Legislation Details

File #: HIST-1778    Version: 1 Subject:
Type: Historical Status: Joint Consent
In control: City Council Meeting Agenda
On agenda: 2/21/2006 Final action: 2/21/2006
Title: Joint City Council/Redevelopment Agency Consideration to Waive Advertising For Bids and the Public Hearing and to Award a Tri-Party Contract to Viking Equipment Corporation for Asbestos Abatement and Building and Site Demolition of the Properties at 12811 and 12813 Washington Boulevard.
Attachments: 1. J-1 Demolition Contract 12811 and 12813 Washington Boulevard.doc, 2. J-1 Washington Blvd.pdf
City of Culver City, California City Council Agenda Item Report RECOMMENDATION: Staff recommends the City Council (“Council”) determine that demolition and asbestos abatement of the two apartment buildings at 12811 and 12813 Washington Boulevard be deemed to be “of urgent necessity for the preservation life, health or property” pursuant to Section 1304 of the Culver City Charter; and to award a contract for asbestos abatement and demolition of the aforesaid properties to Viking Equipment Corporation for a cost of $58,400. BACKGROUND: The Culver City Redevelopment Agency (“Agency”) owns all of the properties on the north side of the block of Washington Boulevard from Meier Street to Moore Street. These properties were acquired for the purpose of eliminating blight in the area. The new use proposed for this block by Urban Equity Partners is 12 live/work units plus 12 loft housing units. The Agency will be required to deliver a cleared site to Urban Equity Partners under the terms of the Disposition and Development Agreement now being drafted. Towards this end, on October 24, 2005, the Council awarded a contract to Marcor Remediation, Inc., for the demolition of the Baldwin Motel at 12823 Washington Boulevard. The work was completed the following month. The structures that remain on the block are two four-unit apartment buildings (12811 and 12813 Washington Boulevard) and one multi-tenant commercial building 12803- Meeting Date: 2/21/06 Item Number: J-1 AGENDA ITEM: Joint City Council/Redevelopment Agency Consideration to Waive Advertising For Bids and the Public Hearing and to Award a Tri-Party Contract to Viking Equipment Corporation for Asbestos Abatement and Building and Site Demolition of the Properties at 12811 and 12813 Washington Boulevard. Contact Person/Dept.: John Fisanotti (CDD/Redev) / Andy O' Connell (PW) Phone Number: (310) 253-5767 (310) 253-5606 Fiscal Impact: Yes [X] No [] General Fund: Yes [] No [X] Public Hearing: [] Action Item: [X] Attachments: [X] Public Notification: All proposing companies were notified by mail on February 9, 2006. Master Notification List (02/15/06) Department Approval: Charles Herbertson (02/01/06) Susan Evans (02/01/06) CAO Approval: Martin R. Cole for Jerry B. Fulwood (02/15/06) City Controller Approval: Marlee Chang (02/13/06)City of Culver City, California City Council Agenda Item Report 07 Washington Boulevard). At about 3:30 am on January 22, 2006, a fire broke out in Apartment D at 12811 Washington Boulevard. The building had tenants occupying Apartments B and D. The tenants in A and C had been previously relocated. Fortunately everyone got out safely during the fire. The building was damaged and has been red-tagged by the City’s Building Official. The fire damaged building has been boarded up and fenced as a precaution. The fire damaged building represents an obvious hazard that should be demolished as soon as possible. The adjoining apartment at 12813 Washington Boulevard was not damaged by fire. Although much of this building is boarded up, staff has had to remove homeless people from the site and there are at least three locations actively used by the homeless. This too represents a health and safety hazard, including a further risk of fire. DISCUSSION: The apartment that burned was purchased by the Agency 11 days prior to the fire, and an asbestos survey of the building had not occurred yet. In contrast, the apartment at 12813 Washington Boulevard was purchased on March 2, 2005. It has been sampled for asbestos and the report was made available to the proposing contractors. The proposing contractors will also be responsible for the proper abatement of the asbestos containing material. To achieve an economy of scale when obtaining proposals, and to eliminate health and safety hazards, staff is recommending that the demolition