Title:
|
Acceptance of Work Performed by All American Asphalt; Authorization to File a Notice of Completion; and Authorization to Release the Retention Payment after the Expiration of the 35-Day Lien Period, for the Sherbourne Drive Street Resurfacing Project, P-955, CDBG #601392-11.
|
City of Culver City, California
Agenda Item Report
Meeting Date: 09/10/12 Item Number: C-4
CITY COUNCIL AGENDA ITEM: (1) Acceptance of Work Performed by All
American Asphalt; (2) Authorization to File a Notice of Completion; and (3)
Authorization to Release the Retention Payment after the Expiration of the 35-Day
Lien Period, for the Sherbourne Drive Street Resurfacing Project, P-955, CDBG
#601392-11
Contact Person/Dept.: Lee Torres/PW Phone Number: (310) 253-5623
Fiscal Impact: Yes [x] No [] General Fund: Yes [x] No []
Public Hearing: [] Action Item: [] Attachments: []
Commission Action Required: Yes [] No [x] Date: _______________
Public Notification: (E-Mail) Agenda and Meetings – City Council (09/05/12); All American
(09/04/12).
Department Approval:
Charles D. Herbertson 08/31/12
City Attorney Approval:
Carol Schwab (by H. Baker) (09/04/12)
Chief Financial Officer Approval:
Jeff Muir (by K. Marsden) (09/05/12)
City Manager Approval:
John M. Nachbar (09/05/12)
RECOMMENDATION:
Staff recommends that the City Council:
1. Accept the work performed by All American Asphalt for the Sherbourne Drive
Street Resurfacing Project, P-955, CDBG # 601392-11;
2. Authorize filing a Notice of Completion; and
3. Authorize the release of the retention funds in the amount of $6,078.40 after the
expiration of the 35-day lien period.
BACKGROUND/DISCUSSION:
On May 7, 2012, the City Council approved a construction contract with All American
Asphalt to construct the Sherbourne Drive Street Resurfacing Project, P-955, CDBG
#601392-11.
The Sherbourne Drive Street Resurfacing Project consisted of cold milling two-
inches of the deteriorated roadway pavement and overlying two-inches of new
asphalt concrete from Washington Boulevard to the end of the cul-de-sac. The work
was successfully completed on time and under budget.
Change Orders
There were no change orders on this project. City of Culver City, California
Agenda Item Report
FISCAL IMPACT:
Project Budget
P-955 CDBG Funds (42800955) $ 42,346.00
P-863 General Funds (42000863) $ 65,000.00
Available Funds $107,346.00
Final Project Expenses
Original Construction Contract $ 87,500.00
Actual Construction Cost $ 60,784.01
Subtotal $ 60,784.01
Construction Inspection Services $ 4,940.00
Geotechnical Construction Services (Observation &
Testing)
$ 1,635.00
Total Estimated Project Expenses $67,359.01
The original contract included removal and reconstruction of localized pavement
sections in the amount of $24,250. However, after the cold milling process was
completed it was determined that the underlying pavement was in good condition
and did not need to be reconstructed. Also, the estimated quantities for cold milling
and asphalt concrete in the contract were slightly higher than the final actual
quantities and resulted in a $2,465.99 savings.
The unspent funds will remain in Residential Pavement Program, P-863.
MOTIONS:
That the City Council:
1. Accept the work performed by All American Asphalt for the Sherbourne
Drive Street Resurfacing Project, P-955, CDBG #601392-11; and
2. Authorize the Public Works Director/City Engineer to execute the Notice of
Completion and submit it to the Los Angeles County Recorder’s office; and,
3. Authorize the City Manager to release $6,078.40 in retention to All American
after the expiration of the 35-day lien period.