File #: 18-01074    Version: 1 Name:
Type: Minute Order Status: Consent Agenda
File created: 3/26/2018 In control: City Council Meeting Agenda
On agenda: 4/23/2018 Final action:
Title: CC - 1) Acceptance of Work Performed by Sully-Miller Contracting Company; (2) Authorization to File a Notice of Completion; and (3) Authorization to Release the Retention Funds upon Expiration of the 35-Day Lien Period, for the 2017 Pavement Rehabilitation Project, PS-005 and Culver West Alexander Park Paddle Tennis Court Reconstruction PZ-835
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
title
CC - 1) Acceptance of Work Performed by Sully-Miller Contracting Company; (2) Authorization to File a Notice of Completion; and (3) Authorization to Release the Retention Funds upon Expiration of the 35-Day Lien Period, for the 2017 Pavement Rehabilitation Project, PS-005 and Culver West Alexander Park Paddle Tennis Court Reconstruction PZ-835

body
Meeting Date: April 23, 2018

Contact Person/Dept: Hong Wang/PW-Engineering

Phone Number: 310.253.5604

Fiscal Impact: Yes [X] No [] General Fund: Yes [X] No []

Public Hearing: [] Action Item: [] Attachments: []

Commission Action Required: Yes [] No [X] Date:

Public Notification: (E-Mail) Meetings and Agendas - City Council (04/18/18);

Department Approval: Charles D. Herbertson (04/10/18)
_____________________________________________________________________


RECOMMENDATION

Staff recommends the City Council (1) accept the work performed by Sully-Miller Contracting Company; (2) authorize filing a Notice of Completion; and (3) authorize the release of the retention funds after the expiration of the 35-day lien period, for the 2017 Pavement Rehabilitation Project, PS-005 and Culver West Alexander Park Paddle Tennis Court Reconstruction PZ-835.


BACKGROUND

In accordance with the recommendations of the pavement management system and visual observation, street segments were selected to be resurfaced with new asphalt pavement. The scope of work consists of removing and replacing 2 inches of deteriorated asphalt concrete pavement. Damaged curb and gutter were reconstructed as necessary. The following arterial and residential street segments were resurfaced:

1. Jefferson Blvd. - Overland Ave. to Sepulveda Blvd.
2. Sepulveda Blvd. - Centinela Blvd. To Green Valley Circle
3. Sepulveda Blvd. - Venice Blvd. to Washington Blvd. (localized repairs only)
4. Buckingham Pkwy - Hannum Ave. to Slauson Ave.
5. Slauson Ave. - Sepulveda Blvd. to Hannum Ave.
6. La Cien...