project encompass both buildings. Because of the urgent, emergency nature of the work, staff obtained proposals without preparing a formal bid package or advertising for bids. Staff walked the site with four abatement and demolition companies (including the three which bid on the Baldwin Motel demolition last October) to assess the work to be done. Staff solicited four proposals in an attempt to obtain a competitive price. Asbestos abatement in 12813 Washington Boulevard will be pursuant to the previously completed asbestos survey. Asbestos abatement in the fire damaged building at 12811 will be pursuant to SCAQMD approved Procedure Five plan, to be prepared by CTL Environmental. CTL Environmental is the consultant hired by the Agency to monitor the abatement of the asbestos such as during the demolition of the Baldwin Motel. CTL Environmental will again be providing abatement monitoring services and, in the case of the fire damaged apartment, will conduct a sampling survey, write the Procedure Five plan for abatement of asbestos containing materials within the building, and submit the plan to SCAQMD for approval. The results of the proposals are shown on the following page.City of Culver City, California City Council Agenda Item Report Name of Firm Cost Proposal 1. Viking Equipment Corporation, of Glendale, CA $58,400 2. TEG/LVI Environmental, Inc. of Santa Fe Springs, CA $82,091 3. Marcor Remediation, of Cerritos, California $86,598 4. K.G. Mullen, Inc. of Culver City, CA $136,941 Staff recommends the Council award a contract to Viking Equipment Corporation, in the amount of $58,400 for the abatement and demolition services as the lowest and most responsive cost proposal and also recommends that staff have authorization to approve change orders for unforeseen conditions not to exceed an additional $15,000. Unforeseen conditions are common when demolishing structures because subsurface infrastructure in particular is difficult to identify beforehand. Also, in this instance, the final asbestos abatement process for the fire damaged building was not available to all proposing companies prior to submitting proposals. The work is expected to commence within ten days of contract award and be completed within approximately 15 working days. Construction management will be performed by the Public Works Department and CTL Environmental will monitor the abatement process under an administratively approved contract. The City and Agency are authorized by the Community Redevelopment Law to cooperate in carrying out the Agency’s activities. Pursuant to Article XIII, Section 1304, of the City Charter, if four fifths of the City Council deems the work to be of urgent necessity for the preservation of life, health or property, the contract may be awarded without complying with the bidding procedures, including advertising and a public hearing, which otherwise would apply. Given the situation with the red- tagged, fire damaged building and the break-ins by homeless at the other building, staff recommends the Council make this determination. As part of the City’s ongoing cooperation with the Agency to assist with the redevelopment of the community, staff recommends the Agency and City enter into a three-party agreement with Viking Equipment Corporation for the asbestos abatement and demolition of the above described structures. Pursuant to that agreement, the City will manage the contract and the Agency will pay for the contractor’s satisfactory services.City of Culver City, California City Council Agenda Item Report FISCAL ANALYSIS: The cost of a contract with the proposed bidder is $58,400. There is a balance of $114,979.00 presently available in account number 55392630.710150 (Baldwin Motel Block – Demolition of Structures) to provide for this expense. ATTACHMENTS: 1. Copies of the four proposals received MOTION: That the City Council: Four fifths (4/5) vote needed: 1. Determine that the work is of urgent necessity for the preservation of life, health or property, and that the contract may be awarded without advertising for bids or conducting a public hearing, Majority vote needed: 2. Award a tri-party contract to Viking Equipment Corporation in the amount of $58,400 for the demolition and asbestos abatement of the buildings and site improvements at 12811 and 12813 Washington Boulevard; 3. Authorize the Public Works Director/City Engineer to negotiate any change