File #: 19-735    Version: 1 Name:
Type: Public Hearing Status: Action Item
File created: 1/2/2019 In control: PLANNING COMMISSION
On agenda: 1/9/2019 Final action: 1/9/2019
Title: PC: Status Report and Extension for Site Plan Review, SPR P-2008047 - Conjunctive Points Warner Development, LLC.
Attachments: 1. 19-01-09-ATT NO 1_City Council Resolution 8511 Warner, 2. 19-01-09-ATT NO 2_Planning Commission Resolution 8511 Warner, 3. 19-01-09-ATT NO 3_January 10 2018 PC Staff Report Extension for 8511 Warner, 4. 19-01-09-ATT NO 4_January 10 2018 PC Minutes Extension for 8511 Warner, 5. 19-01-09-ATT NO 5_October 15 2018 Developer Progress Update 8511 Warner
title
PC: Status Report and Extension for Site Plan Review, SPR P-2008047 - Conjunctive Points Warner Development, LLC.

body

Meeting Date: January 9, 2018

Contact Person/Dept: Jose Mendivil, Associate Planner / CDD
Michael Allen, Current Planning Manager

Phone Number: (310) 253-5757

Fiscal Impact: Yes [] No [X] General Fund: Yes [] No [X]

Public Hearing: [] Action Item: [X] Attachments: [X]

Public Notification: (E-Mailed) Project Applicant (12/12/18); (E-Mail) Meetings and Agendas - Planning Commission (01/03/19).

Department Approval: Sol Blumenfeld, Community Development Director (01/03/19)
____________________________________________________________________________


RECOMMENDATION

Staff recommends that the Planning Commission either:

1) Review and consider the Developer Status Report and consider the Initial Grading and Shoring Permit application and Preliminary Soils Review application adequate to grant a one year extension for Site Plan Review, SPR P-2008047;

Or

2) Review and consider the Developer Status Report and consider the Initial Grading and Shoring Permit application and Preliminary Soils Review application insufficient to grant a one year extension for Site Plan Review, SPR P-2008047


PROCEDURES:

1. Chair calls on staff for a brief staff report and Planning Commission poses questions to staff as desired.

2. Chair invites the Applicant to speak, followed by the general public.

3. Commission discusses the matter and arrives at its decision.


BACKGROUND:

On May 13, 2009, the Planning Commission approved Site Plan Review, SPR P-2008047 (the "Warner Parking Structure") for construction of a parking structure with 775 parking spaces, 41,520 square feet of retail space, and 10,000 square feet of restaurant space within a five level, 43 foot high development (the "Project"). After an appeal to the Planning Commission decision, the City Council, on August 3, 2009, approved the Project w...

Click here for full text