File #: 18-037    Version: 2 Name: Sully-Miller Change Order, PS-005
Type: Minute Order Status: Consent Agenda
File created: 7/11/2017 In control: City Council Meeting Agenda
On agenda: 7/24/2017 Final action:
Title: CC - Approval of an Extra Work Change Order, in the Amount of $96,000, to the Existing Contract with Sully-Miller Contracting Company for the Construction of the 2017 Pavement Rehabilitation Project, PS-005
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

title

CC - Approval of an Extra Work Change Order, in the Amount of $96,000, to the Existing Contract with Sully-Miller Contracting Company for the Construction of the 2017 Pavement Rehabilitation Project, PS-005

 

body

Meeting Date:  July 24, 2017

 

Contact Person/Dept:                     Hong Wang/Public Works Dept.

 

Phone Number:  310.253.5604

 

Fiscal Impact:  Yes [X]    No []                                                                General Fund:  Yes []     No [X]

 

Public Hearing:  []          Action Item:                     []          Attachments: []   

 

Commission Action Required:     Yes []     No []    Date:

 

Public Notification:   (E-Mail) Meetings and Agendas - City Council (7/18/2017);

 

Department Approval:  Charles D. Herbertson (07/13/17)

_____________________________________________________________________

 

 

RECOMMENDATION

 

Staff recommends the City Council approve an extra work change order, in the amount of $96,000, to the existing contract with Sully-Miller Contracting Company for the construction of the 2017 Pavement Rehabilitation Project, PS-005

 

 

BACKGROUND/DISCUSSION

 

As part of the City’s current street rehabilitation project, PS-005, Buckingham Parkway from Slauson Avenue to Hannum Avenue/Buckingham Avenue is scheduled to be resurfaced.  In addition, a condition of approval for the C3 project located at 5800 Bristol Parkway requires the Developer to resurface Hannum Avenue from Bristol Parkway to Uplander Way.  With the City’s project and C3 project, this would leave a 700 foot pavement rehabilitation gap on Hannum Ave from Uplander Way to Buckingham Parkway.  Staff recommends that the City approve a change order to Sully-Miller’s contract to include this segment in the PS-005 contract.  The cost estimate to resurface Hannum Avenue from Uplander Way to Buckingham Parkway is approximately $96,000. The actual construction cost will be based on the original contract bid unit price.

 

After the pavement resurface is completed, a bike lane will be added on Hannum Avenue from Slauson Avenue to Bristol Parkway, wherever feasible.

 

The construction project with Sully-Miller is currently on schedule and all the work is expected to be completed by October, 2017.  The $244,710 in original contingency amount will be used toward any unforeseen field conditions.

 

 

FISCAL ANALYSIS

 

The original contract amount to Sully -Miller is fully funded in the FY 2016-17 CIP budget.  This additional work will be funded through the FY 2017-18 CIP budget:

 

Funding Source:                                                                                                              Amount

PS-005 Streets Pavement Rehab (FY2017-18)                                          $1,144,989

 

Total Estimated Project Expenses                                           

Proposed Change Order                                                                                                         $     96,000

 

 

ATTACHMENTS

 

None

 

 

MOTION

 

That the City Council:

 

1.                     Approve Extra Work Change Order in the amount of $96,000 (in addition to the original $244,710 change order authority) to the existing contract with Sully-Miller Contracting Company for the construction of the 2017 Pavement Rehabilitation Project, PS-005; and,

 

2.                     Authorize the Public Works Director/City Engineer to execute the extra work change order on behalf of the City.