orders at a total not-to-exceed amount of $15,000; and 4. Direct the City Attorney to prepare the necessary documents and authorize the Chief Administrative Officer to execute the documents. That the Culver City Redevelopment Agency: 1. Authorize the Assistant Executive Director to execute a tri-party contract with Viking Equipment Corporation; and 2. Authorize payments to the contractor pursuant to the agreement plus any change orders approved by the Public Works Director/City Engineer not to exceed $15,000. MEETING DATE 02/21 '06 AGENDA ITEM Joint City Council/Redevelopment Agency Consideration to Waive Advertising For Bids and the Public Hearing and to Award a Tn-Party Contract to Viking Equipment Corporation for Asbestos Abatement and Building and Site Demolition of the Properties at 12811 and 12813 Washington Boulevard ATTACHMENTS Pages|109| Copies of the four proposals received 1-14A. Jan 25 2006 Viking Equipment Corp. DEMOLITION CONTRACTORS NATIONAL DEMOLITION DEMOLITION ASSOCIATION ,.. .„, ..._ P 0 BOX 251257 GLENDALE CALIFORNIA 91225 1257 (818) 500 9447 FAX (818) 500 9630 State License No C21 310852 www vilungdemo corn JOHN FISANOTTI City of culver city Dear John Enclosed is our demolition and asbestos removal proposal for the two buildings on Washington blvd Based on conventional asbestos removal procedures If the decision is made to remove under procedure 5 the additional cost will be $7 500 This is based on getting approval from the AQMD to demolish the buildings, pick out the visible asbestos and dispose of the remaining debris as construction debris Thank you for the opportunity to bid on this project I — — 1Viking Equipment Corp. DEMOLITION CONTRACTORS P0 BOX 251257 GLENDALE CALIFORNIA 91225 1257 (818) 500 9447 FAX (818) 500 9630 State License No C 21 310852 WWW vilangdemo corn ILNATIONAL VDEMOL/T/ON ASSOCIATION PROPOSAL AND CONTRACT JOHN FISANOTTI PROPOSAL 13136 TO CULVER CITY, CITY OF DATE 01/25/06 9770 CULVER BLVD PHONE 310/253-5767 CULVER CITY, CA 90232 FAX 310/253-5779 JOB DESCRIPTION JOB ADDRESS WASHINGTON BLVD, 12811-12813, CULVER CITY, The undersigned agrees to furnish and provide necessary labor, materials, and to perform and complete in a good workmanlike manner the following 1 REMOVAL AND DISPOSAL OF ALL ASBESTOS CONTAINING MATERIALS AS LISTED ON SURVEY DATED 2 MAKE ALL APPLICABLE NOTIFICATIONS AS REQUIRED BY LAW 3 PROVIDE ALL ISOLATION MATERIALS, SAFETY EQUIPMENT, LABOR AND DISPOSAL IT 4 CLEAN ALL VISIBLE ASBESTOS CONTAINING DEBRIS FROM THE WORK APEA COVERED BY THIS CONTRACT 5 ENCAPSULATE, WET WIPE AND HEPA VACUUM ENTIRE WORK AREA AFTER REMOVAL AS APPLICABLE 6 PROVIDE AIR MONITORING BEFORE, DURING AND AFTER dl i n • An HAZARDOUb maLerials, propeicy line fercing, dna work on public property IS EXCLUDED unless specifically listed above In the event an action is brought to enforce any of the terms of this agreement, the prevailing party shall be entitled to reasonable attorney's fees All work to be completed for the sum of $ 50900 00 TERMS of payment are 100% ON COMPLETION This price quotation good for 45-Days Respectfully submitted PAGE # 1 CONTINUED ON PAGE # 2 REMOVAL OPERATIONS CT S I _ sa DAP pQbr TAL • t. 8 FINAL CLEARANCE LEVERL TO BE 01 OR BETTER 9 REMOVAL AND DISPOSAL OF BUILDINGS, CONCRETE, TREES, SHRUBS AND DEBRIS OBTAIN ALL NECESSARY DEMOLITION PERMITS CAP SEWERLit 1 -e orp!Al ACCEPaANCE BERGE Viking Equipment Corp. DEMOLITION CONTRACTORS P 0 BOX 251257 GLENDALE CALIFORNIA 91225 1257 (818) 500 9447 FAX (818) 500 9630 State License No C 21 310852 wWW vilungdemo corn ANNATIONAL V A DEMOLITION ASSOCIATION PROPOSAL AND CONTRACT PAGE # 2 CONTINUED FROM PAGE # 1 PR POSAL 1'I36 FOR JOB ADDRESS WASHINGTON BLVD, 12811-12813 You are hereby authorized to complete the work as described in the above proposal for which I/we agree to pay the amount as mentioned in the above proposal and in accordance with the terms as indicated above SIGNED DATE CONST LENDER NAME OF PROPERTY OWNER/S ADDRESS01 / 31 / 2E105 1 ='• 59 5624070571 TEG/LVI PAGE 01/05 TEGAVI eNvinommenn SERVICES INC January 31, 2006 Via FAX [310] 253-5779 Telephone [310] 253-5767 John Fisanotti Culver City Redevelopment Agency 9770 Culver Boulevard SUBJECT Asbestos Abatement & Demolition Proposal 12811 & 12813 Washington Boulevard Proposal Number [A06-016] Revised 1/31/06 Dear Mr Fisanotti TEG/LVI Environmental Services, Inc. is pleased to present this proposal for asbestos