eComments During Meetings: When available, click here to submit eComments during a live meeting | Attendees must register here to attend all virtual meetings.

File #: 20-129    Version: 1 Name:
Type: Minute Order Status: Action Item
File created: 8/7/2019 In control: Bicycle & Pedestrian Advisory Committee
On agenda: 8/15/2019 Final action:
Title: Update on the La Ballona Elementary School Safe Routes to School Project
Attachments: 1. May 5, 19 BPAC Staff Report.pdf
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
title
Update on the La Ballona Elementary School Safe Routes to School Project


body
Meeting Date: August 15, 2019

Contact Person/Dept: Gabe Garcia/PW

Phone Number: 310-253-5633

Fiscal Impact: Yes [] No [X] General Fund: Yes [] No [X]

Public Hearing: [] Action Item: [] Attachments: [X]

Commission Action Required: Yes [] No [] Date:

Public Notification: (E-Mail) Meetings and Agendas - City Council ();

Department Approval: Charles D. Herbertson - 8/12/2019
_____________________________________________________________________


RECOMMENDATION

Provide the Bicycle & Pedestrian Advisory Committee (BPAC) with an update on the project progress and planned schedule to seek Council approval and proceed with construction.


BACKGROUND

On May 5, 2019, staff provided a presentation on the La Ballona Elementary School Safe Routes to School project during a special meeting of the Bicycle and Pedestrian Advisory Committee. Attached is the staff report regarding the May 5th BPAC meeting, which summarizes the project activities and community consultation since the project inception in 2014 until the May 2019 meeting. Issues and concerns were raised by the community during the meeting, and consequently staff proceeded to make changes to the project to address the community's concerns.

This report is to update BPAC on the revisions made to the plans since the special meeting earlier this year and provide a tentative timeline for project implementation. The report focuses on describing changes made at specific locations with reported concerns.


DISCUSSION

The 90% design plans that the BPAC reviewed during the special May 5th meeting have been modified as follows in response to community's input:

1. Length of the curb extension on the south side of Matteson Avenue at College Boulevard was reduced to the width of the proposed raised crosswalk across Matteson Avenue. The purpose of the reduction is to return the...

Click here for full text