,000 LF 60,00 10,200.00 160 CONSTRUCT RETAING WAL F New 140.000 LF 210,00 29,400.00 LAI 170 CONSTRUCT MOW STRIP 1 1-0 11 WIDE x 4' 1 THK F - New 550,000 LF 16.00 8,800,00 180 CONSTRUCT BANKS 6" REBAR REINFORCED SHOTCRETE F - New 1,365.000 SF 21.00 25,685.00 190 CONSTRUCT TRANSITIONS - 6" REBAR F - New 2,750.000 SF 19.00 52,250.00 200 CONSTRUCT. BANKED WALL RIDE 6" REBAR F - New 1,466.000 SF 30,00 43,950,00 210 CONSTRUCT POOL COPING F - New 176,000 Lr 50.00 8,750.00 220 F/12' x 2' SQ STEEL TUBE F - New 166,000 LF 40.00 6,640.00 230 FA 2-1/2" x 5" RECTANGULAR STEEL TUBE F - New 19.000 LF 75,00 1,425,00 240 F/1 3" ROUND STEEL PIPE F - New 17.000 LF 75.00 1,275,00 260 BLACK VINYL COATED 8' Chain Link Fence F - New 545.000 LF 85,00 29,975.00 260 VINYL COATED Chain Link Gale F - New 2.000 EA 900.00 1,800,00 Bid Total => $569,775.00 4. ?am)? y 049 16 -ss eit irtogo.w .re.t.,' 1 P-1001 tt"7. cfrA/0 -$ < 33 S--3 inn a 6,41/".. or,t/ rTJiAngel Poc-ir 44-4 0 fri.Pars 'vie att-o r s PAgviutro, 0 4,0 10 UV 01,1,rp r11.4.A.0$M,/t Pfr, ,}0 rile|1013|