abatement and demolition at the above referenced location. This proposal has been prepared in accordance with Executive Environmental Services Corporation dated September 6 2005 SCOPE OF WORK 12813 Washington The scope of the work includes the removal and disposal of the identified asbestos tnatenals on the survey and also the demolition of building, slabs, footings, trees and site improvements, remok e debns from site The work will be performed as described on CTL Enviromuental Services sqe letter dated January 27, 2006 12811 Washington The scope of work includes the remok al of the fire damaged building The building will be removed under a Procedure 5 All debris will be disposed of as asbestos debns PROCEDURES Mobilization The mobilization phase will commence upon receipt of a Notice to Proceed Mobilization includes Agency Notification This regulatory notification includes submission of properly executed notification forms and fees to applicable agencies Typically, 10 working days notification is required Hazardous Remediation & Demolition Services 13320 CambnJgP Street Santa Fe Spnngs CA 90670 (562) 407 05-10 C Mail LA@LVISSPVICES COM Website WW‘As LV15ERVICES COM - FAX (552) 407 0571 State Lic 4174335101 /31/ 2006 13 59 5624070971 TEG/LVI PAGE 02/05 12811 a. 12813 Washington A.B06 016 ReviKed 1/31/06 Page 2 of 5 Staging of Supplies and Waste Dumpster Supplies will be staged in a neat and orderly manner and will be coordinated with the designated Owner's Representative Dumpster will be located as close as possible to the designated waste egress, and coordinated with the Owner's Representative Preparation Non-Friable Materials All openings will be sealed with one layer of 6-mil polyethylene and splash guards vkill be installed up to 4 feet high. A two-stage dry type decontamination unit will be utilized Negatts, e Air Filtration Units will be set up within the containment, exhausted directly to the outside of the facility to filter the air and create a pressure differential beta een the containment and the outside area At a minimum, the units %Ill supply one air change mere fifteen (15) minutes Removal All asbestos material will be remoNed utilizing wet methods Material will be wetted utilizing an amended v ater solution, remmed from the substrate in manageable sections and placed into properly labeled 6-mil polyethylene bags These will then be closed, rinsed and double bagged for removal from the work area. Cleaning Following removal, the substrate will be detail cleaned This involves the removal of residual material from the substrate utilizing hand-brushing and wet-wiping the surface Detail cleaning will continue until all visual residue has been rerricoyed Visual Inspection Following cleaning, a visual inspection will be made by a TEG/LVI representative and the Owner's Representatn e Alter approval, the surfaces will be sprayed with a liquid encapsulant to lock down any residual fibers Clearance Clearance air monitoring will be performed by owner s independent air sampling professional Transportation and Disposal All asbestos materials remmed from the site will be bagged and properly labeled prior to being placed into a sealed disposal bin for transport to an authorized disposal site The .% aste material will be manifested prior to removal from the project site and signed for by an authorized representatne of the Owner Asbestos-containing material will be removed from the site by a licensed and certified hazardous waste hauler and properly placed into an EPA approved landfill Special Note Before TEG/LVI can place durnpsters on the job site, we must have the Owners EPA Generator Number and their Excise Tax 11) Number01 /31/2006 13 59 5624070571 TEG/LvI PAGE 03/ 05 12811 4E4 12813 Waslungton ABO6 016 1131/06 Page 3 of 5 Worker Protection Personal Air Monitoring Personal air samplmg is conducted during renovation or abatement projects to determine employees' exposure (outside any respirator) to airborne fibers Representative, daily personal monitoring during abatement projects is required by OSHA Asbestos Standard (29 CFR 1926 1101) and TEG/LVI s work policy Moreover, every TEGrLVI worker shall have the right to know the asbestos coocentranons to which they are exposed and what measures are being taken to protect them Results of personal air sampling shall be used to select proper respiratory protection for the abatement worker Data from personal