Title:
|
Approval of Final Plans and Specifications and Authorization to Publish a Notice Inviting Bids for the Syd Kronenthal Park Playground Rehabilitation Project, PZ-831.
|
City of Culver City, California
Agenda Item Report
Meeting Date: 10/13/14 Item Number: _C-5__
CITY COUNCIL AGENDA ITEM: Approval of Final Plans and Specifications and
Authorization to Publish a Notice Inviting Bids for the Syd Kronenthal Park
Playground Rehabilitation Project, PZ-831.
Contact Person/Dept.: Patrick Reynolds,
Parks Manager
Phone Number: (310) 253-6470
Fiscal Impact: Yes [X] No [] General Fund: Yes [] No [X]
Public Hearing: [] Action Item: [] Attachments: [X]
Commission Action Required: Yes [] No [X] Date: _______________
Public Notification: (Email) Meetings and Agendas – City Council (10/08/14).
Department Approval:
Dan Hernandez (10/01/14)
City Attorney Approval:
Carol Schwab (by H. Baker) (10/07/14)
Chief Financial Officer Approval:
Jeff Muir (by M. Noller) (10/08/14)
City Manager Approval:
John M. Nachbar (10/08/14)
RECOMMENDATION:
Staff recommends the City Council approve the final plans and specifications and
authorize the publication of a notice inviting bids for the Syd Kronenthal Park
Playground Rehabilitation Project, PZ-831.
BACKGROUND:
On October 22, 2012, the City Council adopted a Resolution approving the
application for grant funds from the Los Angeles County Regional Park and Open
Space District Excess Funds Grant Program for the Syd Kronenthal (SK) Park
Playground Rehabilitation Project. On March 5, 2013, the Los Angeles County
Board of Supervisors approved Proposition A Cities Excess Funds in the amount of
$250,000.00 for the Project. The fully-executed Grant Agreement was received in
July 2013 and in 2014 the project performance period (completion deadline) was
extended to June 30, 2015.
DISCUSSION:
The scope of work for the Project includes: (a) replacing the outdated playground
equipment with sculptural elements that are both physically and intellectually
stimulating; (b) replacing the sand surfacing using 100% engineered wood fibar; (c)
incorporating needed features such as an accessible ramp; and, (d) providing a path
of travel to and from the parking area to the playground area that will bring the entire
playground into 100% federal ADA compliance.
City of Culver City, California
Agenda Item Report
FISCAL ANALYSIS:
The SK Park Playground Rehabilitation Project, PZ-831, is fully-funded by
Proposition A Cities Excess Funds. There are sufficient funds for the Project in the
City Council Adopted Budget for Fiscal Year 2014/2015 in account
42380000.730100.PZ831 (Grants Capital Projects / Improvements Other Than
Buildings / Syd Kronenthal Playground Project).
ATTACHMENTS:
The plans and specifications and a rendering of the playground are available at the
following link:
http://www.culvercity.org/en/Government/PRCS/CouncilItems.aspx
MOTION:
That the City Council:
1. Approve the final plans and specifications for the Syd Kronenthal Park
Playground Rehabilitation Project, PZ-831; and,
2. Authorize the publication of a notice inviting bids for the
construction/installation of the Project.