title
CC - (1) Acceptance of Work Performed by BC Traffic Specialist; (2) Authorization to File a Notice of Completion; and (3) Authorization to Release the Retention Payment After the Expiration of the 35-Day Lien Period, for the Arterial Street Restriping Project, PS-005.
body
Meeting Date: May 14, 2018
Contact Person/Dept: Diana Szymanski/PW Engineering
Phone Number: 310-253-5623
Fiscal Impact: Yes [X] No [] General Fund: Yes [X] No []
Public Hearing: [] Action Item: [] Attachments: []
Commission Action Required: Yes [] No [X] Date:
Public Notification: (E-Mail) Meetings and Agendas - City Council (05/09/18);
Department Approval: Charles D. Herbertson, Director of Public Works/City Engineer (05/03/18)
_____________________________________________________________________
RECOMMENDATION
Staff recommends the City Council (1) accept the work performed by BC Traffic Specialist; (2) authorize the filing of a Notice of Completion; and (3) authorize the release of retention funds in the amount of $2,954.77 after the expiration of the 35-day lien period, for the Arterial Street Restriping Project, PS-005.
BACKGROUND/DISCUSSION
On June 12, 2017, the City Council approved a construction contract with BC Traffic Specialist for the Arterial Street Restriping Project, PS-005.
The Project consisted of restriping all major arterial and collector streets. The Project included repainting of one coat over existing lines with glass beads. Glass beads provide a retroreflection that makes the striping stand out during the night or during rain.
BC Traffic Specialist successfully completed the work in February 2018. The construction management and inspection were performed by Public Works Department - Engineering Division staff.
FISCAL ANALYSIS
The City Council approved construction contract amount was $48,261 with an additional 10% contingency authority ($48,261 + $4,826 = $53,087).
Staff added several str...
Click here for full text