au monitoring can used as an indication of effective removal engineering techniques which result in the lowest employee exposure Employee Protection For this project, workers will utilize half-face protection Higher levels of protection will be unheed if necessary based upon sampling levels Additionally, all personnel on site will be required to wear proper protective clothing, including hooded Tyvek suits, gloves and boots Decontamination All personnel working within a contaminated space will be required to decontaminate prior to exiting via a personnel decontamination unit The decontamination unit is a three chamber passage consisting of a contaminated changing room shower and a clean mom All water generated from the unit will be filtered prior to being discharged to a sanitary system SCHEDULE Work la, Ili proceed 10 working days following submission of notification to regulatory agencies Work will be substantially complete within approximately 9 working days HEALTH AND SAFETY TEG/LV I employs a full time Director of Health and Safety who is responsible for dea elopmg implementing and enforcing our quality assurance program INSURANCE AND BONDING TEG/LVI carries standard General Liability Insurance in the amount of $2 million per occurrence, $5 million general aggregate and a $20 million umbrella with Commerce and Industry Company an A10 Company, Best Rated 43,-H-15 Bonds are provided at owner's account by National Union Fire Insurance Company of Pittsburgh, Best Rated A-H-1501./ W2006 13 59 5624070571 TEG/LVI PAGE 04/05 12811 & 12813 Washington ABM-016 1/31/06 Page 4 of 5 ATTORNEI 'S FEES If a dispute arises relating to the performance of the services covered under this agreement, and legal or other costs are incurred it is agreed that the prevailing party shall be entitled to recovery of all reasonable costs incurred in the prosecution or defense of a claim including staff time at current billing rates, court costs, attorney a fees and other claim related expenses TERMS 4.M) CONDITIONS Inclusions All salvage is the property of TEGLVI Environmental Sex-laces, Inc Exclusions The following is specifically excluded from this work My asbestos outside the Scope of Work as defined herein Removal of any other hazardous material whether contaminated with asbestos or not Replacement of fixtures or funnture moved to access asbestos Replacement of any asbestos materials removed whether asbestos materials or not, unless specifically noted otherwise in the Scope of Work Damages to surfaces caused by installation of containment or removal procedures Adherence to Specifications or Procedures submitted to TEG/LVI after proposal submission Re-strapping or re-hanging of any items to meet code, or any other code upgrades Costs or conditions caused by delays by others beyond TEG/LVI's control Inaccessible asbestos Costs for added work caused by hidden obstruction caused by floors, walls slabs or ceilings not shown on drawings Cify waste hauling franchise fee, Taxes/Surcharges for waste disposal at landfill sites use of franchise haulers, sidewalk control and protection, dewatermg, SWPP, site secuntv, staking and layout, diseon.nect, excavation of footings below 3 feet, back fill, sand bags Performance and/or Payment Bonds 2re Union labor or overtime costs, unless specifically noted o/ c() ( tti 6_e_ Floor Tile More than one layer of tile Damages to or removal of leveling compounds Tile concealed below carpet RA( A- I 6/de c/01'31/2006 13 59 5624070571 TEG/Ur I PAGE 05/05 12811 & 12813 Washington A1306-016 /131/05 Page 5 of 5 Unforeseen grooves or other conditions that prohibit the use of "bead-blastmg" or chemical removal of mastic Damages to substrate caused by "bead-blasting", including re leveling substrate, or to wood substrates Owner/Agent ResponsKbilthes The Owner or his designated agent is responsible for providing to TEG/LVI the following Water power (including assistance to hook up temporary power) and HVAC lockout Staging areas for equipment and dumpsters (dock access) Access to the work area Sanitary facilities Parking for work force Removal of trash or tenant items, leaving tlac area "broom clean", prior to mobilization Designate those items to be left or saN, ad prior to TEG/LVI mobilization TERMS OF PAYMENT Payment will be progressive, net 30 days upon substantial completion Substantial completion is defined as complete visual removal of asbestos materials