Title:
|
Approval of Final Plans and Specifications and Authorization to Publish a Notice Inviting Bids for the Construction of the Sewer Main Lining Rehabilitation Project (Phase IV), PZ-906.
|
City of Culver City, California
Agenda Item Report
Meeting Date: 10/13/14 Item Number: C-10
CITY COUNCIL AGENDA ITEM: Approval of Final Plans and Specifications and
Authorization to Publish a Notice Inviting Bids for the Construction of the Sewer
Main Lining Rehabilitation Project (Phase IV), PZ-906
Contact Person/Dept.: Hong Wang/PW Phone Number: (310) 253-5604
Fiscal Impact: Yes [X] No [] General Fund: Yes [ ] No [X]
Public Hearing: [] Action Item: [] Attachments: [X]
Commission Action Required: Yes [] No [X] Date: _______________
Public Notification: (E-Mail) Agenda and Meetings – City Council (10/08/2014)
Department Approval:
Charles D. Herbertson (09/30/14)
City Attorney Approval:
Carol Schwab (by H. Baker) (10/07/14)
Chief Financial Officer Approval:
Jeff Muir (by M. Noller) (10/08/14)
City Manager Approval:
John M. Nachbar (10/08/14)
RECOMMENDATION:
Staff recommends that the City Council approve the final plans and specifications
and authorize the publication of a notice inviting bids for construction of the Sewer
Main Lining Rehabilitation Project (Phase IV), PZ-906.
BACKGROUND:
As the City’s sewer collection systems age, the risk of potential failure increases.
Issues of concern include collapse, blockage, overflow, and other potential service
interruptions. In an effort to overcome these challenges, staff utilizes closed circuit
television (CCTV) inspection to assess the condition of the sewer and to prioritize
sanitary sewers for rehabilitation and maintenance. Instead of excavation and
replacement of the existing sewer main, the trenchless lining process provides for
the insertion of a special lining material inside the existing pipe, and the liner is then
heated or cured-in-place to adhere to the inside of the existing pipe. The new liner
creates a water tight, smooth surface within the existing sewer main pipe that is
structurally sound and long lasting. Since 2009, Phases I, II and III of the Sewer
Main Rehabilitation Project, PZ-906 have installed approximately 19 miles of cured-
in-place pipe in existing deteriorated sewer mains.
DISCUSSION:
After the review and evaluation of the latest CCTV inspection of the existing sewer
mains, approximately 17 miles of sewer mains are proposed to be rehabilitated with
this phase of the sewer lining project due to their current condition and root intrusion. City of Culver City, California
Agenda Item Report
In addition, it is estimated that approximately 25% of the active sewer laterals
studied have various degrees of root intrusion extending into the City’s sewer main
lines. As part of this project, only defective sewer lateral connections to the sewer
main with root intrusion will receive a “top hat” trenchless lateral sealing system at
the main line connection point. It is the homeowner’s responsibility to maintain their
sewer lateral from the building to the City’s sewer main, per Culver City Municipal
Code Section 5.02.007.
Engineering Division staff has completed the design and preparation of
specifications for the sewer rehabilitation project. The IT Department’s GIS staff
prepared the project location exhibits.
FISCAL ANALYSIS:
This project is included in the City Council Adopted Budget for Fiscal Year
2014/2015 (20480000.730100.PZ906) funded by the Sewer Enterprise Fund.
ATTACHMENTS:
The Plans and Specifications are available at the following link:
http://www.culvercity.org/Government/PublicWorks/CouncilItems.aspx
MOTION:
That the City Council:
Approve the final plans and specifications and authorize publication of a notice
inviting bids for the construction of Sewer Main Lining Rehabilitation Project
(Phase IV), PZ-906.