Title: Consideration to approve a Budget Amendment and Approve Construction Change Orders for the Carlson Park Restroom Project, P-814.
Attachments: 1. A-18__06-06-12_PW_Eng_CarlsonParkRestroomChangeorders.doc, 2. A-18 Budget Amendment for the Carlson Park Restroom Project.pdf
City of Culver City, California City Council Agenda Item Report RECOMMENDATION: Staff recommends that the City Council: 1) approve change orders for the Carlson Park Restroom Project, P-814; and, 2) approve a budget amendment to transfer $11,326 from the El Marino Park Ceramics Hut Rehabilitation Project, (P-827) to the P-814 budget. A four-fifths affirmative vote is required to amend the budget. BACKGROUND: On November 10, 2003 the City Council awarded a construction contract to Cohen Construction, Inc., in the amount of $202,000 for the construction of the subject project. The work consisted of the demolition and construction of a new restroom facility, re-roofing the existing picnic shelter, and site furnishings. The construction of the Carlson Park Restroom Project began in February 2004 and was scheduled for completion in May 2004. The construction progress was slow due to delayed delivery of materials. Also, rain and change order delays revised the completion date to September 2004. In October 2004, the contractor declared bankruptcy. After several months of legal work from the City Attorney’s office and Cohen’s surety bonding company, work commenced again in April 2005 with a new contractor. The project completion was managed by the Engineering Division. (The original construction contract was managed by the Parks, Recreation & Community Services Meeting Date: 06/12/06 Item Number: A-18 AGENDA ITEM: Consideration to approve a Budget Amendment and Approve Construction Change Orders for the Carlson Park Restroom Project, P-814 Contact Person: Mate Gaspar/PW Phone Number: (310) 253-5623 Fiscal Impact: Yes [X] No [] General Fund: Yes [X] No [] Public Hearing: [] Action Item: [X] Attachments: [] Public Notification: Master Notification List on June 7, 2006 and Hartford Surety Company via e-mail on June 7, 2006. Department Approval: Charles D. Herbertson 06/01/06 CAO Approval: City Controller Approval:City of Culver City, California City Council Agenda Item Report Department utilizing a consultant to oversee the construction work.) The work was successfully completed to the satisfaction of the Building Maintenance Division, Parks, Recreation, and Community Services staff, Building and Safety Division, and Engineering Division staff. DISCUSSION: On August 8, 2005, the City Council approved a motion accepting the project as complete in the amount of $202,000 with no change orders. In November 2005 staff received the final invoice from the surety bond company and it included change orders that occurred during construction by the original contractor. Up to that point, staff was unaware of any project change orders. As mentioned earlier, the construction management was performed by a consultant and their file did not contain any written documentation of change orders. Nevertheless, a review of the change orders submitted by the surety was conducted by staff from the Engineering and Parks Divisions Staff determined that the change orders are legitimate and is therefore recommending their approval. (Change orders descriptions are attached to this report). The recommended approval amount is $12,346.79 (6% of awarded construction contract amount, $202,000). FISCAL ANALYSIS: In October 2002, the City of Culver City was awarded an $119,923 Land and Water Conservation Fund (LWCF) grant to replace the restroom building and repair the picnic pavilion at Carlson Park. This grant was leveraged with $119,923 in Proposition 12 Per Capita Grant funds for a total project budget of $239,846. In light of the change orders discussed in this report and other expenses that were incurred due to the delay of the project, the final Carlson Restroom project total is as follows: PROJECT EXPENSES Amount Consulting Construction Manager $28,700.00 Cohen Construction (Original Contractor) $148,594.50 The Hartford Insurance Co. $53,405.50 Construction change orders $12,346.79 Temporary restroom structures and related services $2,486.31 Storage costs and miscellaneous expenses $1,090.84 TOTAL $246,624City of Culver City, California City Council Agenda Item Report PROJECT BUDGET Amount Land and Water Conservation Fund Grant $119,923.00 Proposition 12 Matching Funds ($4,548 of the original match was reallocated to the Skateboard Park Project, P-830) $115,375.00 Proposed transfer of funds from the El Marino Ceramics Hut Project, P-827(a reduction in the scope of the Ceramics Hut Project is being proposed for the FY 06/07 budget) $11,326.00 TOTAL $246,624 ATTACHMENT: 1. Change orders spreadsheet MOTIONS: That the City Council: 1) Approve the construction change orders in the amount of $12,346.79 for the Carlson Park Restroom Project, P-814, and 2) Authorize a budget amendment to appropriate El Marino Park Ceramics Hut Rehabilitation Project, (P-827) funds in the amount of $11,326 to the Carlson Park Restroom Project and transfer $11,326 to project expenditure line item 42000814.720100 Carlson Park Restroom Project. A 4/5ths vote is required to approve the budget amendment. MEETING DATE 06/12/06 AGENDA ITEM Consideration to approve a Budget Amendment and Approve Construction Change Orders for the Carlson Park Restroom Project, P-814 ATTACHMENTS Pages|109| Change orders spreadsheet 1CONTINUATION SHEET AM DOCUMENT G703 ALA. Document G702 APPLICATION AND CERTIFICATION FOR PAYMENT containing APPLICATION NO 6 Page 3 of 3 Contractors signed certification is attached APPLICATION DATE 10/31/2005 In tabulations below amounts are stated to the nearest dollar PERIOD TO 10/11/2005 Use Column I on Contracts where variable retamage for line items may apply ARCHITECTS PROJECT NO Project Carlson Park Playground Improvements City of Culver City C D E F G H I ITEM NO DESCRIPTION OF WORK SCHEDULE OF VALUES WORK COMPLETED MATERIALS PRESENTLY STORED ( NOT IN D OR E) TOTAL COMPLETE & S CORED TO DATE (D+E+F) / BALANCE TO FINISH (C G) RETAINAGE FROM PREVIOUS APPLICATION (D+E) THIS PERIOD CHANGE ORDERS COP #1 ADD 1/4' CAP PLATE 1 126 24 1 126 24 1 126 24 100% $ - 112 62 COP #2 EXTRA 6 FLOOR DRAINS $ 5 069 92 $ 5 069 92 $ 5 069 92 100% $ - 506 99 COP #3 2 1 BACKFLOW DEVICE $ - $ - $ - 100% $ $ - COP #4 REPAIR IRRIGATION $ 4 303 46 $ 4 303 46 $ 4 303 46 100% $ 430 35 COP #5 IRRIGATION SLEEVES (ELEC) $ 981 45 $ 981 45 $ 981 45 100% $ $ 98 15 COP #6 ADDITIONAL RECEPTACLES $ 214 04 $ 214 04 $ 214 04 100% $ 21 40 COP #7 ADDITIONAL SLEEVES $ 243 11 243 11 $ 243 11 100% $ 24 31 COP #8 1 IRRIGATION LINE $ 408 57 $ 408 57 $ 408 57 100% $ 40 86 $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $- $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ - $ $ $ $ $ $ $ $ - $ $ $ $ $ $ $ $ $ TOTAL CHANGE ORDERS $ 12 346 79 $ $ 12,346 79 12 346 79 $ 1 234 68 TOTAL ORIGINAL CONTRACT $ 202 000 00 $ - $ 202 000 00 10% Retention $ 202 000 00 100% $ 20 200 00 TOTAL CONTRACT W/CHANGE ORDERS $ 214 346 79 $ - $ 214 346 79 $ 192 912 11 $ 214 346 79 100% $ 21 434 68