and acinet . ernent air clearance PRICING For the scope of work as specified herein $79,700 00 -{ S"), Oq( Thank you for this opportunity to submit our proposal on this project If you have any questions or require any additional information, please do not hesitate to contact me at 562-407-0570 Respectfully Submitted, TEG/LVT Environmental Services, Inc. 9ose Arany° Account Manager/Estimator!I P :1;r; I MARCOR Remediation, Inc 16027 Carmenita Rd Cemtos, CA 90703 800-237-6271 Fax 562-921-2383 FAX COVER SHEET Please Deliver The Forthcoming Pages a k of Name ) /;2 AM I/ Firm/Department 644," e .44 162,440t6t17/1110A.4 Fax Machine Number 2 From ZYt, leo'hiert) / "la Date Transmission Includes Page (s) - Including this cover sheet. If you do nor receive all the pages indicated above please call (562) 921-2733 *** ** sew • SWAPS ****** • *S MARCOR RernazGabon, Ina aims supenor turnkey environmental contracting services with a complete range of setwces (or any sae project such as Asbestosaead Abatement Decommissioning & Demolition Gun Range Rentedlation IndoorAlr QualltylDuct Cleaning Industdal Cleaning & Vacuuming Emergency Spill Response Hazaidous Waste Management Groundwater & Soil Remecffation Building Dry Down/Mold Comments end/or Special Instructions "Confidentiality Nonce"*".'•••• The documents accompanying this telecopy transmission contain confidential information belonging to the sender which is legally privileged The information is intended only far the use of the indhridual or entity named above If you are not the intended recipient you are hereby notified that any disclosures copying distribution or the taking of any action in reliance on the contents of this telecopied information is strictly prohibited It you have received this telecopy In error please Immediately notify us by the telephone to arrange For the return of onginal documents to us. Austin DC *Atlanta, GA` Eialtimore MD Boston MA- Cerritos, ce Norfolk, VA Philadelphia PA* Rochester NY' Salisbury MD Dublin CA ci Z/ 30Vd criV170 14 90 SZ tor `eeez Z6Z9S ONI 1:1001:1VM AS 11'Via fax 1-310 263 6779 362 921 2731 567 991 7'483 (FAX} BOO 237 6271 www =icor corn MARCOR Rernschation Inc 16027 Carmel-lira Road Cerritos CA 90703 2208 MARCOR Remediation Inc Agreed to this day of 2005 (signature) (Title) Mr John Fisanotti Culver City Redevelopment Agency 9770 Culver Boulevard Culver City Ca 90232 Re Asbestos Abatement & Demolition Proposal Vacant Apartment Buildings 12511 12813 Washington Boulevard Culver City CA 90232 MARCOR Proposal # IOG 056 Rev 1 Dear Mr Fisanoth Thank you ror allowing MARCOR RernediatIon Inc (MARCOR) to submit a proposal for the above mentioned project We look forward to working with you on this and future projects The Scope of Work includes Asbestos abatement and Lot Clearing at 12811 12813 Washington Boulevard Demolition is to include all buildings trees block walls sidewalks asphalt it alley footings and the pre demolition removal of all asbestos containing matenais as Identified in the building survey by Executive Environmental Services Corporation dated September 8 2005 including the following I) 375 sq ft 9x9 tile and mastic apartment A 2 ) 150 Eq ft 9x9 tile tile and mastic Apart. A 3 ) 80 Eq ft Linoleum ( Friable ) Apart A e ) 80 sq ft. Linoleum Apart B S ) 160sq ft 0x9 Tile and mastic Apart B 6 ) 80 sq ft 9E9 tile and Mils& Apart B 400 sq rt Linoleum Aparts s C and D 7 ) Exterior Stucco and Drywall faint Compound in the apartment buildings contain leas than 1% asbestos and will be demolished with the buildings B ) 80 lin ft window putty in unit C 9 ) 80 sq ft roof penetration mastic Pricing Includes the identical materials listed as being located in both buildings and that the rrietteiale Will be removed prior to budding demolition under a Procedure S work plan Final pncing would be based on the contents and procedures prescribed in said Procedure 5 MARCOR will isolate the work area from etl -joining areas by installing critical barriers at all openings and covering walls arid horizontal surfecce with polyethylene sheeting as required The work Brea will br Plat-Cd uncle, rtagahva pressure Of required) to prevent contamination of adjacent arcae Wails will be removed in manageable sections using wet methods and properly packaged for disposal/treatment at an EPA approvori I-mall/recycling facility MARCOR will require acce--s to electrical power and potable Water for