Title:
|
Approval of the Bid Documents (Including the Plans, Specifications, and Call for Bids) for the West Washington Area Improvement Plan, Phase II Demonstration Project.
|
City of Culver City, California
Agenda Item Report
Page 1 of 3
RECOMMENDATION
Staff recommends that the Culver City Redevelopment Agency Board (“Agency
Board) approve the Bid Documents for the West Washington Area Improvement
Plan, Phase II Demonstration Project (Project) and direct staff to proceed with official
notification for bids.
BACKGROUND
In December 2007, the Culver City Redevelopment Agency (Agency) approved a
multi-phased Area Improvement Plan (AIP) along West Washington Boulevard to
improve the physical and economic quality of the area. A key component of this AIP
involves the installation of landscaped medians funded by the Agency. While the
Agency proposed to fund the improvements, it has indicated it would do so only if
the on-going median maintenance is carried out through an assessment district.
The Phase I portion of the plan is complete and maintenance funds are being
collected by the associated assessment district.
In July 2010, the City Council approved formation of an assessment district to fund
the Project’s ongoing maintenance costs. Subsequently, staff issued the Notice to
Proceed for the preparation of construction drawings for the Project.
DISCUSSION:
The design of the Project is consistent with all previous design direction given by
the Agency Board.
Meeting Date: 3/07/11 Item Number: C-2
REDEVELOPMENT AGENCY BOARD AGENDA ITEM: Approval of the Bid
Documents (Including the Plans, Specifications, and Call for Bids) for the West
Washington Area Improvement Plan, Phase II Demonstration Project.
Contact Person/Dept.: Elaine Warner Phone Number: 310.253.5777
Fiscal Impact: Yes [] No [X] General Fund: Yes [] No [X]
Public Hearing: [] Action Item: [] Attachments: []
Commission Action Required: Yes [] No [X] Date: _______________
Public Notification: Meetings and Agendas – Redevelopment Agency (03/04/11)
Department Approval:
Sol Blumenfeld (03/02/11)
Agency General Counsel Approval:
Murray Kane (03/01/11)
Chief Financial Officer Approval:
Jeff Muir (by N. Kimball) (03/03/11)
Executive Director Approval:
John Nachbar: (03/04/11) City of Culver City, California
Agenda Item Report
Page 2 of 3
The plans include three (3) new medians, totaling 437 linear feet that will be
positioned between Centinela Avenue and Boise Avenue along West Washington
Boulevard (Attachment 1). The medians will be located in the center of the right-of-
way within existing median striping to minimize traffic impacts and allow for a
potential bike lane/sharrow in the future. Staff has worked closely with the
landscape architect to ensure that this configuration and planting palette will not
cause any visual blind spots or distractions for vehicular and pedestrian traffic and
that understory planting will be maintained at a low level and below sightlines as
required by California State Law.
The proposed medians will beautify the commercial area and the planting palette
will include Queen Palm trees as the primary species and Blue Oat Grass, New
Zealand Flax and Daylilies as the understory planting (Attachment 4). In addition,
two uplights will be positioned near each tree to illuminate them at night. This effect
will be critical to the development of this area as a safe and pedestrian friendly
location.
The Bid Documents include all plans, specifications, general conditions, Notice
Inviting Bidders, Instructions to Bidders, and surveys which bidders will utilize to
formulate their bids. The Bid Documents are on file in the Office of the Secretary of
the Redevelopment Agency and are available for public inspection.
The Project will be advertised on the City’s website and through the Culver City
News and construction trade publications.
The proposed schedule for this Project is as follows:
March 17
th
& March 24th Bid Notification in Culver City News
March 30
th
Mandatory Pre-Bid Meeting
April 7
th
Bids are due
April 25
th
Board to consider award of construction contract
May 2011 Construction begins
FISCAL ANALYSIS:
The Agency has tax exempt bond funds allocated in the Agency Board Adopted
Budget for Fiscal Year 2010/2011 for construction of the three new medians. If the
adopted funds are insufficient, staff will seek a budget amendment when the Agency
Board considers awarding the contract for constructing the medians. However, staff
anticipates that actual construction costs may be lower than previously budgeted
due to the current economic conditions and the competitive process.
City of Culver City, California
Agenda Item Report
Page 3 of 3
ATTACHMENTS:
1. Phase II Area Improvement Plan Boundaries
MOTION:
That the Agency Board:
Approve the Bid Documents for the West Washington Area Improvement Plan,
Phase II Demonstration Project.
MEETING DATE: 03.07.11
AGENDA ITEM: AGENDA ITEM: Approval of the Bid Documents
(Including the Plans, Specifications, and Call for Bids)
for the West Washington Area Improvement Plan,
Phase I Demonstration Project.
ATTACHMENTS
Pages
1. Phase II Area Improvement Plan Boundaries 1 WASHINGTON BOULEVARD
CENTINELA AVENUE
BOISE AVENUE
WEST WASHINGTON AREA IMPROVEMENT PLAN
PHASE II BOUNDARIES