File #: 24-877    Version: 1 Name: Unsignalized Intersections Safety Improvement Project
Type: Minute Order Status: Action Item
File created: 3/28/2024 In control: Mobility, Traffic & Parking Subcommittee
On agenda: 4/11/2024 Final action:
Title: MTP - ACTION ITEM - (1) Receive a Presentation on the Unsignalized Intersections Safety Improvement Project; and 2) Discuss and Provide Direction to Staff.
Attachments: 1. 2024-04-11-ATT-MTP-UnsignalizedIntersectionsImprovementPlans
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

title

MTP - ACTION ITEM - (1) Receive a Presentation on the Unsignalized Intersections Safety Improvement Project; and 2) Discuss and Provide Direction to Staff.

 

body

Meeting Date:                       April 11, 2024

 

Contact Person/Dept.:                      Andrew Maximous/Public Works

 

Phone Number:                       (310) 253-5628

 

Fiscal Impact:                     Yes [  ]    No [X]                     General Fund:                     Yes [  ]    No [X]

 

Attachments:                     Yes [X]    No [  ]   

 

Public Notification:                     E-Mail via GovDelivery (04/09/2024): Meetings and Agendas - Mobility, Traffic & Parking Subcommittee; Notify Me - Construction, Street Maintenance and Closures; Stay Informed - Bicycle & Pedestrian / Culver CityBus / Construction, Street Maintenance and Closures

 

Department Approval:                     Yanni Demitri, Public Works Director & City Engineer (04/05/2024)

 

 

RECOMMENDATION

 

Staff recommends the Mobility, Traffic & Parking Subcommittee receive a presentation on the Unsignalized Intersections Safety Improvement Project; and 2) discuss and provide direction to staff.

 

 

BACKGROUND

 

Culver City’s Local Road Safety Plan (LRSP) report was finalized in November 2021.  The LRSP analyzed collision data over a five-year period citywide and identified the top high-risk intersections.  Ten locations were identified to seek grant funding for safety improvements.

 

On March 26, 2021, the City received confirmation from The State of California Department of Transportation (Caltrans) Highway Safety Improvement Program (HSIP) that the Unsignalized Safety Improvement Project of our grant application was selected for funding.

 

On March 23, 2022, the City received Program Supplement Agreements from Caltrans for the project which allocated the HSIP funding for the projects.

 

 

DISCUSSION

 

The Unsignalized Safety Improvement Project proposes safety improvements at the ten (10) intersections listed below.  The safety improvements include intersection lighting, installation/upgrade of stop signs and other warning and regulatory signs, and upgrade of intersection pavement markings.

 

Higuera St at Krueger St

Washington Blvd at Midway Ave*

Overland Ave at Northgate St

Washington Pl at Boise Ave

Washington Blvd at Kensington Rd*

Washington Pl at Tuller Ave

Washington Blvd at Prospect Ave

Sepulveda Blvd at Vera Way

Washington Blvd at Kenyon Ave

Jackson Ave at Farragut Dr/Revere Pl

* New or enhanced roadway lighting

 

Two locations, Washington Blvd at Kensington Rd and Jackson Ave at Farragut Dr/Revere Pl, include curb extensions to shorten pedestrian crossing distance and to make intersection operations clearer.  The extension at Farragut Dr/Revere Pl will be constructed with flex curb and filled in with pavers.

 

Two locations indicated in the table above are proposed to install new or enhanced roadway lighting for better nighttime visibility.

 

The HSIP Grant funding is available and ready to begin construction.  Next step would be to proceed with finalizing and advertising the project for bid.

 

 

ATTACHMENTS

 

2024-04-11-ATT-MTP-UnsignalizedIntersectionsImprovementPlans

 

 

FISCAL IMPACT

 

Grant funding is available and ready for project construction.