worker decontamination/clean up as rcouircd by CaUOSNA Air Monitoring Of MARCOR proposes to complete this project In 10 eight hour shifts for the once of $136 598 00 /Ls Assumptions/conditions Mutually agreeable contract terms & conditions of MARCOR s Standard Proposal/Environmental Micas Agreement Reaching mutually agreeable contract terms with both our etistornor and vendor(s) This proposal includret Prevailing Wage Rates This proposal excludes work on Public Properly This proposal assumes no demolition lower than three (3) foot below exisUng grade The Scope of Work and site conditions as we understand them at time of bid The cost and availability of resources remaining consistent from time of bid through the completion of the project Our proposal is valid for de days Please do not hesitate to contact me at (562) 921 2733 if you have any qucetions or require addittenul infoimation Respectfully Submitted ACCEPTANCE t ASLitSTOS LFAD MOLD PCBs Tams HA7WAS1E COATINCS Snii GEOUNfMNATER DEC OMMISSIONING DEW.) DI,A0TERS 30Vd '11VV0 90 SZ Nvr 'E8SZI.Z6Z9S ONI 'NOUVI031131:1 UO3UVIN A9 VOctober 3, 2005 Page 1 of 4 Rsanoth, John From Sammy [Sammy@sti motorsports corn] Sent Tuesday January 24 2006 6 18 PM To Asanotti John Subject Demo Proposal SAmmy doc Here is the demo bid for washington please call if any question thanks sammy 310 901 8080 1,0.111111N INC CA License #650730 5895 Washington Blvd Culver City ca 90232 (310)901 8080 January 24, 2006 Mr John L Fisanotti Culver City Public Works 9770 Culver Boulevard Culver City, CA 90232 RE DEMOLITION OF APARTMENT BUILDING WITH GARAGES 12811-12813 WASHINGTON BLVD CULVER CITY, CA Dear Mr Fisanotti K G Mullen, Inc is pleased to present our proposal for Demolition at the above reference location Our prop( been prepared in accordance with today's tour SCOPE OF WORK The scope of work includes 1) All asbestos materials shall be removed by a certified asbestos removal contractor Remove all t material including all framing, utilities, finishes, foundations, etc 2) Cap all utilities at the property line 3) Al boxes or meters shall remain, which shall be marked clearly 4) Remove all sidewalks, landscaping, uncle] utilities, etc Cap all utilities at the property line Removal and proper disposal of the following materials 1) 650 sq ft of roof mastic 2) 200sq ft 9x9 ti mastic in room 101 3) 60sq ft of Brown Linoleum and mastic in room 109 4) Tran site pipe at roof 15 liner ft sq ft 9x9 tile only in room 108 6) 145 sq ft Tile only in room 104 7) 220 sq ft tile only in room 105 8) 605 s( only in Apt A 9) 290 sq ft of tile only in Apt B 10) 400sq ft linoleum in units C & D kitchens and baths 01/25/2006 I(October 3, 2005 Page 2 of 4 liner Ft window putty 12) 50sq ft penetration mastic on roof 13) 4500 sq ft of exterior stucco this contains 1( 1% asbestos Removal and proper disposal of the following materials 1) 375 sq ft of floor tile and associated mastic sq ft of brown floor tile and associated mastic, 3) 80 sq ft of orange linoleum, 4) 1180 sq ft of light brown linol, 80 sq ft of green linoleum and brown floor tile and associated mastic under linoleum, 6) 150 sq ft of white an floor tile and associated mastic, 7) 60 sq ft of speckled floor tile and associated mastic, 8) 400 sq ft of brown linoleum, 9) 1600 sq ft of 1 ceiling tile and associated mastic, 10) 4,500 sq ft of exterior stucco, 11) 160 sq ceiling tile and associated mastic, 12) 6,000 asphalt roof shingles This bid includes the removal and disposa exterior stucco as non-hazardous construction debris At the completion of the removal process K G Mullen, remove all site improvements per the plans and specifications MOBILIZTION PROCEDURES Mobilization will commence upon receipt of acceptance to this proposal of issuance of Notice to Proce( regulatory notification includes submission of properly executed notification forms and fees to applicable ag Typically, 10 working days notification is required Supplies will be staged in a neat and orderly manner and coordinated with the designated Owner's Representative Dumpster will be located as close as possible designated waste egress and coordinated with the Owner's Representative SCHEDULE Work will proceed 10 working days following submission of notification to regulatory agencies Work substantially complete within approximately 15 working days A detailed schedule, showing task sequence and dates will be submitted upon request HEALTH AND SAFETY K G Mullen, Inc employs a full time Director of Health and Safety who is responsible for developing, impler and enforcing our quality assurance program GOVERNING REGULATIONS, All work performed by K G Mullen, inc, Inc will be in accordance with written procedures, and all applicabb rules and regulations In conducting our research, we have collaborated with governmental regulatory a including the U S Occupational Safety and health Administration (OSHA), the State of California Departr Health Services (DOHS), the California Department of Industrial Relations Division of Occupational Safety and (Cal/OSHA) and the National Institute of Occupational Safety and Health (NIOSH) Our work procedures are p documented and performed in compliance with the following regulations and specifications Code of Federal Regulations (CFR Publications 29 CFR 1910 134— Respiratory Protection 29 CFR 1910 145 — Specifications for Accident Prevention — Signs and Tags 29 CFR 1910 1001 Asbestos 40 CFR 61 Subpart A — General Provisions 40 CFR 61 Subpart B — National Emission Standards for Hazardous Air Pollutants (NESHAP) California Code of Regulations ((CCR) Title 8 8 CCR 341 6 to 341 15 8 CCR 1529 American National Institute (ANSI) Publications ZP 279 — Fundamentals Governing the Design and Operation of Local Exhaust Systems ZP 280 — Practices for Respiratory Protection American Society for Testing and Materials (ASTM) Nation Institute of Occupational Safety and Health (NIOSH) 77 173 Occupational Exposure Sampling Strategy Manual South Coast Air Quality Management District (SCAQMD) Rule 1403 01/25/2006 I 2-October 3, 2005 Page 3 of 4 INSURANCE AND BONDING, K G Mullen, Inc carries standard General Liability insurance in the amount of $1 million per occurrence/$2 aggregate with EMC Insurance Company, Best Rated A+15, K G Mullen, Inc is capable of obtaining an umbre EMC Insurance Company at coverage amounts of either $10 million or $20 million if required ( at additional co TERMS AND CONDITIONS INCLUSIONS • All equipment, scaffolding, cranes, required to complete the scope of work • All salvage is the property of K G Mullen, Inc • Notifications/fees to SCAQMD and CA/OSHA • All misc concrete slabs and footings to 3 ft — 0" below grade • Pricing is valid for 60 days EXCLUSIONS The following is specifically excluded from this work • Any Hazardous Materials, • Removal of any other hazardous material except as noted in scope of work, • Replacement of any materials removed unless specified in the scope of work • This proposal excludes work on public property • This proposal excludes demolition of items beyond three (3) foot below existing grade except a above • Minor damages to surfaces caused by installation of containment or removal procedures • Adherence to Specifications/Procedures submitted to K G Mullen, Inc after proposal submissior • Costs or conditions caused by delays by others beyond K G Mullen, Inc control • Layout, excavation, backfill and compaction except as noted above • Unknown items below ground • Performance and/or Payment Bonds Add 2% to pricing if Bonds are required • Side Walk Canopy City to coordinate and close sidewalk during demolition OWNER/AGENT RESPONSIBILITIES The owner/agent is responsible for providing the following • Water, power (including assistance to hook up temporary power) • Staging areas for equipment and dumpsters (dock access) • 24 hour access to the work area • site security • Parking for work force (free of charge) • Designate those items to be left or saved prior to K G Mullen, Inc mobilization • Identification of underground utilities to be protected in place • Coordination of Utilities shut off and disconnect TERMS OF PAYMENT Payment will be progressive, net 10 days upon substantial completion Substantial completion is del complete visual removal of asbestos material and achievement air clearance PRICING Per the Scope of Work as specified herein (price valid for 60 days) $84,660 Per Abatement Survey $52,281 TOTAL FOR ALL WORK $136,941 01/25/2006October 3, 2005 Page 4 of 4 1 - Thank you for the opportunity to submit this proposal for this project If you have any questions or require ad information, please do not hesitate to contact me on my cell at 310-901-8080 This quote is based on prevai1n4 and certified payroll Respectfully Submitted ACCEPTANCE K G Mullen, Inc Agreed to Samir Sayegh Project Manager Signature Date l'i 01/25/2006